Friday, August 17

Next week's construction-related closures

I-35 – Northeast San Antonio 
  • Monday, August 20 until Friday, August 24. 9 a.m. until 3 p.m. Various mainlanes and exit ramps on both directions at I-410 will be closed for cleaning inlets and manholes and illumination work. 
I-10 – West San Antonio
  • Current until Monday, September 10. 7 a.m. until 5 p.m. Westbound left frontage road lane between La Cantera Parkway and Rim Drive will be closed for traffic barrier placement. 
  • Monday, August 20, 9 a.m. until 3 p.m. Westbound left lane between Dominion Drive and Exit 551 will be closed for ingress and egress of concrete trucks. 
I-410 – West San Antonio
  • Current and continuous until December 2018. Turnarounds, both directions, at Marbach Road. The turnarounds will remain closed while crews construct the new Marbach overpass bridge. Traffic will use the signalized intersection. 
  • Current and continuous until December 2018. Northbound exit ramp to Marbach. The ramp will remain closed while crews reconstruct the road. Traffic will exit US Hwy 90 and continue along the frontage road to reach its destination. 
SH 16 (Bandera Road) – West San Antonio
  • Current until December 2018. 24 hour closure. The westbound to eastbound Loop 1604 turnaround will be closed for modification of the turnaround as part of the operational improvements. 
  • Monday, August 20 until Friday, August 24. 9 p.m. until 5 a.m. Alternating lanes on both directions between Quincey Lee to Legend Trail will be closed for striping and concrete traffic barrier work. 
US 90 – West San Antonio
  • Sunday, August 19 until Wednesday, August 22. 9 p.m. until 5 a.m. Two westbound mainlanes between I-35 to General Hudnell Drive will be closed for pavement repair work. 
  • Friday, August 24 until Saturday, August 25. 9 p.m. until 5 a.m. The westbound to eastbound turnaround at Loop 1604 will be closed for direct connector deck pour work. DETOUR: Traffic will need to drive through the intersection to turnaround. 
Loop 1604 – West San Antonio
  • Thursday, August 23 until Friday, August 24. 9 p.m. until 5 a.m. The southbound left frontage road lane between Military Drive to Westcreek Oaks Drive will be closed for metal beam guard fence work. 
U.S. Hwy 281 – Far North San Antonio
  • Saturday, August 18. 2 a.m. until 7 p.m. All southbound frontage road lanes between Sonterra Boulevard entrance ramp and Loop 1604 westbound frontage road will be closed for setting beams. DETOUR: Traffic will need to take the Sonterra Boulevard entrance ramp; use the Donella Drive exit ramp; take the Donella Drive turnaround and turn left on the westbound frontage road. 
  • Saturday, August 18. 8 a.m. until 5 p.m. The westbound left lane at Encino Rio will be closed for median curb work. 
  • Sunday, August 19 until Tuesday, August 21, 9 p.m. until 5 a.m. The northbound right mainlane between Encino Commons and TPC Parkway will be closed for restriping work. 
  • Sunday, August 19 until Tuesday, August 21. 9 p.m. until 5 a.m. The westbound left lane at TPC Parkway will be closed for restriping work. 
  • Monday, August 20 until Thursday, August 23. 9 p.m. until 5 a.m. All southbound frontage road lanes between Sonterra Boulevard entrance ramp and Loop 1604 westbound frontage road will be closed for direct connector work. DETOUR: Traffic will need to take the Sonterra Boulevard entrance ramp; use the Donella Drive exit ramp; take the Donella Drive turnaround and turn left on the westbound frontage road. 
  • Monday, August 20 until Friday, August 24. 9 p.m. until 5 a.m. The southbound left and center mainlanes between Sonterra Boulevard entrance ramp and Donella Drive exit ramp will be closed for direct connector work. 
  • Monday, August 20 until Friday, August 24. 9 p.m. until 5 a.m. The northbound left and center mainlanes between Donella Drive entrance ramp and Sonterra Boulevard exit ramp will be closed for direct connector work. 
  • Monday, August 20 until Saturday, August 25. 9 p.m. until 5 a.m. The southbound right frontage road lane between Sonterra Boulevard exit ramp and Sonterra Boulevard entrance ramp will be closed for installing delineators and pylons. 
  • Monday, August 20 until Saturday, August 25. 9 p.m. until 5 a.m. The westbound left lane at Encino Commons Boulevard will be closed for restriping work. 
  • Monday, August 20 until Sunday, August 26. 9 p.m. until 5 a.m. The northbound right and center lanes between Donella Drive and Sonterra Boulevard will be closed for retaining wall demolition. DETOUR: Traffic will use the Frontage Road exit near Donella Drive. Continue down the frontage road and reenter the highway at Sonterra Boulevard. 
  • Wednesday, August 22 until Friday, August 24. 9 p.m. until 5 a.m. The northbound right lane between Sonterra Boulevard entrance and exit ramps will be closed for direct connector work. DETOUR: Use Frontage Road exit ramp. 
Loop 1604 – North San Antonio
