The transition is to
construct the second half of the Bus 87 bridge while maintaining a safe passage
for motorists and all construction personnel. The entrance ramp will also
undergo construction to complete its final configuration that will include a
longer merge lane for motorists entering I-10.
DETOUR:
The westbound entrance ramp traffic will utilize the westbound frontage road,
across the BUS-87 intersection (ALL-WAY STOP), then onto the next available
entrance ramp near SH-46.
WHEN:
The mainlane traffic switch will begin Tuesday July 5, 2022, at 9:00 PM,
weather permitting. Multiple nights may be required to complete the work
between the hours of 9 PM – 5 AM.
ADDITIONAL
INFORMATION: http://txdotsanantonio.blogspot.com/