Loop 1604 – North Central San Antonio
- Friday, October 9 until Saturday, October 10. Weekend continuous closure 9 p.m. until 10 a.m. Right lane westbound mainlane closure from Gold Canyon Road to Stone Oak Parkway for signage work. DETOUR: Take the Redland Road exit ramp and continue through the Gold Canyon Road and Redland Road intersections.
- Sunday, October 11 until Thursday, October 15. 9 p.m. to 5 a.m. Single lane closure on frontage road, in both directions, at the Bulverde Rd. intersection for pavement operations.
- Sunday, October 11 until Thursday, October 15. 9 p.m. to 5 a.m. Single lane closure on frontage road, in both directions, from Redland Rd. to Bulverde Rd. for pavement operations.
- Monday, October 12 until Friday, October 16. 9 a.m. to 4 p.m. Single lane closure on eastbound frontage road from Redland Rd. to Bulverde Rd. for pavement operations.
- Saturday, October 17 until Monday, October 19. Weekend continuous closure 2 a.m. until 5 a.m. Full eastbound mainlane closure from the Stone Oak Parkway entrance ramp to the Gold Canyon Road exit ramp for asphalt work. DETOUR: Use the Redland Road exit ramp and take the next turnaround.
- Saturday, October 17 until Monday, October 19. Weekend continuous closure 2 a.m. until 5 a.m. Full westbound mainlane closure from Gold Canyon Road to Stone Oak Parkway for asphalt work. DETOUR: Take the northbound US 281 exit ramp, go through the US 281 intersection and use the northbound US 281 entrance ramp west of Stone Oak Parkway.
- Saturday, October 17 until Monday, October 19. Weekend continuous closure 2 a.m. until 5 a.m. Alternating eastbound frontage road closure from the Stone Oak Parkway entrance ramp to the Gold Canyon Road exit ramp for asphalt work.
- Saturday, October 17 until Monday, October 19. Weekend continuous closure 2 a.m. until 5 a.m. Alternating westbound frontage road closure from Gold Canyon Road to Stone Oak Parkway for asphalt work.
- Tuesday, October 13 until Friday, October 16. 9 a.m. to 4:30 p.m. Alternating lane closures on eastbound frontage road from Bandera Rd. to Hausman Rd. to remove dams.
- Sunday, October 11 until Tuesday, October 12. 8 p.m. to 6 a.m. Full closure of mainlanes, in both directions, at Kitty Hawk Rd for structure installations.
- Tuesday, October 13 until Thursday, October 15. 5 p.m. to 5 a.m. Full closure of turnarounds, in both directions, at Pat Booker Rd. for bridge work.
- Tuesday, October 13 until Thursday, October 15. 8 p.m. to 5 a.m. Single lane closure of northbound frontage road from Pat Booker Rd. exit ramp to Pat Booker Rd. entrance ramp for bridge work.
- Tuesday, October 13 until Wednesday, October 15. 9 p.m. to 5 a.m. Singe lane closure of northbound mainlanes from Pat Booker Rd. exit ramp to Pat Booker Rd. entrance ramp for bridge work.
- Monday, October 12 until Thursday, October 22. Daily 8 a.m. to 5 p.m. Alternating lane closures, in both directions, from the Medina River to I-35 for road improvements.
- Friday, October 9 until Monday, October 12. Weekend continuous closure 9 p.m. until 5 a.m. Full southbound mainlane closure from Sonterra Boulevard to the Donella Drive entrance ramp to for asphalt work. DETOUR: Take the Sonterra Boulevard exit ramp, continue through the Loop 1604 and Donella Drive intersections and use the Donella Drive entrance ramp.
- Friday, October 9 until Monday, October 12. Weekend continuous closure 9 p.m. until 5 a.m. Full northbound mainlane closure from the Donella Drive entrance ramp to Sonterra Boulevard for asphalt work. DETOUR: Take the frontage road exit ramp near Donella Drive, continue through the interchange and use the Sonterra Boulevard entrance ramp.
- Friday, October 9 until Monday, October 12. Weekend continuous closure 9 p.m. until 5 a.m. Northbound frontage road closure of the north- to southbound turnaround at Evans Road for a traffic switch. DETOUR: Use the turnaround at Stone Oak/ Tournament Players Club (TPC) Parkway. Closure will not happen concurrently with other turnaround closures in the same direction.
- Friday, October 9 until Monday, October 12. Weekend continuous closure 9 p.m. until 5 a.m. Southbound frontage road closure of the south- to northbound turnaround at Evans Road for a traffic switch. DETOUR: Use the turnaround at Encino Rio. Closure will not happen concurrently with other turnaround closures in the same direction.