  • Saturday, August 18. 2 a.m. until 7 p.m. All westbound frontage road lanes between the US 281 southbound frontage and Stone Oak Parkway exit ramp will be closed for setting beams. DETOUR: Traffic will need to take the turnaround at US 281; continue west and take the Redland Road turnaround; use the Redland Road entrance ramp; and take the exit ramp to Stone Oak Parkway. 
  • Monday, August 20 until Tuesday, August 21. 9 p.m. until 5 a.m. Alternating westbound mainlanes between Huebner Road and Bitters Road will be closed for concrete traffic barrier work. 
  • Tuesday, August 21 until Wednesday, August 22. 9 p.m. until 5 a.m. Alternating eastbound mainlanes between Bitters Road and Huebner Road will be closed for concrete traffic barrier work. 
  • Wednesday, August 22 until Thursday, August 23. 9 p.m. until 5 a.m. Alternating westbound frontage road at Huebner Road will be closed for low profile concrete traffic barrier work. 
  • Thursday, August 23 until Friday, August 24. 9 p.m. until 5 a.m. Alternating eastbound frontage road at Huebner Road will be closed for low profile concrete traffic barrier work. 
  • Friday, August 24 until Saturday, August 25. 9 p.m. until 5 a.m. Alternating westbound frontage road at Bitters Road will be closed for low profile concrete traffic barrier work. 
State Highway 151 – West San Antonio
  • Sunday, August 19 until Friday August 31. 8 p.m. until 5 a.m. Alternating westbound frontage road lanes between Castroville Road and Pinn Road will be closed for inlay and paving work. 
  • Monday, August 20 until Friday, August 24. 9 a.m. until 4 p.m. Alternating westbound frontage road lanes between Castroville Road and Pinn Road will be closed for installing metal beam guard fence. 
I-10 - Boerne
  • Sunday, August 19 until Wednesday, August 22. 9 p.m. until 5 a.m. The right eastbound mainlane between 1 mile south of Fair Oaks Parkway and .4 miles north of Ralph Fair Road will be closed for relocating traffic barrier. 
  • Sunday, August 19 until Monday, August 20. 9 p.m. until 5 a.m. The right westbound mainlane between .1 mile north of Ralph Fair Road and .1 mile south of Fair Oaks Parkway will be closed for relocating traffic barrier. 
  • Monday, August 20 until Tuesday, August 21. 9 p.m. until 5 a.m. The right eastbound mainlane between .1 mile south of Fair Oaks Parkway and 1.8 miles north of Ralph Fair Road will be closed for relocating traffic barrier. 
  • Monday, August 20 until Tuesday, August 21. 9 p.m. until 5 a.m. The right eastbound mainlane between 1 mile south of Fair Oaks Parkway and 1.8 miles north of Ralph Fair Road will be closed for relocating traffic barrier. 
  • Thursday, August 23 until Friday, August 24. 9 p.m. until 5 a.m. The right mainlane on both directions between .1 mile south of Fair Oaks Parkway and .1 mile south of north of Ralph Fair Road will be closed for relocating traffic barrier. 
I-10 - Kerrville
  • Sunday, August 19 until Wednesday, August 22. 8 p.m. until 5 a.m. Eastbound exit and entrance ramps at Exit 508 between FM 1338 (Goat Creek Road) and SH 16 will be closed for milling and paving operations. DETOUR: Traffic will exit to Harper Road (Exit 505). 
  • Monday, August 20 until Friday, August 24. 7 a.m. until 7 p.m. Alternating westbound mainlanes between FM 1338 (Goat Creek Road) and SH 16 will be closed for guardrail and pavement work. 
  • Monday, August 20 until Tuesday, August 21. 8 a.m. until 5 p.m. Eastbound exit ramps at Exit 501 between FM 1338 (Goat Creek Road) and SH 16 will be closed for installing mowstrip under the metal beam guard fence. DETOUR: Traffic will exit to Harper Road (Exit 505). 
  • Monday, August 20 until Friday, August 24. 8 p.m. until 5 a.m. Westbound exit and entrance ramps at Exit 508 between FM 1338 (Goat Creek Road) and SH 16 will be closed for a milling and paving operation. DETOUR: Traffic will exit to Harper Road (Exit 505). 
Other roads – San Antonio
  • Monday, August 20 until Friday, August 24. 9 p.m. until 5 a.m. The center lane on both directions of FM 1957 (Potranco Road) between Leopard Claw and Rousseau Road will be closed for mill and overlay work. 
Other roads – Helotes
  • Current and continuous until Friday, September 28. Northbound SH 16 at FM 1560. The left turn lane will close while crews do road work. No left turns will be permitted. Traffic will continue to the next intersection and turn around to reach its destination. Cross traffic from Circle A is also blocked. 
  • Current until October 2018, 9 a.m. until 5 p.m. The intersection on both directions on SH 16 at Circle A Trail will be closed for center median work. 
  • Monday, August 20 until Friday, August 24. 9 a.m. until 3 p.m. Alternating lanes on both directions on SH 16 between ¼ mile south and ¼ north of Circle A Trail will be closed for hot mix work. 
  • Monday, August 20 until Friday, August 24. 9 a.m. until 3 p.m. Alternating lanes on both directions on FM 1560 between Riggs Road and City Hall will be closed for hot mix work. 
Other roads – Atascosa County
  • Current until September 1. 7 a.m. until 8 p.m. Various northbound mainlanes on I-37 between Atascosa/Live Oak County Line and just north of US 281A for base repair work.

