Friday, December 11

Next week's construction-related closures

I-10 – Seguin
  • Monday-Tuesday, December 14-15. 9 a.m. until 4 p.m. Eastbound main lanes between Hwy 46 and Walnut Branch Creek. The right lane will close while crews set barrier.
  • Wednesday-Thursday, December 16-17. 9 a.m. until 4 p.m. Westbound main lanes between Walnut Branch Creek and Hwy 46. The right lane will close while crews set barrier.
I-10 – East San Antonio
  • Saturday-Monday, December 12-14. 8 p.m. until 5 a.m. nightly. Eastbound main lanes between I-37 and I-410. The right lane will close while crews repair the pavement base.
I-10 – Northwest San Antonio
  • Monday-Wednesday, December 14-16. 9 p.m. until 5 a.m. Westbound main lanes between Medical Drive and Huebner Road. Alternating lanes will close while crews stripe the roadway.
I-35 – East San Antonio
  • Current until January 2016. Exit ramps, both directions, to Eisenhauer Road. The ramps will close while crews build a new exit ramp. Traffic will use the next available ramp and turn around to reach Eisenhauer Road.
  • Current until January 2016. Northbound entrance ramp from Eisenhauer Road. The ramp will close while crews build a new entrance ramp. Traffic will use the next available ramp.
  • Sunday-Friday, December 13-18. 9 p.m. until 5 a.m. nightly. Main lanes, both directions, between Binz-Engleman and AT&T Center Parkway. Alternating lanes will close while crews do road work.
  • Sunday-Friday, December 13-18. 9 p.m. until 5 a.m. nightly. Frontage road, both directions, between Binz-Engleman and AT&T Center Parkway. Alternating lanes will close while crews do road work.
  • Sunday-Friday, December 13-18. 9 p.m. until 5 a.m. nightly. Turnarounds, both directions, at Salado Creek. The turnarounds will be closed while crews do bridge work.
  • Monday-Friday, December 14-18. 9 a.m. until 3 p.m. daily. Frontage road, both directions, between Binz-Engleman and AT&T Center Parkway. Alternating lanes will close while crews do bridge work.
  • Monday-Friday, December 14-18. 9 a.m. until 3 p.m. daily. Turnarounds, both directions, at Salado Creek. The turnarounds will be closed while crews do bridge work.
I-35 – Downtown San Antonio
  • Monday-Thursday, December 14-17. 9 p.m. until 5 a.m. Southbound main lanes between U.S. 281 and North Walters Street. The inside two lanes will close while crews stripe the roadway. Please note the start time will be later on nights the Spurs play to accommodate traffic for the event.
I-37 – Atascosa County
  • Monday, December 14. 7 a.m. until 6 p.m. Northbound main lanes between mile markers 96 and 99. Alternating lanes will close while crews shift traffic into its original configuration.
U.S. Hwy 90 – West San Antonio
  • Current until May 2016. Westbound frontage road between Hunt Lane and East Kriewald. The frontage road will close while crews reconstruct the Medio Creek Bridge.
Loop 1604 – Northwest San Antonio
  • Friday-Saturday, December 11-12. 9 p.m. until noon. Southbound frontage road at Alamo Concrete Plant. The right lane will close while crews pour concrete for a driveway.
  • Monday-Thursday, December 14-17. 9 a.m. until 4 p.m. daily. Southbound frontage road at Shaenfield Road. The left lane will close while crews hang bridge support beams. Traffic will have two lanes.
  • Monday-Sunday, December 14-20. 10 p.m. until 5:30 a.m. nightly. Northbound frontage road between Culebra and Braun roads. The right lane will close while crews do curb work.
  • Wednesday-Friday, December 16-18. 10 p.m. until 5 a.m. Southbound frontage road at New Guilbeau Road. The right lane will close while crews do concrete work.
  • Monday-Tuesday, December 21-22. 10 p.m. until 5 a.m. Southbound frontage road at New Guilbeau Road. The right lane will close while crews install traffic signal poles.
Hwy 151 – Northwest San Antonio
  • Current until December 2016. Westbound exit ramp to Ingram and Potranco roads. The ramp will remain closed while crews install bridge support structures for the direct connector ramps being constructed.
  • Current until December 2016. Eastbound entrance ramp from Ingram and Potranco roads. The ramp will remain closed while crews install bridge support structures for the direct connector ramps being constructed.
Other roads – Converse
  • Friday-Monday, December 18-21. 8 p.m. until 5 a.m. continuous. FM 1516, both directions, at Crestway. All lanes will close while crews reconstruct the roadway surface. Traffic will detour to I-10, Loop 1604 and FM 78. This is a change from a previously announced closure.
Other roads – Schertz
  • Monday-Friday, December 14-18. 9 a.m. until 4 p.m. daily. FM 3009, both directions, between I-35 and FM 78. The right lane will close in each direction while crews do sidewalk work.
Other roads – Uvalde County
  • Monday, December 21. 7 a.m. until 7 p.m. State Highway 127 at the Frio River crossing in Concan. Full closures of the highway will be used for 25-minute increments while crews set bridge support beams. Traffic should expect long delays or seek an alternate route.
Other roads – Southwest San Antonio
  • Wednesday, December 16. 9 a.m. until 9 p.m. Southwest Military Drive (state Loop 13) between South Zarzamora Street and Somerset Road. All lanes will close at the Union Pacific Railroad crossing while crews with Union Pacific work on the crossing area. Traffic will use South Zarzamora Street, West Mayfield Boulevard, Wabash Street and Somerset Road to reach its destination.