- Friday, October 9 until Monday, October 12. Weekend continuous closure 9 p.m. until 5 a.m. Left turn lane southbound frontage road closure at Evans Road both south- to eastbound turn lanes for a traffic switch. DETOUR: Use the turnaround at Encino Rio. Closure will not happen concurrently with the other turnaround closures in the same direction.
- Friday, October 9 until Monday, October 12. Weekend continuous closure 9 p.m. until 5 a.m. Left turn lane northbound frontage road closure at Evans Road both north- to westbound turn lanes for a traffic switch. DETOUR: Use the turnaround at Stone Oak/Tournament Players Club (TPC) Parkway. Closure will not happen concurrently with the other turnaround closures in the same direction.
- Saturday, October 10 until Monday, October 12. Weekend continuous closure 2 a.m. until 5 a.m. Alternating northbound mainlane closure from the Donella Drive entrance ramp to Evans Road for concrete paving.
- Saturday, October 10 until Monday, October 12. Weekend continuous closure 2 a.m. until 5 a.m. Alternating northbound frontage road closure from Loop 1604 to Redland Road.
- Saturday, October 10 until Monday, October 12. Weekend continuous closure 2 a.m. until 5 a.m. Alternating southbound frontage road from the Redland Road exit ramp to Loop 1604.
- Monday, October 12 until Friday, October 16. Nightly 9 p.m. until 5 a.m. Full southbound mainlane closure from Sonterra Boulevard to the Donella Drive entrance ramp to for asphalt work. DETOUR: Take the Sonterra Boulevard exit ramp, continue through the Loop 1604 and Donella Drive intersections and use the Donella Drive entrance ramp.
- Monday, October 12 until Friday, October 16. Nightly 9 p.m. until 5 a.m. Full northbound mainlane closure from the Donella Drive entrance ramp to Sonterra Boulevard for asphalt work. DETOUR: Take the frontage road exit ramp near Donella Drive, continue through the interchange and use the Sonterra Boulevard entrance ramp.
- Monday, October 12 until Friday, October 16. Nightly 9 p.m. until 5 a.m. Full northbound mainlane closure of the Sonterra Boulevard exit ramp for drainage work. DETOUR: Take the northbound US 281 frontage road exit ramp and go through the Loop 1604 intersection.
- Monday, October 12 until Friday, October 16. Nightly 9 p.m. until 5 a.m. Northbound frontage road closure of the north- to southbound turnaround at Encino Rio for concrete paving. DETOUR: Use the turnaround at Stone Oak/Tournament Players Club (TPC) Parkway. Closure will not happen concurrently with other turnaround closures in the same direction.
- Monday, October 12 until Friday, October 16. Nightly 9 p.m. until 5 a.m. Southbound frontage road closure of the south- to northbound turnaround at Encino Rio for concrete paving. DETOUR: Use the turnaround at Redland Road. Closure will not happen concurrently with other turnaround closures in the same direction.
- Monday, October 12 until Friday, October 16. Nightly 9 p.m. until 5 a.m. Alternating northbound mainlane closure from Sonterra Boulevard to Evans Road.
- Monday, October 12 until Friday, October 16. Nightly 9 p.m. until 5 a.m. Alternating northbound frontage road closure from Loop 1604 to Redland Road.
- Monday, October 12 until Friday, October 16. Nightly 9 p.m. until 5 a.m. Alternating southbound frontage road closure from the Sonterra Boulevard exit ramp to Loop 1604 for concrete paving.
- Monday, October 12 until Friday, October 16. Nightly 9 p.m. until 5 a.m. Alternating northbound frontage road closure from Encino Rio to Stone Oak/Tournament Players Club (TPC) Parkway for a concrete paving.
- Saturday, October 17 until Monday, October 19. Weekend overnight closure 2 a.m. until 5 a.m. Southbound mainlane closure of the south- to northbound turnaround at Evans Road for concrete paving. DETOUR: Use the turnaround at Encino Rio. Closure will not happen concurrently with other turnaround closures in the same direction.
- Saturday, October 17 until Monday, October 19. Weekend overnight closure 2 a.m. until 5 a.m. Northbound frontage road closure of the north- to southbound turnaround at Encino Rio for concrete paving. DETOUR: Use the turnaround at Stone Oak/Tournament Players Club (TPC) Parkway. Closure will not happen concurrently with other turnaround closures in the same direction.