All closures are pending weather


Thursday, August 16

Updates on setting beams at US 281 and Loop 1604 interchange

There will be a major closure for this Saturday, August 18, 2018 from 2 a.m. to 7 p.m. that will require full closures for both US 281 and Loop 1604 frontage roads.

For most of the working shift, crews will require a full closure along southbound frontage road and, then early afternoon, the crews will move onto the westbound frontage road. See details for closures below.

US 281 southbound frontage road from the Sonterra Boulevard entrance ramp to the westbound frontage road of Loop 1604 that includes the following detour: taking the Sonterra Boulevard entrance ramp, using Donella Drive exit ramp, taking the Donella Drive turnaround and taking a left onto the westbound frontage road.
Loop 1604 westbound frontage road from the southbound frontage road of US 281 to the Stone Oak Parkway exit ramp that includes the following detour: taking the turnaround at US 281, heading west and take the Redland Road turnaround, using the Redland Road entrance ramp, and taking the exit ramp to Stone Oak Parkway.

A look ahead for next weekend...
Work for the following weekend will include closing the center and right lane of northbound US 281 from Donella entrance ramp to Sonterra Blvd. entrance ramp (includes closing the Sonterra Blvd. exit ramp) from Saturday (August 25, 2018) at 3 a.m. to Monday (August 27, 2018) at 5 a.m. Traffic to use the Frontage Rd. exit ramp.
You can receive information on lane closures straight to your e-mail inbox by registering here (link to http://eepurl.com/cXz2kr). Daily updates are sent out daily for the full closures.

Tuesday, August 14

What is happening at Fair Oaks Parkway???

