Friday, November 30

UPCOMING CONSTRUCTION-RELATED CLOSURES

**ALL CLOSURES WEATHER PERMITTING**

I-10 – East San Antonio
  • Current until further notice. Eastbound entrance ramp from FM 1516. DETOUR: Take next entrance ramp east of Loop 1604.
  • Current until 4/30/19. Alternating eastbound mainlanes from SH 130 to US 183 for milling and inlay work.
  • Current until further notice. Daily 7:30 a.m. until 6 p.m. Eastbound entrance ramp from FM 1516. DETOUR: Take next entrance ramp east of Loop 1604.
  • Saturday, December 1. 7 a.m. until 5 p.m. Eastbound right mainlane from Woodlake to FM 1516 for drainage work.
  • Saturday, December 1. 5 a.m. until 9 p.m. Alternating eastbound and westbound mainlanes in various locations between I-410 and Loop 1604 for installation of portable concrete traffic barriers.
  • Sunday, December 2 until Friday, December 7. Nightly 9 p.m. until 5 a.m. Left eastbound mainlane between I-410 and Foster Road for installation of portable concrete traffic barriers. 
  • Sunday, December 2 until Friday, December 7. Nightly 9 p.m. until 5 a.m. Left westbound mainlane between FM 1516 and Martinez Creek, and between Foster Road and I-410 for installation of portable concrete traffic barriers. 
  • Saturday, December 8. 5 a.m. until 9 p.m. Left eastbound mainlane between I-410 and Foster Road for installation of portable concrete traffic barriers. 
  • Saturday, December 8, 5 a.m. until 9 p.m. Left westbound mainlane between FM 1516 and Martinez Creek, and between Foster Road and I-410 for installation of portable concrete traffic barriers. 
I-10 – West San Antonio
  • Saturday, December 1. 7 a.m. until 5 p.m. Eastbound right mainlane from Camp Bullis Road to La Cantera Parkway for placing asphalt.
  • Saturday, December 1. 7 a.m. until 5 p.m. Westbound right mainlane from Camp Bullis Road to La Cantera Parkway for placing asphalt.
  • Monday, December 3 until Tuesday, December 4. 9 p.m. until 5 a.m. Alternating westbound mailanes from Ralph Fair Road to Fair Oaks Parkway for striping work.
  • Monday, December 3 until Friday, December 7. Nightly 9 p.m. until 5 a.m. Alternating eastbound & westbound mainlanes from Frederick Creek to US 87 for barrier installation work.
  • Monday, December 3 until Thursday, December 6. Nightly 9 p.m. until 5 a.m. Eastbound right mainlane from Camp Bullis Road to La Cantera Parkway for placing barrier removal work.
  • Tuesday, December 4 until Friday, December 5. 9 p.m. until 5 a.m. Alternating westbound mainlanes from Ralph Fair Road to Fair Oaks Parkway for striping work.
  • Tuesday, December 4 until Thursday, December 6. Nightly 9 p.m. until 5 a.m. Right mainlane and shoulder in both directions from Balcones Creek to Fair Oaks Boulevard.
  • Thursday, December 6 until Friday, December 7. 9 p.m. until 5 a.m. Alternating eastbound mainlanes from Fair Oaks Parkway to Ralph Fair Road for striping work.
  • Monday, December 10 until Friday, December 14. Nightly 9 p.m. until 5 a.m. Westbound right mainlane from Camp Bullis Road to La Cantera Parkway for barrier removal work.
  • Friday, December 7 until Monday, December 10. Nightly 9 p.m. until 5 a.m. Right westbound mainlane from Parkway Drive to US 87 for shoulder work.
  • Monday, December 10 until Friday, December 14. Nightly 9 p.m. until 5 a.m. Alternating westbound mainlanes from US 87 to Frederick Creek for barrier installation work.
  • Monday, December 17 until Friday, December 21. Nightly 9 p.m. until 5 a.m. Alternating westbound mainlanes from US 87 to Frederick Creek for barrier installation work.
I-410 – West San Antonio
  • Sunday, December 2 until Friday, December 14. Daily 8 p.m. until 5 a.m. Full northbound mainlane and frontage road closure from US 90 to Marbach to install light poles.
  • Sunday, December 2 until Friday, December 14. Daily 8 p.m. until 5 a.m. Full southbound mainlane and frontage road closure from US 90 to Valley Hi for overhang removal and direct connector work.
  • Monday, December 3 until Thursday, December 3. Daily 9 a.m. until 3 p.m. Northbound left frontage road lane from Landing Avenue to Bronco Lane for curb work.
Loop 1604 – West San Antonio
  • Saturday, December 1. 9 p.m. until 5 a.m. Alternating southbound mainlanes from Potranco Road to US 90 for paving, striping and barrier work.
  • Monday, December 3 until Friday, December 7. Daily 9 a.m until 3 p.m. Northbound right mainlaine from Reed Road to Military Drive for curb and sidewalk work.
  • Sunday, December 2 until Friday, December 7. Nightly 9 p.m. until 5 a.m. Westbound frontage road from Bandera Road to La Cantera Parkway for milling and paving work.
  • Sunday, December 2 until Friday, December 7. Nightly 9 p.m. until 5 a.m. Westbound frontage road from I-10 to Roger’s Ranch Road for milling and paving work.
  • Monday, December 3 until Friday, December 7. Daily 9 a.m. until 3 p.m. Westbound frontage road from Lockhill Selma to Bandera for guardrail and mow strip work.
Loop 1604 – North San Antonio
  • Saturday, December 1 until Monday, December 3. Nightly 3 a.m. until 5 a.m. Full closure of eastbound mainlanes from US 281 northbound exit ramp to northbound-eastbound direct connector entrance ramp for setting steel girders.
  • Saturday, December 1 until Monday, December 3. Nightly 3 a.m. until 5 a.m. US 281 northbound exit ramp for direct connector work.
  • Saturday, December 1 until Monday, December 3. Nightly 3 a.m. until 5 a.m. Full closure of westbound mainlanes from US 281 northbound exit ramp to US 281 entrance ramp for direct connector work.
  • Saturday, December 1 until Monday, December 3. Nightly 3 a.m. until 5 a.m. Full closure of westbound frontage road from Gold Canyon Road to US 281 northbound frontage road for direct connector work.
  • Monday, December 3 until Friday, December 7. Nightly 9 p.m. until 5 a.m. Full closure of eastbound mainlanes from US 281 northbound exit to direct connector entrance to set steel girders. DETOUR: Use Gold Canyon Road entrance.
  • Monday, December 3 until Friday, December 7. Nightly 9 p.m. until 5 a.m. Full closure of westbound frontage road from Sonterra Boulevard exit to Sonterra Boulevard entrance for direct connector work.