- Saturday, October 17 until Monday, October 19. Weekend overnight closure 2 a.m. until 5 a.m. Northbound frontage road closure of the north- to southbound turnaround at Evans Road for concrete paving. DETOUR: Use the turnaround at Stone Oak/ Tournament Players Club (TPC) Parkway. Closure will not happen concurrently with other turnaround closures in the same direction.
- Saturday, October 17 until Monday, October 19. Weekend overnight closure 2 a.m. until 5 a.m. Southbound frontage road closure of the south- to northbound turnaround at Encino Rio for concrete paving. DETOUR: Use the turnaround at Redland Road. Closure will not happen concurrently with other turnaround closures in the same direction.
- Saturday, October 17 until Monday, October 19. Weekend overnight closure 2 a.m. until 5 a.m. Left turn lane southbound mainlane closure at Evans Road both south- to eastbound turn lanes for concrete paving. DETOUR: Use the turnaround at Encino Rio. Closure will not happen concurrently with the other turnaround closures in the same direction.
- Saturday, October 17 until Monday, October 19. Weekend overnight closure 2 a.m. until 5 a.m. Left turn lane northbound frontage road closure at Evans Road both north- to westbound turn lanes for concrete paving. DETOUR: Use the turnaround at Stone Oak/Tournament Players Club (TPC) Parkway. Closure will not happen concurrently with the other turnaround closures in the same direction.
- Saturday, October 17 until Monday, October 19. Weekend overnight closure 2 a.m. until 5 a.m. Left lane northbound frontage road closure from Encino Rio to Stone Oak /Tournament Players Club (TPC) Parkway for concrete paving.
- Saturday, October 17 until Monday, October 19. Weekend continuous closure 2 a.m. until 5 a.m. Alternating southbound mainlane closure from Sonterra Boulevard to the Donella Drive entrance ramp to for asphalt work.
- Friday, October 9 until Sunday, October 11. 9 p.m. to 5 a.m. Full closure of lanes in both directions at Wilderness Oak intersection for pavement work.
- Saturday, October 10 until Sunday, October 11. 6 p.m. to 5 a.m. Single lane closure on northbound mainlanes from Bulverde Rd. to Trinity Park for barrier movement.
- Monday, October 12 until Tuesday, October 13. 9 p.m. to 5 a.m. Full closure of lanes in both directions at Marshall Road intersection for bridge cap setting.
- Monday, October 12 until Tuesday, October 13. 9 p.m. to 5 a.m. Single lane closure of northbound mainlanes at Bulverde Road for traffic switch.
- Tuesday, October 13 until Wednesday, October 14. 9 p.m. to 5 a.m. Full closure of lanes in both directions at Wilderness Oak intersection for bridge cap setting.
- Wednesday, October 14 until Thursday, October 15. 9 p.m. to 5 a.m. Full closure of lanes in both directions at Bulverde Road intersection for bridge cap setting.
- Thursday, October 15 until Friday, October 16. 9 p.m. to 5 a.m. Full closure of lanes in both directions at Borgfeld Road intersection for bridge cap setting.
- Friday, October 16. 9 a.m. to 5 a.m. Full closure of lanes in both directions at Overlook Parkway intersection for bridge cap setting.
- Friday, October 9 until Monday, October 12. Weekend continuous closure 9 p.m. until 5 a.m. Alternating eastbound crossing closure of Evans Road to the east and west of US 281 for a traffic switch.
- Friday, October 9 until Monday, October 12. Weekend continuous closure 9 p.m. until 5 a.m. Alternating westbound crossing closure of Evans Road to the east and west of US 281 for a traffic switch.
- Monday, October 12 until Friday, October 16. Nightly 9 p.m. until 5 a.m. Full westbound crossing closure from westbound Encino Rio to southbound US 281 for concrete paving. DETOUR: Use the turnaround at Stone Oak/Tournament Players Club (TPC) Parkway.
- Saturday, October 17 until Monday, October 19. Weekend overnight closure 2 a.m. until 5 a.m. Full westbound crossing closure from westbound Encino Rio to southbound US 281 for concrete paving. DETOUR: Use the turnaround at Stone Oak/Tournament Players Club (TPC) Parkway.
- Current until Friday, October 16. Daily 9 a.m. to 3 p.m. Right lane and shoulder closure on eastbound mainlanes from Ralph Fair Road to La Cantera Parkway for work on concrete traffic rail.
- Friday, October 9 until Saturday October 10. 10 p.m. to 8 a.m. Full closure of westbound mainlanes from Boerne Stage Road to Ralph Fair Road for asphalt work.
- Sunday, October 11 until Friday, October 16. Nightly 9 p.m. to 6 a.m. Full closure of westbound mainlanes from Boerne Stage Road to Ralph Fair Road for asphalt work.