Here's the scoop..as you are aware, the intersection at Fair Oaks Parkway at I-10 is not in its final configuration but once complete, many of the concerns we have heard will be addressed.

As of now, motorists will not be using the current right turn from the westbound frontage road to go onto Fair Oaks Parkway, but motorists will have their own designated right turn lane. Lanes will be 12' wide when completed which is the same width as the mainlanes. The final overlay starts today. We just ask for a little patience while we get through the final leg of the project.

Also, the turning movement on the north side of the interstate will be eliminated with the next project that has already let. The next project, which is anticipated to begin this fall, will convert the frontage roads from Fair Oaks Parkway to Scenic Loop to one-way. However, the anticipated lane shift will allow for traffic to make the left turn onto Fair Oaks Parkway.


Friday, August 10

Next week's construction-related closures

I-35 – Northeast San Antonio
  • Monday, August 13 until Tuesday, August 14. 9 a.m. until 3 p.m. Various mainlanes and exit ramps on both directions at I-410 will be closed for cleaning inlets and manholes and illumination work. 

I-410 – West San Antonio
  • Current and continuous until December 2018. Turnarounds, both directions, at Marbach Road. The turnarounds will remain closed while crews construct the new Marbach overpass bridge. Traffic will use the signalized intersection. 
  • Current and continuous until December 2018. Northbound exit ramp to Marbach. The ramp will remain closed while crews reconstruct the road. Traffic will exit US Hwy 90 and continue along the frontage road to reach its destination. 
  • Current until Friday, August 17. 9 p.m. until 5 a.m. Alternating frontage road lanes in both directions between SH 151 and Ingram Road will be closed for overlay work. The Culebra Road and Military Road exits will both be closed. DETOUR FOR NORTHBOUND: For Military Drive, traffic will detour SH 151 eastbound frontage road to westbound Military Drive to access I-410 northbound. For Culebra Road, traffic will take the Military entrance ramp then exit Ingram and take the turnaround back to Culebra Road. DETOUR FOR SOUTHBOUND: For Military Drive, traffic will take Culebra Road westbound to southbound Potranco Road and travel to Military Drive and take a left. For SH 151, traffic will take westbound Military Drive to Potranco Road, take a left at Potranco Road to travel to SH 151 westbound frontage road. 

SH 16 (Bandera Road) – West San Antonio
  • Current until December 2018. 24 hour closure. The westbound to eastbound Loop 1604 turnaround will be closed for modification of the turnaround as part of the operational improvements. 

US 90 – West San Antonio
  • Current until Thursday, August 16. 24 hour closure. The eastbound left frontage road lane between the new entrance ramp to just west of Medio Creek bridge is closed for barrier work. 
  • Friday, August 10 until Saturday, August 11 and Sunday, August 12 until Monday, August 13. 9 p.m. until 5 a.m. The westbound mainlanes between ½ mile west of southbound Loop 1604 and ½ east of northbound Loop 1604 for direct connector deck pour work. DETOUR: Traffic will exit Loop 1604, detour through US 90 westbound frontage road and re-enter at the next entrance ramp. 
  • Friday, August 17 until Saturday, August 18. 9 p.m. until 5 a.m. The westbound to eastbound turnaround will be closed for direct connector deck pour work. 

Loop 1604 – West San Antonio
  • Monday, August 13 until August 17. 9 a.m. until 3 p.m. Alternating lanes in both directions on FM 1957 (Potranco Road) will be closed for installing temporary overhang brackets and shoring for bridge deck slab work. 
  • Monday, August 13 until August 17. 9 a.m. until 3 p.m. Alternating lanes in both directions on Military Drive will be closed for installing temporary overhang brackets and shoring for bridge deck slab work. 
  • Monday, August 13 until August 17. 9 a.m. until 3 p.m. Alternating lanes in both directions on Wiseman Boulevard will be closed for installing temporary overhang brackets and shoring for bridge deck slab work. 