  • Saturday, December 8 until Monday, December 10. Nightly 2 a.m. until 5 a.m. Full closure of westbound frontage road from Gold Canyon Road to US 281 northbound frontage road for direct connector work.
Loop 1604 – South San Antonio
  • Sunday, December 2 until Monday, December 3. Nightly 9 p.m. until 5 a.m. Westbound left frontage road lane from Golden Corral to SH 16 for striping work.
  • Sunday, December 2 until Monday, December 3. Nightly 9 p.m. until 5 a.m. Both directions at SH 16 turnaround for striping work.
Loop 1604 – Northeast San Antonio
  • Sunday, December 2 until Friday, December 7. Nightly 9 p.m. until 5 a.m. Southbound right mainlane from Pat Booker Road to Kitty Hawk for barrier and lighting work.
  • Monday, December 3 until Friday, December 7. Nightly 9 p.m. until 5 a.m. Southbound Pat Booker Road entrance ramp for lighting work.
US 281 – North San Antonio
  • Saturday, December 1 until Monday, December 3. Nightly 3 a.m. until 5 a.m. Full northbound mainlane closure from Frontage Road to Sonterra Boulevard for direct connector work.
  • Saturday, December 1 until Monday, December 3. Nightly 3 a.m. until 5 a.m. Full southbound mainlane closure from Sonterra Boulevard exit to Loop 1604 westbound frontage road for direct connector work.
  • Saturday, December 1 until Monday, December 3. Nightly 3 a.m. until 5 a.m. Northbound Sonterra Boulevard exit ramp for direct connector work.
  • Saturday, December 1 until Monday, December 3. Nightly 3 a.m. until 5 a.m. Southbound Sonterra Boulevard entrance ramp for retaining wall demolition work.
  • Monday, December 3 until Friday, December 7. Nightly 9 p.m. until 5 a.m. Northbound Sonterra Boulevard exit ramp for direct connector work.
  • Monday, December 3 until Wednesday, December 5. Nightly 9 p.m. until 5 a.m. Full northbound frontage road closure from Frontage Road to Sonterra Boulevard for direct connector work.
  • Monday, December 3 until Friday, December 7. Nightly 9 p.m. until 5 a.m. Southbound Sonterra Boulevard entrance ramp for retaining wall demolition work.
  • Tuesday, December 4 until Friday, December 7. Nightly 9 p.m. until 5 a.m. Full southbound mainlane closure from Sonterra Boulevard exit ramp to Sonterra Boulevard entrance ramp for moving stockpile work.
  • Wednesday, December 5 until Friday, December 7. Nightly 9 p.m. until 5 a.m. Full northbound mainlane closure from Frontage Road to Sonterra Boulevard for direct connector work.
  • Wednesday, December 5 until Friday, December 7. Nightly 9 p.m. until 5 a.m. Full northbound frontage road closure from Loop 1604 eastbound frontage road to Loop 1604 westbound frontage road for direct connector work.
  • Saturday, December 8 until Monday, December 10. Nightly 2 a.m. until 5 a.m. Full northbound frontage road closure from Frontage Road to Sonterra Boulevard for direct connector work.
  • Saturday, December 8 until Monday, December 10. Nightly 3 a.m. until 5 a.m. Northbound Sonterra Boulevard exit ramp for direct connector work.
  • Saturday, December 8 until Monday, December 10. Nightly 3 a.m. until 5 a.m. Southbound Sonterra Boulevard entrance ramp for retaining wall demolition work.
US 281 – Central San Antonio
  • Tuesday, December 4. 9 a.m. until 12 p.m. Left northbound mainlane and shoulder from Stadium Drive to Hildebrand Avenue for survey work.
US 90 – West San Antonio
  • Current until Saturday, December 1. 10 p.m. until 7 a.m. Westbound frontage road from I-410 to Horal Street for direct connector work.
  • Sunday, December 2 until Friday, December 14. Nightly 8 p.m. until 5 a.m. Full closure of eastbound mainlanes from Ray Ellison Drive to I-410 for direct connector work. DETOUR: Traffic diverted onto frontage road.
  • Sunday, December 2 until Monday, December 15. Nightly 8 p.m. until 5 a.m. Full closure of westbound mainlanes and frontage road from I-410 to Horal Street for direct connector work.
I-37 – South Region
  • Monday, December 3 until Friday, February 1. Daily 7 a.m. until 8 p.m. Northbound mainlanes from Atascosa/Live Oak county line to approximately one mile north of US 281A for laying asphalt and bridge joint work.
  • Tuesday, December 4 until Wednesday, December 5. Daily 9 a.m. until 5 p.m. Northbound right mainlane at Atascosa River for concrete rail work.
SH 16 – Bandera Road
  • Sunday, December 2 until Friday, December 7. Nightly 9 p.m. until 5 a.m. Alternating northbound lanes from HEB to Legend Trail for curb work.
  • Sunday, December 2 until Friday, December 7. Nightly 9 p.m. until 5 a.m. Alternating southbound lanes from Legend Trail to Chili’s for curb work.
Loop 1346 – E. Houston St.
  • Monday, December 3 until Saturday, December 8. Daily 9 a.m. until 4 p.m. Westbound right lane from Flora to WW White for sidewalk and driveway work.
US 87 – Rigsby Road
  • Monday, December 3 until Saturday, December 8. Daily 9 a.m. until 4 p.m. Eastbound right lane from Bonair to WW White for sidewalk and driveway work.
  • Monday, December 3 until Saturday, December 8. Daily 9 a.m. until 4 p.m. Eastbound right lane from Kaiser Road to I-410 for sidewalk and driveway work.
FM 1957 – Potranco Road
  • Tuesday, December 4 until Friday, December 7. Daily 9 p.m. until 5 a.m. Both directions at Loop 1604 for bridge work.
Other roads – Bexar County
  • Current until Friday, December 21. Nightly 9 p.m. until 5 a.m. Both directions of Kilmarnoch Lane from Bonny Brae Lane to Loop 1604 for construction work.
  • Current until Saturday, December 15. Daily 9 a.m. until 5 p.m. Both directions of Reed Road between Copperfield Road to Loop 1604 northbound for road work.
  • Saturday, December 8 until Monday, December 10. Nightly 3 a.m. until 5 a.m. Westbound and eastbound Encino Commons at US 281 for drainage work.
  • Sunday, December 2 until Friday, December 7. Nightly 9 p.m. until 5 a.m. Ackerman Road closed at I-10 East for overpass construction. DETOUR: Northbound traffic will be diverted to the I-10 frontage road and use the turnaround at Foster Road; southbound traffic will go to the I-10 westbound mainlanes and exit at WW White Road to turn around

