Loop 1604 – North Central San Antonio
  • Sunday, June 30 until Wednesday, July 3. Nightly 9 p.m. to 5 a.m. Full eastbound mainlane closure from US 281 north exit ramp to the Redland Road entrance ramp for bridge span work. DETOUR: Use the US 281 north exit ramp through the US 281 and Gold Canyon Road intersection, then use the Gold Canyon Road entrance ramp.
  • Sunday, June 30 until Wednesday, July 3. Nightly 9 p.m. to 5 a.m. Full westbound mainlane closure from the north exit ramp to the US 281 entrance ramp for bridge span work. DETOUR: Use the north exit ramp, continue through the US 281 intersection and use the US 281 entrance ramp.
  • Sunday, June 30 until Wednesday, July 3. Nightly 9 p.m. to 5 a.m. Full westbound frontage road closure at US 281 for bridge span work. DETOUR: Take the west to eastbound turnaround at US 281 through the Gold Canyon Road intersection, use the turnaround at Redland Road, take the Redland Road entrance ramp and use the Stone Oak Parkway exit ramp.
  • Sunday, June 30 until Wednesday, July 3. Nightly 9 p.m. to 5 a.m. Turnaround closed on the eastbound frontage road, eastbound to westbound turnaround at US 281 for bridge span work. DETOUR: Make a double left at the signalized intersection.
  • Sunday, June 30 until Wednesday, July 3. Nightly 9 p.m. to 5 a.m. Westbound to eastbound turnaround at US 281 for bridge span work. DETOUR: Make a double left at the signalized intersection.
  • Monday, July 1. 8 a.m. until 3 p.m. Westbound to eastbound turnaround at US 281 for utility work. DETOUR: Make a double left at the signalized intersection.
Loop 1604 – Northwest San Antonio
  • Sunday, June 30 until Wednesday, July 3. Nightly 9 p.m. until 5 a.m. One frontage road lane in both directions from Bandera Road to Roger’s Ranch Road for pavement marking work.
  • Sunday, June 30 until Wednesday, July 3. Nightly 9 p.m. until 5 a.m. Alternating frontage road lanes in both directions between Golden Corral and Discount Tire for pavement marking and striping work.
Loop 1604 – West San Antonio
  • Monday, July 1 until Saturday, July 6. Daily 9 a.m. to 5 p.m. The northbound exit ramp to Wiseman Boulevard for concrete work.
  • Monday, July 1 until Saturday, July 6. Daily 9 a.m. to 5 p.m. The northbound entrance ramp north of Wiseman Boulevard for topsoil and seeding work.
  • Monday, July 1 until Saturday, July 6. Daily 9 a.m. to 5 p.m. Alternating lanes FM 1957 (Potranco Road), Military Drive, and Wiseman Boulevard for sign, curb/directional island work.
  • Monday, July 1 until Saturday, July 6. Daily 9 a.m. to 7 p.m. Alternating southbound frontage road lanes between SH 151 to south of FM 1957 (Potranco Road) for drainage ditch work.
  • Monday, July 1 until Saturday, July 6. Daily 9 a.m. to 7 p.m. Alternating northbound frontage road lanes between FM 1957 (Potranco Road) to SH 151 for sidewalk work.
  • Monday, July 1 until Saturday, July 6. Nightly 9 p.m. to 5 a.m. Alternating southbound frontage road lanes between SH 151 to south of FM 1957 (Potranco Road) for paving turn lanes.
  • Monday, July 1 until Saturday, July 6. Nightly 9 p.m. to 5 a.m. All lanes at FM 1957 (Potranco Road) for painting beams under the bridge deck and installing clearance. DETOUR: Traffic will be detoured to Military Drive or FM 471 (Culebra Road) to access east or westbound Wiseman Road.
  • Monday, July 1 until Saturday, July 6. Nightly 9 p.m. to 5 a.m. All lanes at Military Drive for painting beams under the bridge deck and installing clearance signs. DETOUR: Traffic will be detoured to Military Drive or FM 471 (Culebra Road) to access east or westbound Wiseman Road.