U.S. Hwy 281 – Far North San Antonio

  • Monday, August 13 until Thursday, August 16. 9 p.m. until 5 a.m. All mainlanes on the southbound frontage road between Sonterra Boulevard entrance ramp and Loop 1604 westbound frontage road will be closed for direct connector work. DETOUR: Traffic will need to take the Sonterra Boulevard entrance ramp; use the Donella Drive exit ramp; take the Donella Drive turnaround and turn left on the westbound frontage road. 
  • Monday, August 13 until Friday, August 17. 9 p.m. until 5 a.m. The southbound left and center mainlanes between Sonterra Boulevard entrance ramp and Donella Drive exit ramp will be closed for direct connector work. 
  • Monday, August 13 until Friday, August 17. 9 p.m. until 5 a.m. The northbound left and center mainlanes between Donella Drive entrance ramp and Sonterra Boulevard exit rampwill be closed for direct connector work. 
  • Monday, August 13 until Friday, August 17. 9 p.m. until 5 a.m. The northbound right mainlane between Encino Commons and TPC Parkway will be closed for restriping work. 
  • Monday, August 13 until Friday, August 17. 9 p.m. until 5 a.m. The southbound left turn lane at Stone Oak Parkway/TPC Parkway will be closed for restriping work. DETOUR: Traffic will use the next turn around and take a right on TPC Parkway. 
  • Monday, August 13 until Friday, August 17. 9 p.m. until 5 a.m. The southbound right mainlane between Redland Road and Sonterra Boulevard exit ramp will be closed for restriping work. DETOUR: Traffic will use the Donella Drive exit and take the turnaround at Donella Drive. 
  • Monday, August 13 until Friday, August 17. 9 p.m. until 5 a.m. The southbound left mainlane between Sonterra Boulevard exit ramp and Sonterra Boulevard will be closed for installing delineators and pylons. 
  • Monday, August 13 until Friday, August 17. 9 p.m. until 5 a.m. The eastbound right lane at TPC Parkway will be closed for restriping work. 
  • Monday, August 13 until Friday, August 17. 9 p.m. until 5 a.m. The westbound left lane at TPC Parkway will be closed for restriping work. 
  • Wednesday, August 15 until Friday. 9 p.m. until 5 a.m. The northbound right mainlane between Sonterra Boulevard exit ramp and Sonterra Boulevard entrance ramp will be closed for direct connector work. DETOUR: Use the frontage road exit ramp. 
Other roads – Boerne
  • Sunday, August 12 until Monday, August 13, 9 p.m. until 5 a.m. The right mainlane on westbound I-10 between Schools Street on the westbound entrance ramp to Frederick Creek will be closed for single slope barrier work. 
Other roads – Converse
  • Current until Friday, August 17. 24 hour closure. Two lanes on westbound FM 1516 closed at School Street for pavement work on School Street. 
Other roads – Helotes
  • Current and continuous until Friday, September 28. Northbound Bandera Road at FM 1560. The left turn lane will close while crews do road work. No left turns will be permitted. Traffic will continue to the next intersection and turn around to reach its destination. Cross traffic from Circle A is also blocked. 
  • Current until October 2018, 9 a.m. until 5 p.m. The intersection on both directions on SH 16 at Circle A Trail will be closed for center median work. 
  • Monday, August 13 until Friday, August 17. 9 p.m. until 5 a.m. Alternating lanes on both directions on SH 16 between ¼ mile south and ¼ north of Circle A Trail will be closed for mill/inlay work. 
Other roads – Kerrville
  • Monday, August 6 until Friday, August 10. 7 a.m. until 7 p.m. Alternating mainlanes on both directions between FM 1338 (Goat Creek Road) and SH 16 will be closed for guardrail work. 
  • Monday, August 6 until Tuesday, August 7. 8 a.m. until 5 p.m. Eastbound exit and entrance ramps at Exit 508 between FM 1338 (Goat Creek Road) and SH 16 will be closed for a moving operation. DETOUR: Traffic will exit to Harper Road (Exit 505). 
  • Wednesday, August 8. 8 a.m. until 5 p.m. Westbound exit and entrance ramps at Exit 508 between FM 1338 (Goat Creek Road) and SH 16 will be closed for a moving operation. DETOUR: Traffic will exit to Harper Road (Exit 505). 
Other roads – Atascosa County
  • Monday, August 6 until September 1. 7 a.m. until 8 p.m. Various northbound mainlanes between Atascosa/Live Oak County Line and just north of US 281A for base repair work. 
All closures are pending weather