Traffic counts to be collected on SH 16 (Bandera Road)

Where are the cars coming from and where are they going on SH 16 (Bandera Road) between I-410 and Loop 1604? These are questions that the Texas Department of Transportation (TxDOT) is answering as the agency kicks off a new study to review possible improvements along SH 16 (Bandera Road) between I-410 and Loop 1604. 

Traffic counting equipment and survey crews will be seen along the corridor starting in December 2018. 

TxDOT is working closely with officials from the cities of Leon Valley and San Antonio to study congestion within the project corridor. Earlier this year, the City of San Antonio announced plans to study land use and economic development opportunities along SH 16 (Bandera Road) in a separate effort as part of the SA Tomorrow Corridor Plan. 

According to the Texas A&M Transportation Institute, the 6.5-mile stretch of SH 16 (Bandera Road) between I-410 and Loop 1604 is the 8th most congested road in the region and one of the top 100 most congested in the State of Texas. 

For ongoing TxDOT project updates, community members are invited to email their names and contact information to BanderaRoad@pozcam.com or contact the TxDOT Public Information Office at Laura.Lopez@txdot.gov or (210) 615-5839.

Monday, November 26

Newly-Scheduled Post-Thanksgiving Week Closures

**WEATHER PERMITTING**

Please take note of these additional scheduled closures for this week:

I-37 -- South San Antonio/Bexar County
  • Thursday, November 28. 12 a.m. to 3 p.m. Southbound right shoulder at US 181 (Exit 132/Floresville) for sign maintenance work.
  • Thursdsay, November 28. 9 a.m. to 12 p.m. Southbound right sholder at I-410 (Exit 133) for sign maintenance work.
US 90 -- West San Antonio
  • Current until Friday, November 29. 9 a.m. to 3 p.m. daily. Westbound left frontage road lane from Horal Street to Hunt Lane for retaining wall work.
Loop 1604 -- Far West San Antonio
  • Current until Saturday, December 15. Alternating southbound frontage road lanes from Dove Canyon to Red Musket for paving, striping and median construction work.



Wednesday, November 21

US 281 Expansion Project Long-term Closure

Starting Tuesday morning, November 27, the Sonterra Boulevard entrance ramp on US 281 southbound will be closed for several weeks (until at least early 2019) in order to construct a new realigned ramp, new retaining wall and drainage work related to the new direct connector between Loop 1604 westbound and US 281 southbound (see illustration below).



As always, all scheduled work is weather permitting and may need to be adjusted accordingly

Interesting in receiving email updates on the US 281 expansion project? Sign up here to get messages straight into your inbox: http://eepurl.com/cXz2kr).

