Monday, November 14

THIS week's construction-related closures

Sorry this is late to post! We missed getting some closures posted that occurred this weekend, and we sincerely apologize. If you got caught in traffic at the I-410-Hwy 151 interchange yesterday, or on US 90 on the west side of town, we're sorry.
Our crews and contractors are working hard to get as much work as they can finished before December 15; we don't allow them any major closures between December 15 and January 2. We'll also keep off the road next week during Thanksgiving (Thursday-Sunday) to make sure everyone can get to their destinations relatively easily.
At any rate, here's a look at what we've got:

I-10 – Boerne
  • Monday-Friday, November 14-18. 9 p.m. until 5 a.m. nightly. Eastbound main lanes at Scenic Loop Road. The left lane will close while crews repair the retaining wall. 
  • Sunday-Wednesday, November 20-23. 9 p.m. until 5 a.m. nightly. Eastbound main lanes at Scenic Loop Road. The left lane will close while crews repair the retaining wall. 
  • Sunday, November 27-Friday, December 2. 9 p.m. until 5 a.m. nightly. Westbound main lanes at Scenic Loop Road. The left lane will close while crews repair the retaining wall. 
I-10 – Leon Springs
  • Tuesday-Wednesday, November 15-16. 7:30 p.m. until 5 a.m. Eastbound frontage road between Ralph Fair Road and Boerne Stage Road. The right lane will close while crews move barrier. 
I-10 – East San Antonio
  • Monday-Wednesday, November 14-16. 7 p.m. until 5 a.m. nightly. Eastbound frontage roads at Foster Road. Alternating lanes will close while crews install concrete barrier. 
I-35 – New Braunfels
  • Tuesday-Friday, November 15-18. 7 a.m. until 6 p.m. daily. Southbound frontage road between the Hays County line and FM 306. The right lane will close while crews repair asphalt. 
  • Thursday-Monday, November 17-21. 9 a.m. until 3 p.m. daily. Northbound main lanes at Alligator Creek. The right shoulder will close while crews work on guardrail. 
I-35 – Northeast San Antonio
  • Sunday-Friday, November 13-18. 9 p.m. until 5 a.m. nightly. Northbound exit to westbound I-410. Alternating lanes will close while crews do overhead bridge work. Traffic will exit Walzem and continue along the frontage road to reach I-410. 
  • Sunday-Friday, November 13-18. 9 p.m. until 5 a.m. nightly. Main lanes, both directions, between Rittiman and Walzem roads. Alternating lanes will close while crews do road work. 
  • Sunday-Friday, November 13-18. 9 p.m. until 5 a.m. nightly. Frontage roads, both directions, between Rittiman and Walzem. Alternating lanes will close while crews do road work. 
  • Monday-Friday, November 14-18. 9 a.m. until 3:30 p.m. daily. Frontage roads, both directions, between Rittiman and Walzem roads. Alternating lanes will close while crews do road work. 
I-35 – East San Antonio
  • Sunday-Friday, November 13-18. 9 p.m. until 5 a.m. nightly. Northbound main lanes between AT&T Center Parkway and Binz-Engleman. Alternating lanes will close while crews do finish work. 
  • Monday-Friday, November 14-18. 9 a.m. until 3 p.m. daily. Northbound frontage road between AT&T Center Parkway and Binz-Engleman. The left lane will close while crews do finish work. 
I-410 – Northeast San Antonio
  • Sunday-Friday, November 13-18. 9 p.m. until 5 a.m. nightly. Eastbound exit ramp to Randolph Boulevard and the city of Windcrest. The ramp will close while crews do bridge work. Traffic will exit Thousand Oaks, turn around and return to Randolph Boulevard to reach its destination. 
I-410 – East San Antonio
  • Current through Friday, December 2. Southbound main lanes over North WW White. The right lane will close while crews repair damaged bridge rail. 
I-410 – Northwest San Antonio
  • Current until May 2017. Northbound exit ramp to Culebra Road. The ramp will remain closed while crews reconstruct the main lanes and frontage road and construct a new ramp. Traffic will exit Ingram Road, turn around and return to Culebra to reach its destination.
  • Tuesday-Friday, November 15-18. 9 p.m. until 5 a.m. nightly. Southbound frontage road at Hwy 151. All lanes will close while crews do overhead bridge work. Traffic will head west on Hwy 151, turn around at Ingram Road and return to I-410 to reach its destination. 
US Hwy 281 – Central San Antonio
  • Sunday-Friday, November 13-18. 9 p.m. until 6 a.m. nightly. Main lanes, both directions, between Airport and Josephine. Alternating lanes will close while crews do bridge work. This closure includes ramps as needed. Traffic will follow the posted detour route. 
  • Monday-Friday, November 14-18. 11 a.m. until 3 p.m. daily. Main lanes, both directions, between I-35 and I-410. Alternating lanes will close while crews work on guardrail. This closure includes ramps as needed. Traffic will follow the posted detour route. 
Hwy 151 – Northwest San Antonio
  • Current until December 2016. Westbound exit ramp to Ingram and Potranco roads. The ramp will remain closed while crews install bridge support structures for the direct connector ramps being constructed. 
  • Tuesday-Friday, November 15-18. 9 p.m. until 5 a.m. nightly. Eastbound main lanes at I-410. All lanes will close while crews set overhead bridge support beams. Traffic will exit I-410, follow the frontage road and use the next available ramp. 
Other roads – Seguin
  • Current until Saturday, December 31. 9 a.m. until 4 p.m. daily. King Street, both directions, between Cedar Street and US 90. All lanes will close while crews install storm drains and rebuild the road. Traffic will use Hwy 123 as a detour. 
Other roads – Boerne
  • Sunday-Friday, November 13-18. 9 p.m. until 5 a.m. nightly. Scenic Loop Road, both directions, at I-10. Traffic will be reduced to one-way, controlled by off-duty officers while crews do roadwork. 
  • Thursday-Friday, November 17-18. 9 p.m. until 5:30 a.m. Hwy 46, both directions, between Amman Road and Cinco Lane. Alternating lanes will close while crews lay asphalt. 
  • Sunday-Wednesday, November 20-23. 9 p.m. until 5:30 a.m. nightly. Hwy 46, both directions, between Amman Road and Cinco Lane. Alternating lanes will close while crews lay asphalt. 
Other roads – Northeast San Antonio
  • Sunday-Friday, November 13-18. 9 p.m. until 5 a.m. nightly. Randolph Boulevard, both directions, at I-35. All lanes will close while crews do overhead bridge work. Traffic will turn right onto the frontage road and turn around at the next available intersection to reach its destination. 
Other roads – East Bexar County
  • Sunday-Friday, November 13-18. 7 p.m. until 6 a.m. nightly. Westbound WW White between East Houston Street and Fairlawn Ave. The right lane will close while crews resurface the road. 
Other roads – Northwest San Antonio
  • Current until Wednesday, November 30. 8:30 p.m. until 5 a.m. nightly. Eastbound Bandera Road between Grissom and Tezel roads. Alternating lanes will close while crews repair the road. 
  • Current until Monday, December 5. 9 p.m. until 5 a.m. nightly. Military Drive, both directions, at I-410. All lanes will close while crews do overhead bridge work. Traffic will turn right onto the frontage roads and turn around at the next intersection to reach its destination. 
All closures are pending weather.