Thursday, October 1

Full Closure of Loop 410 This Weekend in West San Antonio

 


This weekend, the Texas Department of Transportation (TxDOT) is scheduled to perform major closures in west San Antonio on I-410 and SH 151. The closures are expected to greatly impact traffic flow and drivers are encouraged to avoid the area. Details on the specific closures are listed below.

What:                          Full closure of all I-410 mainlanes from Marbach Rd. to Military Dr.

                                    Full closure of SH 151 eastbound frontage road from I-410 to Ingram
                                    Rd.

When:                         Friday, October 2 at 8 p.m. to Monday, October 5 at 5 a.m.

Scheduled Work:      Continued construction of flyover ramps and installation of steel beams

During the closure of I-410, drivers traveling northbound will be detoured to the frontage roads before the Marbach Road intersection and will be allowed to re-enter the mainlanes after the Military Drive intersection. Drivers traveling southbound on I-410 will be detoured to the frontage roads before Military Drive and will be allowed to re-enter the mainlanes after the Marbach Road intersection. Drivers traveling on the eastbound SH 151 frontage road will be detoured to the peripheral streets.

This weekend’s closures will allow crews to install steel beams for flyover ramps at the I-410 and SH 151 interchange as part of scheduled work in phase one of the I-410 Southwest project.  This project involves several improvements to improve mobility and enhance safety along a 14.9 mile stretch of I-410 from SH 16 to Ingram Rd. 

Phase one of the I-410 Southwest project has a total estimated cost of $100 million. Construction began in 2019 and is scheduled to be completed by Summer 2022. Williams Brother’s Construction is the contractor on the project.