  • Monday, July 1 until Saturday, July 6. Nightly 9 p.m. to 5 a.m. All lanes at Wiseman Boulevard for painting beams under the bridge deck and installing clearance signs. DETOUR: Traffic will be detoured to Military Drive or FM 471 (Culebra Road) to access east or westbound Wiseman Road.
  • Current until Wednesday, July 3. Daily 8 a.m. to 7 p.m. Alternating southbound frontage road lanes between just south of FM 1957 (Potranco Road) to south of US 90 for punch list repairs.
  • Current until Wednesday, July 3. Daily 8 a.m. to 7 p.m. The right lane in both directions at Spurs Ranch for island work.
  • Current until Wednesday, July 3. Daily 8 a.m. to 7 p.m. The right lane in both directions at Emory Peak for island work.
  • Current until Wednesday, July 3. Daily 8 a.m. to 7 p.m. Alternating eastbound lanes on Marbach Road for asphalt work.
US 281 – North Central San Antonio
  • Saturday, June 29 until Monday, July 1. Weekend closure 3 a.m. to 5 a.m. Right/center southbound lane closure from Evans Road to Encino Rio for soundwall work.
  • Sunday, June 30 until Wednesday, July 3. Nightly 9 p.m. to 5 a.m. Full northbound closure from the Frontage Road exit ramp to the Sonterra Boulevard entrance ramp for bridge span work. DETOUR: Take the Frontage Road exit ramp, continue through the Loop 1604 intersection and take the Sonterra Boulevard entrance ramp.
  • Sunday, June 30 until Wednesday, July 3. Nightly 9 p.m. to 5 a.m. Full northbound frontage road closure at Loop 1604 for bridge span work. DETOUR: Take the Frontage Road exit ramp, turn right on the Loop 1604 eastbound frontage road, use the turnaround at Gold Canyon Road and take a right on the US 281 northbound frontage road. If going west: drive along the eastbound frontage road through the Gold Canyon Road intersection and use the turnaround at Redland Road, take the Redland Road entrance ramp and use the Stone Oak Parkway exit ramp.
  • Sunday, June 30 until Wednesday, July 3. Nightly 9 p.m. to 5 a.m. Full northbound frontage road closure from the Loop 1604 westbound frontage road to Sonterra Boulevard to work on bridge caps. DETOUR: On the Loop 1604 westbound frontage road, turn left on the US 281 southbound frontage road, take the turnaround at Donella Drive and use the US 281 Donella Drive entrance ramp.
  • Sunday, June 30 until Wednesday, July 3. Nightly 9 p.m. to 5 a.m. Full southbound frontage road closure at Loop 1604 for bridge span work. DETOUR: Take a right on the Loop 1604 westbound frontage road, take the turnaround at Stone Oak Parkway and turn right on the US 281 southbound frontage road.
  • Sunday, June 30 until Wednesday, July 3. Nightly 9 p.m. to 5 a.m. Alternating northbound lane closure from Loop 1604 to Marshall Road for roadwork.
  • Sunday, June 30 until Wednesday, July 3. Nightly 9 p.m. to 5 a.m. Full northbound to westbound direct connector ramp closure for bridge span work. DETOUR: Take the Frontage Road exit ramp, turn left on the Loop 1604 westbound frontage road and use the US 281 entrance ramp.
  • Sunday, June 30 until Wednesday, July 3. Nightly 9 p.m. to 5 a.m. Alternating southbound lane closure from Marshall Road to Loop 1604 for miscellaneous construction.
  • Sunday, June 30 until Wednesday, July 3. Nightly 9 p.m. to 5 a.m. Southbound to northbound turnaround at Loop 1604 for bridge span work. DETOUR: Take a double left at the signalized intersection.