UPCOMING CONSTRUCTION-RELATED CLOSURES

**WEATHER PERMITTING**

I-10 – East San Antonio
  • Monday, November 26 until Friday, November 30. 9 a.m. until 3 p.m. Eastbound right mainlane from Woodlake to FM 1516 for drainage work. 
  • Monday, November 26 until Friday, November 30. 9 p.m. until 5 a.m. Alternating eastbound and westbound mainlanes in various locations between I-410 and Loop 1604 for installation of portable concrete traffic barriers and pavement striping. 
  • Saturday, December 1. 7 a.m. until 5 p.m. Eastbound right mainlane from Woodlake to FM 1516 for drainage work. 
  • Saturday, December 1. 5 a.m. until 9 p.m. Alternating eastbound and westbound mainlanes in various locations between I-410 and Loop 1604 for installation of portable concrete traffic barriers. 
  • Current until further notice. Eastbound entrance ramp from FM 1516. DETOUR: Take next entrance ramp east of Loop 1604. 
I-10 – West San Antonio
  • Tuesday, November 27 until Thursday, November 29. 9 p.m. until 5 a.m. Right mainlane and shoulders in both directions from Balcones Creek to Fair Oaks Boulevard for road repair work. 
  • Wednesday, November 28 until Friday, November 30. 9 a.m. until 3 p.m. Full closure of westbound frontage road and Boerne Stage Road (exit ramp and road) for bridge work. DETOUR: Use Ralph Fair Road and Dominion Drive as alternative exits. 
  • Sunday, December 2 until Wednesday, December 5. 9 p.m. until 5 a.m. Right mainlane in both directions from Camp Bullis Road to La Cantera Parkway for concrete barrier removal work. 
  • Monday, December 3 until Friday, December 7. 9 p.m. until 5 a.m. Alternating eastbound mainlanes from Frederick Creek to US 87 for barrier installation work. 
  • Monday, December 3 until Friday, December 7. 9 p.m. until 5 a.m. Alternating westbound mainlanes from US 87 to Frederick Creek for barrier installation work. 
  • Friday, December 7 until Monday, December 10. 9 p.m. until 5 a.m. Right westbound mainlane from Parkway Drive to US 87 for shoulder work. 
  • Monday, December 10 until Friday, December 14. 9 p.m. until 5 a.m. Alternating westbound mainlanes from US 87 to Frederick Creek for barrier installation work. 
  • Monday, December 17 until Friday, December 21. 9 p.m. until 5 a.m. Alternating westbound mainlanes from US 87 to Frederick Creek for barrier installation work. 
I-410 – West San Antonio
  • Monday, November 26 until Friday, November 30. 9 a.m. until 3 p.m. Northbound right turn lane at Marbach Road for electrical work. 
  • Monday, November 26 until Friday, November 30. 9 a.m. until 3 p.m. Northbound left frontage road lane from Landing Avenue to Bronco Lane for curb work. 
  • Monday, November 26 until Friday, November 30. 8 p.m. until 5 a.m. Northbound alternating mainlane and frontage road closure from US 90 to Marbach to remove overhangs and direct connector work. 
  • Monday, November 26 until Friday, November 30. 8 p.m. until 5 a.m. Southbound alternating mainlane and frontage road closure from US 90 to Valley Hi for overhang removal and direct connector work. 
Loop 1604 – West San Antonio
  • Current until Saturday, December 1. 9 p.m. until 5 a.m. Alternating southbound mainlanes from Potranco Road to US 90 for paving, striping and barrier work. 
  • Monday, November 26 until Friday, November 30. 9 a.m. until 3 p.m. Northbound right mainlane from Military Drive to Kilmarnoch Lane for curb reconstruction work. 
Loop 1604 – North San Antonio.
  • Monday, November 26 until Friday, November 30. 9 p.m. until 5 a.m. Full closure of eastbound mainlanes from US 281 North exit ramp to northbound-eastbound direct connector entrance ramp for setting steel girders. 
  • Monday, November 26 until Friday, November 30. 9 p.m. until 5 a.m. Westbound US 281 northbound exit ramp for direct connector work. 
  • Monday, November 26 until Friday, November 30. 9 p.m. until 5 a.m. Full closure of westbound mainlanes from US 281 northbound exit ramp to US 281 entrance ramp for direct connector work. 
  • Monday, November 26 until Friday, November 30. 9 p.m. until 5 a.m. Full closure of westbound frontage road from Gold Canyon Road to US 281 northbound frontage road for direct connector work. 
  • Saturday, December 1 until Monday, December 3. 3 a.m. until 5 a.m. Full closure of eastbound mainlanes from US 281 northbound exit ramp to northbound-eastbound direct connector entrance ramp for setting steel girders. 
  • Saturday, December 1 until Monday, December 3. 3 a.m. until 5 a.m. US 281 northbound exit ramp for direct connector work. 
  • Saturday, December 1 until Monday, December 3. 3 a.m. until 5 a.m. Full closure of westbound mainlanes from US 281 northbound exit ramp to US 281 entrance ramp for direct connector work. 
Loop 1604 – South San Antonio
  • Sunday, November 25 until Friday, November 30. 9 p.m. until 5 a.m. Westbound left mainlane from Golden Corral to Jim’s Restaurant for barrier removal work. 
  • Sunday, November 25 until Friday, November 30. 9 p.m. until 5 a.m. Eastbound left mainlane from Chili’s to HEB for barrier removal work. 
Loop 1604 – East San Antonio
  • Monday, November 26 until Friday, November 30. 9 p.m. until 5 a.m. Southbound right mainlane and frontage road entrance ramp to mainlanes from Pat Booker Road to Kitty Hawk for barrier work.
US 281 – North San Antonio
  • Monday, November 26 until Friday, November 30. 9 p.m. until 5 a.m. Northbound Sonterra Boulevard exit ramp for direct connector work. 
  • Monday, November 26 until Friday, November 30. 9 p.m. until 5 a.m. Alternating northbound mainlanes from TPC Parkway to Marshall Road to barrier and striping work. 
  • Monday, November 26 until Friday, November 30. 9 p.m. until 5 a.m. Southbound Sonterra Boulevard entrance ramp for retaining wall demolition work. DETOUR: Continue southbound through Loop 1604 intersection and take Donella Drive entrance ramp. 
  • Monday, November 26 until Friday, November 30. 9 p.m. until 5 a.m. Southbound center frontage road lane from Sonterra Boulevard to Loop 1604 for striping work. 
  • Tuesday, November 27 until Thursday, November 29. 9 p.m. until 5 a.m. Northbound left mainlane from Donella Drive to Sonterra Boulevard for direct connector work. 
  • Tuesday, November 27 until Thursday, November 29. 9 p.m. until 5 a.m. Southbound left mainlane from Sonterra Boulevard to Loop 1604 for direct connector work. 
  • Saturday, December 1 until Monday, December 3. 3 a.m. until 5 a.m. Northbound Sonterra Boulevard exit ramp for direct connector work. 
  • Saturday, December 1 until Monday, December 3. 3 a.m. until 5 a.m. Southbound Sonterra Boulevard entrance ramp for retaining wall demolition work. DETOUR: Continue southbound through Loop 1604 intersection and take Donella Drive entrance ramp. 
US 90 – West San Antonio
  • Monday, November 26 until Friday, November 30. 8 p.m. until 5 a.m. Full closure of westbound mainlanes and frontage road from I-410 to Horal Street for bridge work. 
  • Monday, November 26 until Friday, November 30. 8 p.m. until 5 a.m. Full closure of eastbound mainlanes and frontage road from Ray Ellison Drive to I-410 for eastbound-northbound direct connector work. 
I-37 – South Region
  • Current until November 30. 7 a.m. until 8 p.m. Northbound main lanes from Atascosa/Live Oak county line to approximately one mile north of US 281A for guard rail work. 
I-35 – Central San Antonio
  • Wednesday, November 28. 8 a.m. until 11 p.m. Right frontage road lane from southbound exit 182 to Marigold Way for beam work. 
  • Wednesday, November 28 until Sunday, November 30. 8:30 p.m. until 6 a.m. Full southbound mainlane closure from FM 1103 exit ramp to FM 1103 entrance ramp for bridge work. 
SH 16 – Bandera Road
  • Sunday, November 25 until Friday, November 30. 9 p.m. until 5 a.m. Two northbound lanes from Academy to 7-11 for barrier removal work. 
  • Sunday, November 25 until Friday, November 30. 9 p.m. until 5 a.m. Southbound left-turn lane from Cooter Brown to Chili’s for barrier removal work. 
Loop 345 – Fredericksburg Road
  • Current until Friday, November 23. 9 a.m. to 3 p.m. Right lane in both directions from Callaghan Road to Medical Drive for sidewalk and driveway work. 
Other roads – Bexar County
  • Current until Friday, December 21. 9 p.m. until 5 a.m. Both directions of Kilmarnoch Lane from Bonny Brae Lane to Loop 1604 for construction work. 
  • Current until Saturday, December 15. 9 a.m. until 5 p.m. Both directions of Reed Road between Copperfield Road to Loop 1604 northbound for road work. 
Other roads – Atascosa County
  • Current until November 30. 7 a.m. until 8 p.m. Two lanes of northbound I-37 between Atascosa/Live Oak county line to one mile north of US 281A for pouring concrete, paving and guardrail installation. DETOUR: Northbound traffic on I-37 will be diverted at Exit 98 (FM 541); westbound traffic on FM 1099 will be diverted to US 281A.