- Sunday, October 11 until Friday, October 16. Nightly 10 p.mm. to 8 a.m. Full closure of westbound mainlanes from Boerne Stage Road to Ralph Fair Road for asphalt work.
- Wednesday, October 14. 9 a.m. to 3 p.m. Full closure of eastbound entrance ramp at Ralph Fair Road for illumination pole installation.
- Wednesday, October 14. 9 a.m. to 3 p.m. Single lane closure of westbound frontage road from Camp Bullis Rd. to Dominion Dr. for equipment installation.
- Wednesday October 14 until Thursday, October 15. 9 p.m. to 6 a.m. Single lane closure of eastbound mainlanes from Old Fredericksburg Rd. to Ralph Fair Rd. for equipment installation.
- Thursday, October 15 until Friday, October 16. 9 p.m. to 6 a.m. Single lane closure of the eastbound mainlanes from Camp Bullis Rd. to La Cantera Parkway for equipment installation.
- Friday, October 16 until Saturday, October 17. 10 p.m. to 8 a.m. Full closure of westbound mainlanes from Boerne Stage Road to Ralph Fair Road for asphalt work.
- Saturday, October 10 from 6 a.m. to 7 p.m. Westbound right lane closed from Graytown Road to Loop 1604 for striping and traffic switch. Westbound entrance ramp from Graytown Road also closed. DETOUR: Use Loop 1604 entrance ramp to access westbound I-10 during ramp closure.
- Sunday, October 11 thru Tuesday, October 13 from 7 p.m. to 5 a.m. each night. Left lane closed in both directions between Loop 1604 and Graytown Road for barrier installation.
- Current until further notice. East and westbound I-10 frontage road traffic have right-of-way at Woodlake Parkway intersection. Woodlake traffic must stop before proceeding.
- Monday, October 12 until Wednesday, October 14. Eastbound entrance and exit ramps from FM 1516 to Loop 1604 closed for asphalt work.
- Monday, October 12 until Thursday, October 15. 7 a.m. to 8 p.m. Single lane closure of westbound mainlanes from US 183 to FM 2438 for armor joint work.
- Current until mid-November: Westbound I-10 exit ramp to Foster Road closed. DETOUR: Use Woodlake Parkway exit ramp.
- Current until late-October: Westbound I-10 entrance ramp from Ackerman Road closed. DETOURS:
- Southbound Ackerman traffic can travel south under the I-10 overpass, use the eastbound
frontage road to Foster Road, turn left on Foster, and take the westbound
frontage road to the westbound entrance ramp just west of Foster.
- Northbound Ackerman traffic can use the eastbound frontage road to Foster Road, turn
left on Foster, and take the westbound frontage road to the westbound entrance
ramp just west of Foster.
- Current until further notice. Graytown Road bridge at I-10. DETOURS: Graytown Road traffic will use the frontage roads and the Pfeil Road underpass or Loop 1604 turnaround to cross I-10.
- Current until further notice. Eastbound entrance ramp from FM 1516. DETOUR: Take next entrance ramp east of Loop 1604.
- Current until further notice. Eastbound entrance ramp from Foster Road. DETOUR: Take next entrance ramp east of Woodlake Parkway.
- Until further notice, the southbound entrance ramp at Schwab Rd. is closed.
- Monday, October 12 until Wednesday, October 14. 9 p.m. to 5 a.m. Double lane closure on northbound mainlanes from Hubertus Rd. to Schwab Rd. for barrier removal.
- Monday, October 5 until Monday, October 12. 9 a.m. to 3 p.m. Alternating lane closures on frontage road, in both directions, from Marbach Rd. to Ingram Rd. for retaining wall work.
- Monday, October 5 until Monday, October 12. 9 a.m. to 3 p.m. Alternating mainlane closures, in both directions, from Marbach Rd. to Culebra Rd. for concrete pouring.
- Monday, October 5 until Monday, October 12. 8 p.m. to 5 a.m. Alternating lane closures on frontage road, in both directions, from Marbach Rd. to Ingram Rd. for bridge work.
- Monday, October 5 until Monday, October 12. 8 p.m. to 5 a.m. Alternating full closures of mainlanes, in both directions, from Marbach Rd. to Military Dr. for work on steel beams.
- Monday, October 5 until Monday, October 12. 8 a.m. to 5 p.m. Full closure of southbound frontage road from N.W. Crossroads Rd. to Military Dr. for beam setting.
- Monday, October 12 until Monday, October 19. 9 a.m. to 3 p.m. Alternating lane closures on frontage road, in both directions, from Marbach Rd. to Ingram Rd. for retaining wall work.
