Thursday, May 6

FULL CLOSURE OF I-10 IN BOERNE STARTING FRIDAY, MAY 14

*DUE TO WEATHER, THIS CLOSURE HAS BEEN POSTPONED TO THE WEEKEND OF JUNE 11.*




As part of the ongoing IH-10 frontage road construction, work is progressing into the next stage of construction which will require the demolition of the existing US-87 (Main Street) bridge. 

In order to safely remove the bridge, crews will need approximately 56 hours of continuous full mainlane closure of the IH-10 eastbound and westbound travel lanes between SH-46 (Bandera Rd) and Scenic Loop. The removal of this bridge will allow crews to start working on the new US-87 bridge.  

The work is scheduled to start on Friday May 14, 2021 at 9:00 pm and is expected to be completed by 5:00 am on Monday May 17, 2021, weather permitting.

The westbound mainlanes will be removed at Exit 542 Business US-87 and will be directed along the Westbound Frontage Road to the next available entrance ramp prior to SH-46, and

The eastbound mainlanes will be removed near SH-46 and will be detoured along the Eastbound Frontage Road and will be allowed to enter back onto the mainlanes east of Scenic Loop.  

During this closure, there will be no through traffic at Scenic Loop under IH-10. All traffic will be required to turn right onto the frontage roads.

  • Northbound Scenic Loop traffic will be detoured to Balcones Creek intersection and
  • Southbound Scenic Loop traffic will be detoured to the SH-46 intersection.
As a reminder, all construction work is subject to change. 

    Need Additional Information?

    Construction Update “Go Ahead!” Bloghttp://txdotsanantonio.blogspot.com/

    Twitter: @TxDOTSanAntonio