Friday, November 16

UPCOMING CONSTRUCTION-RELATED CLOSURES

**ALL CLOSURES WEATHER PERMITTING**

I-10 – East San Antonio
  • Current until further notice. Eastbound entrance ramp from FM 1516. DETOUR: Take next entrance ramp east of Loop 1604. 
  • Sunday, November 18 until Wednesday, November 21. 9 p.m. until 5 a.m. Alternating eastbound mainlane closure between FM 1516 and Loop 1604 for installation of portable concrete traffic barriers and striping work. 
  • Sunday, November 18 until Wednesday, November 21. 9 p.m. until 5 a.m. Alternating westbound mainlane closure from FM 1516 to Union Pacific railroad bridge for installation of portable concrete traffic barriers and striping work. 
  • Monday, November 26 until Friday, November 30. 9 a.m. until 3 p.m. Eastbound right mainlane from Woodlake to FM 1516 for drainage work. 
  • Saturday, December 1. 7 a.m. until 5 p.m. Eastbound right mainlane from Woodlake to FM 1516 for drainage work. 
I-410 – West San Antonio
  • Sunday, November 18 until Tuesday, November 20. 8 p.m. until 5 a.m. Full northbound mainlane and frontage road closure from US 90 to Marbach to remove overhangs and direct connector work. 
  • Sunday, November 18 until Tuesday, November 20. 8 p.m. until 5 a.m. Full southbound mainlane and frontage road closure from US 90 to Valley Hi for overhang removal and direct connector work. 
  • Monday, November 26 until Friday, November 30. 9 a.m. until 3 p.m. Northbound right turn lane at Marbach Road for electrical work. 
  • Monday, November 26 until Friday, November 30. 9 a.m. until 3 p.m. Northbound left frontage road lane from Landing Avenue to Bronco Lane for curb work. 
  • Monday, November 26 until Friday, November 30. 8 p.m. until 5 a.m. Northbound alternating mainlane and frontage road closure from US 90 to Marbach to remove overhangs and direct connector work. 
  • Monday, November 26 until Friday, November 30. 8 p.m. until 5 a.m. Southbound alternating mainlane and frontage road closure from US 90 to Valley Hi for overhang removal and direct connector work. 
Loop 1604 – West San Antonio
  • Current until Saturday, December 1. 9 p.m. until 5 a.m. Alternating southbound mainlanes from Potranco Road to US 90 for paving, striping and barrier work. 
Loop 1604 – North San Antonio
  • Saturday, November 17 until Monday, November 19. 3 a.m. until 5 a.m. Full closure of eastbound mainlanes from US 281 northbound exit to northbound-eastbound direct connector entrance for direct connector work. DETOUR: Take US 281 northbound exit, go through US 281 and take Gold Canyon entrance. 
US 281 – North San Antonio
  • Friday, November 16 until Monday, November 19. 9 p.m until 5 a.m. Northbound alternating lanes from Sonterra Boulevard to Encino Rio for road widening work. 
  • Saturday, November 17 until Monday, November 19. 3 a.m. to 5 a.m. Southbound Sonterra Boulevard entrance ramp for retaining wall work. 
  • Saturday, November 17 until Monday, November 19. 3 a.m. to 5 a.m. Northbound Sonterra Boulevard exit ramp for direct connector work. 
US 90 – West San Antonio
  • Current until Tuesday, November 20. 8 p.m. until 5 a.m. Full closure of westbound mainlanes and frontage road from I-410 to Horal Street to set bridge panels. DETOUR: Traffic will take the cloverleaves to I-410 northbound frontage road to the mainlanes; turnaround to southbound frontage road to mainlanes; exit at US 90 to access the westbound frontage road. 
  • Current until Tuesday November 20. 8 p.m. until 5 a.m. Full closure of eastbound mainlanes and frontage road from Ray Ellison Drive to I-410 for eastbound-northbound direct connector work. 
  • Current until Saturday, November 17. 10 p.m. until 5 a.m. Westbound left mainlane from I-410 to Tomar Drive for direct connector work. 
  • Sunday, November 18 until Tuesday, November 20. 8 p.m. until 5 a.m. Full closure of westbound mainlanes and frontage road from I-410 to Horal Street for bridge work. 
  • Monday, November 19. 9 a.m. until 3 p.m. Eastbound mainlane shoulder from I-410 to Military Drive for barrier work. 
  • Monday, November 26 until Friday, November 30. 8 p.m. until 5 a.m. Full closure of westbound mainlanes and frontage road from I-410 to Horal Street for bridge work. 
  • Monday, November 26 until Friday, November 30. 8 p.m. until 5 a.m. Full closure of eastbound mainlanes and frontage road from Ray Ellison Drive to I-410 for eastbound-northbound direct connector work. 
I-37 – South Region
  • Current until November 30. 7 a.m. until 8 p.m. Northbound main lanes from Atascosa/Live Oak county line to approximately one mile north of US 281A for guard rail work. 
  • Monday, November 19 until Tuesday, November 20. 9:30 a.m. until 3:30 p.m. One southbound frontage road lane at Cesar Chavez Boulevard turnaround drilling work. DETOUR: Traffic takes left on Cesar Chavez Boulevard and another left to access I-37 northbound. 
I-35 – Central San Antonio
  • Monday, November 19. 9 a.m. until 3 p.m. One southbound mainlane at I-37 southbound exit ramp for barrier repair work. 
Loop 345 (Fredericksburg Road)
  • Monday, November 18 until Friday, November 23. 9 a.m. to 3 p.m. Right lane in both directions from Callaghan Road to Medical Drive for sidewalk and driveway work. 
FM 1346 (E. Houston St.) – Southeast San Antonio
  • Monday, November 19 until Tuesday, November 20. 9 a.m. until 4 p.m. Eastbound right lane from Whispering Creek to Estates Road for sidewalk and driveway work. 
US 87 – Rigsby Road
  • Monday, November 19 until Tuesday, November 20. 9 a.m. to 4 p.m. Eastbound right lane from Bonair Road to WW White for sidewalk and driveway work. 
Other roads – Bexar County
  • Current until Friday, December 21. 9 p.m. until 5 a.m. Both directions of Kilmarnoch Lane from Bonny Brae Lane to Loop 1604 for construction work. 
Other roads – Atascosa County
  • Current until November 30. 7 a.m. until 8 p.m. Two lanes of northbound I-37 between Atascosa/Live Oak county line to one mile north of US 281A for pouring concrete, paving and guardrail installation. DETOUR: Northbound traffic on I-37 will be diverted at Exit 98 (FM 541); westbound traffic on FM 1099 will be diverted to US 281A.

Friday, November 9

Nitty-Gritty Time On US 281 Expansion Project: Major Changes Taking Place Next Week

Just as promised a couple of weeks ago when we implemented the traffic switch on the southbound side taking traffic off the mainlanes and onto the new frontage road, now we've got the same scenario but for the northbound side lined up to take effect Monday (Nov. 12) morning at 5 a.m. (see illustrations below).







So basically as you head north on US 281 past Loop 1604, you will be diverted off the mainlanes onto the new frontage road -- keeping the same number of lanes at three. This is only for the stretch between Sonterra Boulevard and Encino Rio. Please do note that since it's still a construction zone, the speed limit in the traffic switch stretch goes down from 60 mph to 45 mph.

Additionally, another important closure is scheduled for next week on this project. The southbound Sonterra Boulevard entrance ramp will be closed starting Tuesday night (Nov. 13) through at least early next year for ramp reconstruction, a new retaining wall, drainage and work on the westbound-southbound direct connector between US 281 and Loop 1604 (see illustration below).



You can receive information on US 281 Expansion Project lane closures straight to your e-mail inbox by registering here (link to http://eepurl.com/cXz2kr).