Friday, August 3

Next week's construction-related closures

I-35 – Northeast San Antonio
  • Monday, August 6 until Tuesday, August 7. 9 a.m. until 3 p.m. The northbound exit ramp to Eisenhauer Road will be closed for cleaning inlets and manholes.
  • Monday, August 6 until Wednesday, August 8. 9 a.m. until 3 p.m. The northbound left lane between the I-410 southbound split to the new I-410 southbound bridge will be closed for illumination work.
I-410 – Northeast San Antonio
  • Wednesday, August 8. 9 a.m. until 3 p.m. The northbound right lane to I-35 northbound will be closed for cleaning inlets and manholes.
I-410 – West San Antonio
  • Current and continuous until December 2018. Turnarounds, both directions, at Marbach Road. The turnarounds will remain closed while crews construct the new Marbach overpass bridge. Traffic will use the signalized intersection. 
  • Current and continuous until December 2018. Northbound exit ramp to Marbach. The ramp will remain closed while crews reconstruct the road. Traffic will exit US Hwy 90 and continue along the frontage road to reach its destination. 
  • Sunday, August 5 until Thursday, August 9. 8 p.m. until 5 a.m. All southbound mainlanes between the exit ramp (Marbach Road) to US 90 will be closed bridge panel work. DETOUR: Traffic will exit to the frontage road and enter the highway after US 90. 
  • Sunday, August 5 until Thursday, August 9. 9 a.m. until 3:30 p.m. The left southbound frontage road lane between the entrance ramp to I-410 and Marbach Road will be closed for concrete work. 
  • Sunday, August 5 until Friday, August 17. 9 p.m. until 5 a.m. Alternating frontage road lanes in both directions between SH 151 and Ingram Road will be closed for overlay work. The Culebra Road and Military Road exits will both be closed. DETOUR FOR NORTHBOUND: For Military Drive, traffic will detour SH 151 eastbound frontage road to westbound Military Drive to access I-410 northbound. For Culebra Road, traffic will take the Military entrance ramp then exit Ingram and take the turnaround back to Culebra Road. DETOUR FOR SOUTHBOUND: For Military Drive, traffic will take Culebra Road westbound to southbound Potranco Road and travel to Military Drive and take a left. For SH 151, traffic will take westbound Military Drive to Potranco Road, take a left at Potranco Road to travel to SH 151 westbound frontage road. 
SH 16 (Bandera Road) – West San Antonio
  • Monday, August 6 until December 2018. 24 hour closure. The westbound to eastbound Loop 1604 turnaround will be closed for modification of the turnaround as part of the operational improvements. 
US 90 – West San Antonio
  • Current until Thursday, August 16. 24 hour closure. The eastbound left frontage road lane between the new entrance ramp to just west of Medio Creek bridge is closed for barrier work.
  • Sunday, August 5 until Thursday, August 8. The eastbound frontage road between Loop 1604 and I-410 will be close for storm sewer installation work. DETOUR: Traffic will be detoured to the Military Drive turnaround.
Loop 1604 – West San Antonio
  • Saturday, August 4. 6 a.m. until 6 p.m. All lanes in both directions on Wiseman Boulevard between the south and northbound frontage roads and alternating southbound mainlanes between SH 151 and Critical Habitat Unit will be closed will be closed for a traffic switch on southbound Loop 1604.
  • Monday, August 6. 9 a.m. until 3 p.m. The right southbound mainlane between Westcreek Oaks Drive to Potranco Road for handrail installation work.
  • Monday, August 6 until Friday, August 10. 9 p.m. until 5 a.m. Alternating northbound mainlanes between SH 151 and Wiseman Boulevard will be closed for concrete barrier work. 
  • Monday, August 6 until Friday, August 10. 9 p.m. until 5 a.m. All lanes on FM 1957 (Potranco Road) in both directions under Loop 1604 and the left turns in both directions on Loop 1604 will be closed for bridge deck work.
U.S. Hwy 281 – Far North San Antonio
  • Friday, August 3 until Monday, August 6. 8 p.m. until 5 a.m. All lanes in both directions of Redland Road at the intersection will be closed for intersection work. DETOUR: Traffic will used Ridgewood Parkway and Sonterra Boulevard.
