Friday, February 19

Next week's construction-related closures



I-10 – Boerne
  • Sunday-Friday, February 21-26. 9 p.m. until 5 a.m. nightly. Eastbound main lanes at Scenic Loop Road. Alternating lanes will close while crews set barrier and stripe the roadway.
  • Tuesday-Friday, February 23-26. 9 p.m. until 5 a.m. nightly. Westbound main lanes at Scenic Loop Road. Alternating lanes will close while crews move barrier.
I-10 – Seguin
  • Tuesday, February 23. 9 a.m. until 4 p.m. Eastbound exit ramp to Hwy 123. The ramp shoulder will close while crews set barrier. This work should be accomplished without closing the ramp.
  • Tuesday, February 23. 9 a.m. until 4 p.m. Eastbound main lanes between FM 78 and Hwy 123. The right lane will close while crews set barrier.
I-10 – East San Antonio
  • Sunday-Friday, February 21-26. 8 p.m. until 5 a.m. nightly. Eastbound main lanes between Roland Avenue and I-410. The right shoulder will close while crews do road work.
  • Monday-Friday, February 22-26. 9 a.m. until 3 p.m. daily. Main lanes, both directions, between I-35 and I-410. The right shoulder will close while crews do road work.
I-10 – Downtown San Antonio
  • Current thru Thursday, March 31. 9 p.m. until 6 a.m. nightly. Main lanes, both directions, between North Colorado and Fredericksburg Road (lower level). The right lane will close while crews do overhead bridge work.
I-35 – Kyle
  • Sunday, February 21. 6 a.m. until 10 a.m. Northbound main lanes at exit 213. All lanes will close while crews re-create a crash for investigative purposes. Traffic will exit the highway, follow the frontage road and re-enter the highway. Questions regarding this closure should be directed to Chris Bishop of the Austin District Office at 512.832.7110.
I-35 – East San Antonio
  • Current thru March 2016. Exit ramps, both directions, to Eisenhauer Road. The ramps will close while crews build a new exit ramp. Traffic will use the next available ramp and turn around to reach Eisenhauer Road.
  • Current thru March 2016. Northbound entrance ramp from Eisenhauer Road. The ramp will close while crews build a new entrance ramp. Traffic will use the next available ramp.
I-35 – South Bexar County
  • Saturday, February 20. 8 a.m. until 4 p.m. Main lanes, both directions, between I-410 and Somerset Road. Alternating lanes will close while crews repair cracks in the asphalt.
U.S. Hwy 90 – West San Antonio
  • Current until May 2016. Westbound frontage road between Hunt Lane and East Kriewald. The frontage road will close while crews reconstruct the Medio Creek Bridge.
Loop 1604 – Northwest San Antonio
  • Current through Sunday, March 13. Southbound frontage road north of Braun Road. The right lane will close while crews construct sidewalk.
  • Current through Sunday, March 6. 9 p.m. until 5 a.m. nightly. Frontage road, both directions, between Braun and Culebra roads. The right lane will close while crews do concrete work.
  • Current through Sunday, March 6. 9 a.m. until 4 p.m. daily. Frontage road, both directions, between Braun and Culebra roads. The right lane will close while crews do concrete work. Minimum two lanes will remain open in each direction.
  • Saturday-Sunday, February 20-21. 4 a.m. until 7 p.m. daily. Northbound main lanes at Hwy 151. All lanes will close while crews do overhead bridge work. Traffic will exit Hwy 151, turn around at Wiseman and return to Lp 1604 via Hwy 151.
  • Monday-Sunday, February 22-28. 9 p.m. until 5 a.m. nightly. Northbound main lanes at Hwy 151. All lanes will close while crews do overhead bridge work. Traffic will exit Hwy 151, turn around at Wiseman and return to Lp 1604 via Hwy 151.
  • Monday-Sunday, February 22-28. 9 a.m. until 4 p.m. daily. Southbound frontage road between Bandera and Braun roads. The right lane will close as needed for concrete work.
  • Saturday, February 27 at 6 a.m. until Sunday, February 28 at 6 p.m. Main lanes, both directions, at Hwy 151. All lanes will close while crews hang bridge support beams and do overhead bridge work. Traffic will exit Hwy 151 in both directions. Northbound traffic will follow Hwy 151, turn around at Wiseman and return to Lp 1604 via Hwy 151. Southbound traffic will follow the frontage road and re-enter the highway.
  • Saturday, March 5 at 6 a.m. until Sunday, March 6 at 6 p.m. Main lanes, both directions, at Hwy 151. All lanes will close while crews hang bridge support beams and do overhead bridge work. Traffic will exit Hwy 151 in both directions. Northbound traffic will follow Hwy 151, turn around at Wiseman and return to Lp 1604 via Hwy 151. Southbound traffic will follow the frontage road and re-enter the highway.
Hwy 151 – Northwest San Antonio
  • Current until December 2016. Westbound exit ramp to Ingram and Potranco roads. The ramp will remain closed while crews install bridge support structures for the direct connector ramps being constructed.
  • Current until December 2016. Eastbound entrance ramp from Ingram and Potranco roads. The ramp will remain closed while crews install bridge support structures for the direct connector ramps being constructed.
Other roads – East San Antonio
  • Monday-Wednesday, February 22-24. 9 a.m. until 4 p.m. daily. E Houston Street, both directions, at I-410. Alternating lanes, no more than one at a time, will close while crews install underpass lighting.
  • Wednesday-Friday, February 24-26. 9 a.m. until 4 p.m. Rigsby Avenue, both directions, under I-410. Alternating lanes, no more than one at a time, will close while crews install underpass lighting.
Other roads – Southwest San Antonio
  • Saturday, February 20. 8 a.m. until 4 p.m. New Laredo Highway, both directions, between Cassin Road and Pitluk Avenue. Alternating lanes will close while crews repair cracks in the asphalt.
Other roads – Northwest San Antonio
  • Tuesday-Wednesday, February 23-24. 2-6 a.m. daily. Shaenfield Road, both directions, at Lp 1604. All lanes will close while crews do concrete work. Traffic will turn right onto the frontage road and turn around at the next intersection to reach its destination.
Other roads – Schertz
  • Monday-Friday, February 22-26. 9 a.m. until 4 p.m. daily. FM 3009, both directions, between I-35 and FM 78. The right lane will close in each direction as needed while crews do sidewalk work.
Other roads – Pleasanton
  • Current through Friday, March 18. State Highway 97, both directions, one mile east of Charlotte city limits. One-way traffic control will be employed for one mile with temporary traffic signals while crews rebuild the roadway. Expect delays.
All closures are pending weather.