NEXT WEEK'S CONSTRUCTION-RELATED CLOSURES

ALL CLOSURES WEATHER PERMITTING

I-10 – West San Antonio
  • Current until Monday, November 12. 9 p.m. until 5 a.m. Westbound right mainlane from US 87 to SH 46 for shoulder reconstruction work. DETOUR: Traffic on SH 46 will be diverted to the eastbound frontage road to Scenic Loop to the highway westbound entrance ramp. 
  • Current until Friday, November 16. 8 a.m. until 4 p.m. Westbound Exit 551 (Boerne Stage Road/Leon Springs) for retaining wall construction. 
  • Monday, November 12 until Wednesday, November 14. 7 a.m. until 4 p.m. Westbound frontage road and Boerne Stage Road for bridge work. DETOUR: Use Ralph Fair Road and Dominion Drive as alternate exits. 
  • Monday, November 12 until Friday, November 16. 9 p.m. until 5 a.m. Alternating eastbound mainlanes from Frederick Creek to US 87 for barrier installation work. 
  • Monday, November 12 until Friday, November 16. 9 p.m. until 5 a.m. Alternating westbound mainlanes from Johns Road to SH 46 for barrier repairs at Fredericks Creek.
I-10 – East San Antonio
  • Saturday, November 10. 5 a.m. until 9 p.m. Alternating mainlanes in both directions between I-410 and Loop 1604 for striping, mill/overlay and installing portable concrete traffic barrier. 
  • Sunday, November 11 until Friday, November 9. 9 p.m. until 5 a.m. Alternating mainlanes in both directions between WW White Road and FM 1516 for installation of portable concrete traffic barriers. 
  • Sunday, November 11 until Friday, November 16. 9 p.m. until 5 a.m. Eastbound right mainlane between FM 1516 and Loop 1604 for striping and mill/overlay. 
  • Monday, November 12 until Friday, November 16. 9 a.m. until 5 p.m. Left-turn-only frontage road lane approaching Ackerman Road in both directions. 
  • Current until further notice. Eastbound entrance ramp from FM 1516. DETOUR: Take next entrance ramp east of Loop 1604. 
I-410 – West San Antonio
  • Sunday, November 4 until Friday, November 16. 8 p.m. until 5 a.m. Full northbound mainlane closure from US 90 bridge to Marbach Road for barrier removal on the mainlanes and frontage road. DETOUR: Traffic will use the frontage road and use next ramp. 
  • Monday, November 12 until Thursday, November 15. 9 a.m. to 3 p.m. Northbound left frontage road lane from Landing Avenue to Bronco Lane for curb installation work. 
  • Sunday, November 18 until Tuesday, November 20. 8 p.m. until 5 a.m. Full northbound mainlane and frontage road closure from US 90 to Marbach to remove overhangs and direct connector work. 
  • Sunday, November 18 until Tuesday, November 20. 8 p.m. until 5 a.m. Full southbound mainlane and frontage road closure from US 90 to Valley Hi for overhang removal and direct connector work. 
Loop 1604 – East San Antonio
  • Sunday, November 11 until Tuesday, November 13. 9 p.m. until 5 a.m.. Right northbound mainlane from Pat Booker Road to I-35 for barrier placement work. DETOUR: Traffic will take Loop 1604 westbound to the Lookout Road exit and then take turnaround to Loop 1604 eastbound and then take the exit to I-35. 
  • Sunday, November 11 until Friday, November 16. 9 p.m. until 5 a.m. Southbound frontage road, right mainlane, entrance ramp from Pat Booker Road and Kitty Hawk exit ramp for barrier placement work. 
Loop 1604 – West San Antonio
  • Current until Saturday, December 1. 9 p.m. until 5 a.m. Alternating southbound mainlanes from Potranco Road to US 90 for paving, striping and barrier work. 
  • Saturday, November 10. 5 a.m. to 10 a.m. Westbound shoulder and left mainlane at Huebner Crossing for an emergency repair of damaged crash barrier. 
  • Sunday, November 11 until Friday, November 16. 9 p.m. until 5 a.m. Westbound left mainlane from Golden Corral to Jim’s Restaurant for turnaround barrier removal work. 
  • Sunday, November 11 until Friday, November 16. 9 p.m. until 5 a.m. Eastbound left mainlane from Chili’s to HEB for turnaround barrier removal work. 
  • Sunday, November 11 until Friday, November 16. 9 p.m. until 5 a.m. Westbound frontage road lane from Bandera Road to La Cantera Parkway for milling and paving work. 
  • Sunday, November 11 until Friday, November 16. 9 p.m. until 5 a.m. Westbound frontage road lane and one mainlane from Lockhill Selma to La Cantera Parkway for guardrail and mow strip work. 
Loop 1604 – North San Antonio.
  • Saturday, November 10 until Monday, November 12. 2 a.m. until 5 a.m. Full closure of eastbound mainlanes from US 281 northbound exit to northbound-eastbound direct connector entrance for direct connector work. DETOUR: Take US 281 northbound exit, go through US 281 and take Gold Canyon entrance. 
  • Monday, November 12 until Friday, November 16. 9 p.m. until 5 a.m. Full closure of eastbound mainlanes from US 281 northbound exit to northbound-eastbound direct connector entrance for direct connector work. DETOUR: Take US 281 northbound exit, go through US 281 and take Gold Canyon entrance. 
  • Saturday, November 17 until Monday, November 19. 2 a.m. until 5 a.m. Full closure of eastbound mainlanes from US 281 northbound exit to northbound-eastbound direct connector entrance for direct connector work. DETOUR: Take US 281 northbound exit, go through US 281 and take Gold Canyon entrance. 
US 281 – North San Antonio
  • Saturday, November 10 until Monday, November 12. 2 a.m. until 5 a.m. Right northbound mainlane from Donella Drive entrance ramp to Sonterra Boulevard entrance ramp for direct connector work. DETOUR: Take Frontage Road exit and go through Loop 1604 intersection to get back on US 281 northbound. 
  • Sunday, November 11 until Friday, November 16. 9 p.m. until 5 a.m. Alternating northbound mainlanes from Redland Road to Encino Rio for barrier work. 
  • Sunday, November 11 until Friday, November 16. 9 p.m. until 5 a.m. Alternating southbound mainlanes from Sonterra Boulevard exit ramp to Loop 1604 for barrier work. 
  • Monday, November 12 until Friday, November 16. 9 p.m. until 5 a.m. Northbound right mainlane from Donella Drive entrance ramp to Sonterra Boulevard entrance ramp for direct connector work. DETOUR: Take Frontage Road exit and go through Loop 1604 intersection to get back on US 281 northbound. 
US 90 – West San Antonio
  • Current until Saturday, November 10. 9 p.m. until 5 a.m. Eastbound center mainlane from ½-mile west of Loop 1064 southbound to ½-mile east of Loop 1604 northbound for direct connector work. DETOUR: Traffic rerouted to eastbound frontage road past I-410 interchange and back on to US 90. 
  • Sunday, November 11 until Tuesday, November 20. 8 p.m. until 5 a.m. Full closure of westbound mainlanes and frontage road from I-410 to Horal Street to set bridge panels. DETOUR: Traffic will take the cloverleaves to I-410 northbound frontage road to the mainlanes; turnaround to southbound frontage road to mainlanes; exit at US 90 to access the westbound frontage road. 
  • Sunday, November 11 until Tuesday November 20. 8 p.m. until 5 a.m. Full closure of eastbound mainlanes and frontage road from Ray Ellison Drive to I-410 for eastbound-northbound direct connector work. 
  • Friday, November 16 until Saturday, November 17. 10 p.m. until 5 a.m. Westbound left mainlane from I-410 to Tomar Drive for direct connector work. 
  • Sunday, November 18 until Tuesday, November 20. 8 p.m. until 5 a.m. Full closure of westbound mainlanes and frontage road from I-410 to Horal Street for bridge work. 
I-37 – South Region
  • Current until November 30. 7 a.m. until 8 p.m. Northbound main lanes from Atascosa/Live Oak county line to approximately one mile north of US 281A for guard rail work. 
Loop 368 (Austin Highway)  -- Central San Antonio
  • Monday, November 12 until Tuesday, November 13. 9 a.m. to 3 p.m. Westbound right lane from Sheraton Drive to N. New Braunfels Avenue & N. New Braunfels Avenue from Loop 368 to Wildrose Avenue for barrier installation work. 
SH 16 (Bandera Road) – Northwest San Antonio
  • Sunday, November 11 until Friday, November 16. 9 p.m. until 5 a.m. Alternating southbound lanes from Cooter Brown to Chili’s for barrier removal work. 
  • Sunday, November 11 until Friday, November 16. 9 p.m. until 5 a.m. Two northbound lanes from Academy to 7-11 for barrier removal work. 
FM 1346 (E. Houston St.) – Southeast San Antonio
  • Current until Sunday, November 11. 9 a.m. until 4 p.m. Eastbound right lane from Whispering Creek to Estates Road for sidewalk and driveway work. 
  • Current until Sunday, November 11. 9 a.m. until 4 p.m. Westbound left lane from Flora Road to WW White Road for sidewalk and driveway work. 
FM 1957 (Potranco Road)
  • Tuesday, November 13 until Friday, November 16. 9 p.m. until 5 a.m. Alternating lanes in both directions at Loop 1604 for lighting installation work under Loop 1604 bridge. 
Other roads – Bexar County
  • Monday, November 12 until Friday, November 16. 9 p.m. until 5 a.m. Full closure of eastbound and westbound Redland Road at US 281 for ramp overhang work. 
  • Current until Friday, December 21. 9 p.m. until 5 a.m. Both directions of Kilmarnoch Lane from Bonny Brae Lane to Loop 1604 for construction work. 
Other roads – Atascosa County
  • Current until November 30. 7 a.m. until 8 p.m. Two lanes of northbound I-37 between Atascosa/Live Oak county line to one mile north of US 281A for pouring concrete, paving and guardrail installation. DETOUR: Northbound traffic on I-37 will be diverted at Exit 98 (FM 541); westbound traffic on FM 1099 will be diverted to US 281A.