  • Saturday, August 4. 2 a.m. until 7 p.m. All northbound frontage road lanes between Loop 1604 and Sonterra Boulevard exit ramp will be closed for setting beams. 
  • Sunday, August 5 until Monday, August 6. 9 p.m. until 5 a.m. The southbound right mainlane between Encino Rio Road and Sonterra Boulevard exit ramp will be closed for OSB removal. DETOUR: Traffic will use the Donella Drive exit; take the turnaround; turn left on the westbound frontage road and exit at Sonterra Boulevard. 
  • Monday, August 6 until Friday, August 10. 9 p.m. until 5 a.m. Alternating northbound mainlanes between Sonterra Boulevard entrance and exit ramp will be closed for restripe and temporary barrier work. DETOUR: Traffic will use the Donella Drive exit.
  • Monday, August 6 until Friday, August 10. 9 p.m. until 5 a.m. The southbound left lane between Redland Road and Sonterra Boulevard will be closed for setting temporary barrier. 
  • Monday, August 6 until Friday, August 10. 9 p.m. until 5 a.m. The northbound left turn lane at Stone Oak Parkway will be closed for median work.
  • Monday, August 6 until Friday, August 10. 9 p.m. until 5 a.m. All southbound frontage road lanes between Sonterra Boulevard entrance ramp and Loop 1604 westbound frontage road will be closed for direct connector work. DETOUR: Traffic will take the Sonterra Boulevard entrance ramp; use the Donella Drive exit; take the Donella Drive turnaround; and turn left on to the westbound frontage road.
  • Monday, August 6 until Friday, August 10. 9 p.m. until 5 a.m. The northbound right mainlane between Sonterra Boulevard exit and entrance ramp will be closed for direct connector work. DETOUR: Traffic will use the frontage road exit ramp.
  • Monday, August 6 until Friday, August 10. 9 p.m. until 5 a.m. The east and westbound left turn lane at Stone Oak Parkway will be closed for median work.
  • Tuesday, August 6 until Friday, August 10. 9 p.m. until 5 a.m. The left and center southbound mainlane between Sonterra Boulevard entrance ramp to Donella Drive exit ramp will be closed for direct connector work.
  • Tuesday, August 6 until Friday, August 10. 9 p.m. until 5 a.m. The left and center northbound mainlane between Donella Drive entrance ramp to Sonterra Boulevard exit ramp will be closed for direct connector work.
I-10 – East San Antonio
  • Tuesday, August 7 until Thursday, August 9. 9 a.m. until 3 p.m. Eastbound left mainlane between Foster Road exit ramp and Woodlake Parkway will be closed for culvert crossing work. 
Other roads – Boerne
  • Monday, July 23 until Friday, August 10. 7 a.m. until 7 p.m. Alternating lanes in both directions of FM 474 between Guadalupe River to 7 miles south of the Guadalupe River for base repair work.
Other roads – Converse
  • Current until Friday, August 17. 24 hour closure. Two lanes on westbound FM 1516 closed at School Street for pavement work on School Street. 
Other roads – Helotes
  • Current and continuous until Friday, September 28. Northbound Bandera Road at FM 1560. The left turn lane will close while crews do road work. No left turns will be permitted. Traffic will continue to the next intersection and turn around to reach its destination. Cross traffic from Circle A is also blocked. 
Other roads – Kerrville
  • Monday, August 6 until Friday, August 10. 7 a.m. until 7 p.m. Alternating mainlanes on both directions between FM 1338 (Goat Creek Road) and SH 16 will be closed for guardrail work. 
  • Monday, August 6 until Tuesday, August 7. 8 a.m. until 5 p.m. Eastbound exit and entrance ramps at Exit 508 between FM 1338 (Goat Creek Road) and SH 16 will be closed for a moving operation. DETOUR: Traffic will exit to Harper Road (Exit 505).
  • Wednesday, August 8. 8 a.m. until 5 p.m. Westbound exit and entrance ramps at Exit 508 between FM 1338 (Goat Creek Road) and SH 16 will be closed for a moving operation. DETOUR: Traffic will exit to Harper Road (Exit 505).
Other roads – Atascosa County
  • Monday, August 6 until September 1. 7 a.m. until 8 p.m. Various northbound mainlanes between Atascosa/Live Oak County Line and just north of US 281A for base repair work.
All closures are pending weather