- Monday, October 12 until Monday, October 19. 9 a.m. to 3 p.m. Alternating mainlane closures, in both directions, from Marbach Rd. to Culebra Rd. for concrete pouring.
- Monday, October 12 until Monday, October 19. Alternating lane closures on frontage road, in both directions, from Marbach Rd. to Ingram Rd. for bridge work.
- Monday, October 12 until Monday, October 19. 8 p.m. to 5 a.m. Alternating full mainlane closures, in both directions, from Marbach Rd. to Military Dr. for bent work.
- Monday, October 12 until Monday, October 19. 8 a.m. to 5 p.m. Full closure of southbound frontage road from N.W. Crossroads to Military Dr. for beam setting.
- Tuesday, October 13 until Monday, October 19. 8 p.m. to 5 a.m. Alternating lane closures on northbound frontage road from Marbach Rd. to Ingram Rd. for bridge work.
- Monday, October 12 until Monday, October 19. 8 p.m. to 5 a.m. Alternating full mainlane closures, in both directions, from Marbach Rd. to Culebra Rd. for welding on steel beams.
- Sunday, October 11 until Friday, October 23. 7:30 p.m. to 6 a.m. Alternating lane closures, in both directions, from W. Military Dr. to S.W. 36th St. for milling and paving improvements.
- Monday, October 12 until
Friday, October 23. 9 a.m. to 3 p.m. Alternating lane closures, in both
directions, from W. Military Dr. to S.W. 36th St. for guardrail and
concrete improvements.
SH 151 – West
San Antonio
- Monday, October 5 until Monday, October 12. 9 a.m. to 3 p.m. Single mainlane closures, in both directions, from Ingram Rd. to Loop 410 for bent work.
- Monday, October 5 until Monday, October 12. 9 a.m. to 3 p.m. Alternating lane closures on frontage road, in both directions, from Loop 410 to Ingram Rd. for bent work.
- Monday, October 5 until Monday, October 12. 8 p.m. to 5 a.m. Full closure of eastbound frontage road from Loop 410 to Ingram Rd. for bridge work.
- Monday, October 12 until Monday, October 19. 9 a.m. to 3 p.m. Alternating mainlanes closures, in both directions, from Ingram Rd. to Loop 410 for construction of flyover ramps.
- Monday, October 12 until Monday, October 19. 8 p.mm. to 5 a.m. Full closure of eastbound frontage road from Loop 410 to Ingram Rd. for bridge widening.
- Friday, October 16 until Monday, October 19. 8 p.m. to 5 a.m. Full closure of mainlanes, in both directions, from Ingram Rd. to Loop 410 for construction of flyover ramps.
- City of San Antonio/PWD closure for Hardberger Park
Land Bridge project.
Friday, October 9 until Monday, October 12. 9 p.m. to 5 a.m. Full closure, in
both directions, from N.W. Military Hwy. (FM 1535) to Blanco Rd. (FM 2696) for
bridge work.
SH 218 – Pat Booker Road
- Tuesday, October 13 until Wednesday, October 14. 9 p.m. to 5 a.m. Full closure of all lanes, in both directions, from just east of Village Oak Dr. to just west of Athenian Dr. for road improvements.
- Current until further notice. Daily 7 a.m. until 7 p.m. Alternating southbound lanes between Woodlake Parkway and Gibbs Sprawl Road for barrier/pavement work (existing seven total lanes narrowed to three, with one in each direction and a two-way turn lane in the middle).
- Current until further notice. Full-day closure. Southbound lane between Toepperwein Road and Walzem Road for barrier setting work and road rehab work.
SH 46 – Boerne/Kendall County
- Current until further notice. 9 p.m. until 5 a.m. Eastbound left lane from East Sharon Drive to Charger Boulevard for traffic switch (drivers diverted to the right side for construction access on the right side; left turn lane remains open).
- Monday, October 5 until Saturday, October 10. 7 a.m. to 7 p.m. Single lane closure, in both directions, from US 87 to 0.5 miles past Wasp Creek Road for culvert work and roadway reconstruction.
I-10 – Kerr County
- None scheduled.
- Current until Friday, October 30. 6:30 a.m. to 7 p.m. Alternating lane closures, in both directions, from FM 539 to SH 123 for pavement improvements.
SL 337 – Comal County
- None scheduled.
RM 32 – Comal County
- Current until Saturday, October 31. 6:30 a.m. to 7 p.m. Single eastbound lane closures from FM 484 to Carpers Creek for roadway improvements.