Heads-Up For Closure On I-10 In Far East San Antonio

As the I-10 East widening project continues, construction crews have temporarily closed the eastbound ramp from FM 1516 to I-10 to make ramp and drainage improvements.

Eastbound drivers wishing to enter the I-10 mainlanes must remain on the frontage road and use the eastbound ramp after Loop 1604.

We will let you know when the ramp reopens. Thank you for your patience and understanding as we continue to plan, design, build, maintain and improve state roadways in the South Central Texas region.



Friday, November 2

I-10 East Expansion Project Upcoming Closures

Construction is underway to widen I-10 East from four to six lanes between I-410 and Loop 1604. The following closures are scheduled from Saturday, November 3 through Saturday, November 10. All work is weather-permitting and subject to change.

Eastbound and Westbound I-10 Mainlanes between I-410 and Loop 1604:
Alternating lane closures will occur in both directions as crews perform pavement resurfacing, striping and placement of portable traffic barriers. One lane will remain open in each direction while work is being performed in the other lane. These closures will apply as follows:
  • Saturday, November 3: 5 a.m. until 9 p.m.
  • Sunday night, November 4, until Friday morning, November 9: 9 p.m. until 5 a.m. nightly.
  • Saturday, November 10: 5 a.m. until 9 p.m.
  • No lane closures are scheduled overnights Friday and Saturday.