Updates on setting beams at US 281 and Loop 1604 interchange

Work continues to set beams at the US 281/Loop 1604 interchange. Tomorrow (Saturday, August 4, 2018) from 2 a.m. to 7 p.m. there will be a full closure for both US 281 and Loop 1604 frontage road. Most of the work will take place along the Loop 1604 westbound frontage road and, then early afternoon, the crews will move onto the US 281 northbound frontage road. See details for closures below.

Loop 1604 westbound frontage road from Gold Canyon Drive to US 281 - DETOUR: Take a double left at Gold Canyon Drive and then a double left a Redland Road. Take the Redland Road entrance ramp and exit at Stone Oak Parkway. Take the turnaround at Stone Oak Parkway and turnaround at US 281. 
US 281 northbound frontage road from Loop 1604 to Sonterra Boulevard exit ramp - DETOUR: Head south on the US 281 frontage road and take the turnaround at Donella Drive, enter US 281 and exit at Sonterra Boulevard.
You can receive information on lane closures straight to your e-mail inbox by registering here (link to http://eepurl.com/cXz2kr). Daily updates are sent out daily for the full closures.

Thursday, August 2

Update on Loop 1604 construction

If you hadn't noticed by now, there is quite a bit of construction on the northwest side of Loop 1604. Here's an update on some changes and closures you need to know about. We apologize for the inconvenience. We understand that no one likes construction. But we are trying our best to get these projects completed and traffic flowing. We appreciate your patience greatly!

Loop 1604 - Culebra Road to Potranco Road
If you are not a follower of TxDOTSanAntonio on Twitter you missed a tour of a traffic switch scheduled for this Saturday between 6 a.m. and 12 noon on Loop 1604 SB between Culebra Road and Military Drive. Have no fear, you can check out the video here.

Loop 1604 - Potranco Road to US 90
Tonight we do have a full mainlane closure at the interchange of Loop 1604 at US 90 for a deck pour for the southbound/eastbound direct connector. The closure starts at 9 p.m. and will wrap up by 5 a.m. DETOUR: Northbound traffic will have take a right onto the eastbound frontage road and then enter US 90 eastbound mainlanes; continue on US 90 to the Military Drive exit and take the turnaround and re-enter the US 90 westbound mainlanes and exit Loop 1604 and take a right onto the Loop 1604 northbound mainlanes.

Loop 1604 at SH 16 (Bandera Road)
The westbound frontage road turnaround will be closed starting on Monday, August 6th at 5 a.m.  This closure will be approximately 4 months in duration. The turnaround is being closed to allow for modification of the turnaround as part of the current project that will provide intersection operational improvements at this busy intersection by utilizing an innovative traffic engineering solution described as Displaced Left Turns (DLT). In a DLT, left turn traffic shifts to the left side of the road. Left turns are “displaced” at a new crossover signal prior to the frontage road intersection.  

Landa Street at Loop 337 Closure

TxDOT and its contractor Hunter Industries will close the intersection of Landa Street at Loop 337 in New Braunfels to place pre-cast bents for the bridge over Landa Street starting tonight at 9 p.m. until Friday morning at 5 a.m.

Road signs have been placed to alert drivers of the upcoming closure. TxDOT asks the traveling public to adhere to construction signage and remain aware when traveling through the work zone.

The $43.3 million project consists of expanding Loop 337 to a four-lane divided highway between Hillcrest Drive and Altgelt Lane and will be completed by the end of 2021.