NEXT WEEK'S CONSTRUCTION-RELATED CLOSURES

I-10 – West San Antonio
  • Current until Friday, November 16. 8 a.m. until 4 p.m. Westbound Exit 551 (Boerne Stage Road/Leon Springs) for retaining wall construction. 
  • Current until 9 p.m. Saturday, November 3. Westbound frontage road and Boerne Stage Road for bridge work. DETOUR: Use Ralph Fair Road and Dominion Drive as alternate exits. 
  • Friday, November 2 until Monday, November 5. 9 p.m. until 5 a.m. Eastbound right mainlane from Frederick Creek to SH 46 for shoulder reconstruction work. DETOUR: Traffic will be diverted to Scenic Loop. 
  • Monday, November 5 until Friday, November 9. 9 p.m until 5 a.m. Alternating mainlanes from Frederick Creek to US 87 for barrier work and striping. 
  • Friday, November 9 until Monday, November 12. 9 p.m. until 5 a.m. Westbound right mainlane from US 87 to SH 46 for shoulder reconstruction work. DETOUR: Traffic on SH 46 will be diverted to the eastbound frontage road to Scenic Loop to the highway westbound entrance ramp. 
I-10 – East San Antonio
  • Saturday, November 3. 5 a.m. until 9 p.m. Alternating lanes in both directions from I-410 to Loop 1604 for striping, milling, paving and barrier installation work. 
  • Sunday, November 4 until Friday, November 9. 9 p.m. until 5 a.m. Alternating mainlanes in both directions between I-410 and Loop 1604 for striping, mill/paving and traffic barrier installation work. 
I-35 – East San Antonio
  • Monday, November 5. 9 a.m. to 3 p.m. Northbound left mainlane at AT&T Parkway (railroad bridge) for guardrail repair work. 
I-410 – West San Antonio
  • Sunday, November 4 until Friday, November 16. 8 p.m. until 5 a.m. Full northbound mainlane closure from US 90 bridge to Marbach Road for barrier removal on the mainlanes and frontage road. DETOUR: Traffic will use the frontage road and use next ramp. 
  • Sunday, November 4 until Friday, November 16. 8 p.m. until 5 a.m. Full southbound mainlane and frontage road closure from Lakeside to Valley Hi for mainlanes and before US 90 to the eastbound cloverleaf for the frontage road for barrier and overhang removal. 
  • Monday, November 5 until Thursday, November 8. 9 a.m. to 3 p.m. Northbound left frontage road lane from Landing Avenue to Bronco Lane for curb installation work. 
Loop 1604 – East San Antonio 
  • Monday, November 5 until Friday, November 9. 9 p.m. until 5 a.m. Pat Booker Road exit to I-35 for barrier placement work. DETOUR: Traffic will take Loop 1604 westbound to the Lookout Road exit and then take turnaround to Loop 1604 eastbound and then take the exit to I-35. 
  • Wednesday, November 7 until Friday, November 9. 9 p.m. until 5 a.m. Right northbound mainlane from Pat Booker Road to I-35 for barrier placement work. DETOUR: Traffic will take Loop 1604 westbound to the Lookout Road exit and then take turnaround to Loop 1604 eastbound and then take the exit to I-35. 
  • Monday, November 5 until Friday, November 9. 9 p.m. until 5 a.m. Westbound entrance ramp from Pat Booker Road to I-35 for barrier placement work. DETOUR: Traffic takes I-35 northbound frontage road up to North Evans Road and take the turnaround to I-35 southbound back to Loop 1604 westbound. 
Loop 1604 – West San Antonio
  • Friday, November 2 until Saturday, November 3. 9 p.m. until 5 a.m. Alternating northbound mainlanes from Military Drive to Wiseman Boulevard for concrete traffic barrier work. 
  • Sunday, November 4 until Friday, November 9. 9 p.m. until 5 a.m. One westbound mainlane and ramps to I-10 from Lockhill Selma Road to Chase Hill Boulevard for guardrail and mow strip work. 
  • Monday, November 5 until Friday, November 9. 9 a.m. until 3 p.m. One westbound frontage road lane from Lockhill Selma Road to Chase Hill Boulevard for guardrail and mow strip work. 
  • Monday, November 5 until Friday, November 9. 9 a.m. until 3 p.m. One westbound frontage road lane from Vance Jackson to I-10 for guardrail and electrical repairs. 
  • Sunday, November 4 until Saturday, December 1. 9 p.m. until 5 a.m. Alternating southbound mainlanes from Potranco Road to US 90 for paving, striping and barrier work. 
  • Tuesday, November 6 until Thursday, November 8. 9 a.m until 3 p.m. Northbound left mainlane from Marbach to US 90 for guard fence work. 
Loop 1604 – North San Antonio
  • Monday, November 5 until Friday, November 9. 9 p.m. until 8 p.m. Alternating westbound frontage road between Gold Canyon Road and US 281 for restripe work. 
  • Monday, November 5 until Friday, November 9. 9 p.m. until 5 a.m. Westbound right mainlane from US 281 North exit to US 281 northbound frontage road for restripe work. DETOUR: Traffic will be diverted to Stone Oak Parkway, take the turnaround and back to Loop 1604. 
US 281 – North San Antonio
  • Sunday, November 4 until Friday, November 9. 9 p.m. until 5 a.m. Alternating northbound mainlanes from Redland Road to Encino Rio for barrier work. 
  • Sunday, November 4 until Friday, November 9. 9 p.m. until 5 a.m. Full closure of northbound mainlanes from Sonterra Boulevard exit ramp to Sonterra Boulevard entrance ramp for barrier work. 
  • Sunday, November 4 until Friday, November 9. 9 p.m. until 5 a.m. Alternating southbound frontage road lanes from Sonterra Boulevard to Loop 1604 westbound frontage road for direct connector work. 
  • Monday, November 5 until Friday, November 9. 9 p.m. until 5 a.m. Full closure of northbound mainlanes from Frontage Road exit to Sonterra Boulevard entrance for direct connector work. 
  • Monday, November 5 until Friday, November 9. 9 p.m. until 5 a.m. Alternating northbound mainlanes from Donellla Drive to Sonterra Boulevard entrance for direct connector work. 
  • Monday, November 5 until Friday, November 9. 9 p.m. until 5 a.m. Full closure of southbound mainlanes from Frontage Road exit to Sonterra Boulevard entrance for direct connector work. DETOUR: Take Sonterra exit and continue south on frontage road, getting back on the highway at the Donella Drive entrance. 
  • Tuesday, November 6 until Friday, November 9. 9 p.m. until 5 a.m. Alternating northbound mainlanes from Redland Road to Encino Rio for barrier work. 
US 90 – West San Antonio
  • Current until Saturday, November 10. 9 p.m. until 5 a.m. Eastbound center mainlane from ½-mile west of Loop 1064 southbound to ½-mile east of Loop 1604 northbound for direct connector work. DETOUR: Traffic rerouted to eastbound frontage road past I-410 interchange and back on to US 90. 
  • Sunday, November 4 until Friday, November 9. 8 p.m. until 5 a.m. Full closure of westbound mainlanes and frontage road from I-410 to Horal Street for bridge panel work. 
  • Sunday, November 4 until Friday, November 16. 8 p.m. until 5 a.m. Full closure of westbound mainlanes from I-410 to Horal Street to set bridge panels. DETOUR: Traffic will take the cloverleaves to I-410 northbound frontage road to the mainlanes; turnaround to southbound frontage road to mainlanes; exit at US 90 to access the westbound frontage road. 
  • Sunday, November 4 until Friday, November 16. 8 p.m. until 5 a.m. Full closure of eastbound mainlanes and frontage road from Ray Ellison Drive to I-410 for eastbound-northbound direct connector work. 
  • Monday, November 5 until Thursday, November 8. 9 a.m. until 3 p.m. Right eastbound mainlane from Hunt Lane to I-410 for traffic rail installation work. 
  • Wednesday, November 7. 9 a.m. until 3 p.m. Eastbound mainlane shoulder from I-410 to Military Drive for concrete barrier pour work. 
US 87 (Rigsby Road) – Southeast San Antonio
  • Monday, November 5. 9 a.m. until 4 p.m. Eastbound right lane from Bonair Road to WW White Road & from WW White Road to Diane Road for sidewalk and driveway work. 
I-37 – South Region
  • Current until November 30. 7 a.m. until 8 p.m. Northbound main lanes from Atascosa/Live Oak county line to approximately one mile north of US 281A for guard rail work. 
FM 1346 (E. Houston St.) – Southeast San Antonio
  • Monday, November 5 until Sunday, November 11. 9 a.m. until 4 p.m. Eastbound right lane from Whispering Creek to Estates Road for sidewalk and driveway work. 
  • Monday, November 5 until Sunday, November 11. 9 a.m. until 4 p.m. Westbound left lane from Flora Road to WW White Road for sidewalk and driveway work. 
Other roads – Bexar County
  • Saturday, November 3. 6 a.m. until 3 p.m. Full closure of Military Drive in both directions at Loop 1604 for traffic signal installation work. 
  • Monday, November 5 until Friday, November 9. 9 p.m. until 5 a.m. Full closure of eastbound Redland Road at US 281 and westbound from Sonterra Boulevard exit to Sonterra Boulevard exit for ramp overhang work. 
  • Current until Friday, December 21. 9 p.m. until 5 a.m. Both directions of Kilmarnoch Lane from Bonny Brae Lane to Loop 1604 for construction work. 
Other roads – Atascosa County
  • Current until November 30. 7 a.m. until 8 p.m. Two lanes of northbound I-37 between Atascosa/Live Oak county line to one mile north of US 281A for pouring concrete, paving and guardrail installation. DETOUR: Northbound traffic on I-37 will be diverted at Exit 98 (FM 541); westbound traffic on FM 1099 will be diverted to US 281A.