I-10 – Northwest San Antonio/Bexar County/Kendall County/Kerr County
  • Sunday, June 30 until Monday, July 1. 5 p.m. until 5 a.m. Westbound right mainlane ½-mile east of FM 3351 (Ralph Fair Road) for barrier work.
  • Sunday, June 30 until Wednesday, July 3. Nightly 9 p.m. until 5 a.m. Alternating mainlanes in both directions between Scenic Loop Road and SH 46 for replacing buttons/reflectors.
  • Sunday, June 30 until Wednesday, July 3. Nightly 9 p.m. until 5 a.m. Right mainlane in both directions at Quinlan Creek Bridge for pavement core work.
  • Monday, July 1 until Wednesday, July 3. 9 p.m. until 5 a.m. Westbound right mainlane ½-mile east of FM 3351 (Ralph Fair Road) for barrier work.
I-10 – Far East San Antonio/Bexar County/Guadalupe County
  • Current until further notice. Eastbound entrance ramp from FM 1516. DETOUR: Take next entrance ramp east of Loop 1604.
  • Friday, June 28 until Monday, July 1. Full weekend 9 p.m. until 5 a.m. All eastbound mainlanes from west of I-410 to Foster Road as crews prepare to divert traffic to new mainlanes. DETOUR: Westbound mainlane traffic will exit at Ackerman Road and re-enter the mainlanes east of Foster Road.
  • Monday, July 1 until further notice (at least through the summer). Eastbound Ackerman Road exit ramp. DETOUR: Eastbound I-10 and southbound I-410 traffic wishing to access Ackerman Road must take southbound I-410, exit at FM 1346/E. Houston St., turn around, and take the northbound frontage road to Ackerman Road.
  • Monday, July 1 until Tuesday, July 2. 9 p.m. until 5 a.m. Ackerman Road under the I-10 mainlanes as crews demolish the old eastbound mainlane bridge. DETOURS: Southbound Ackerman Road traffic will take the westbound I-10 frontage road to WW White Boulevard, turn around, and use the Ackerman detour via FM 1346/E. Houston St. described above. Northbound Ackerman Road traffic will take the eastbound frontage road to the turnaround at Foster Road and return to Ackerman Road on the westbound frontage road.
  • Monday, July 1 until Tuesday, July 2. 9 p.m. until 5 a.m. Left eastbound mainlane from FM 1516 to Loop 1604 for construction truck access.
I-35 – Northeast San Antonio & Comal County
  • Sunday, June 30 until Tuesday, July 2. Nightly 9 p.m. until 5 a.m. Right mainlane in both directions at I-10 interchange for guard rail installation work.
  • Sunday, June 30 until Wednesday, July 3. Nightly 8 p.m. until 6 a.m. Alternating frontage road lanes in both directions at FM 1103 (Exit 178) for paving work.
I-410 – West San Antonio
  • Sunday, June 30 until Wednesday, July 3. Nightly 9 p.m. until 5 a.m. Right mainlane in both directions at Leon Creek Bridge for pavement core work.
  • Sunday, June 30 until Wednesday, July 3. Nightly 9 p.m. until 5 a.m. Eastbound left mainlane at SH 16 overpass for pavement core work.
  • Sunday, June 30 until Wednesday, July 3. Nightly 9 p.m. until 5 a.m. Westbound right mainlane at SH 16 for pavement core work.
  • Sunday, June 30 until Wednesday, July 3. Nightly 8 p.m. to 5 a.m. All southbound mainlanes between US 90 exit ramp to US 90 bridge at I-410 for rail work. The exit to Valley Hi Drive will also be closed. DETOUR: Traffic will be detoured to continue on the frontage road to the Valley Hi Drive entrance ramp.
  • Monday, July 1 until Friday, July 5. Daily 9 p.m. to 3 p.m. One southbound frontage road lane between Demya Drive and Bertetti Drive for paving work.
US 90 – West San Antonio
  • Current until Wednesday, July 3. Daily 9 a.m. to 3 p.m. Alternating eastbound mainlanes shoulder just east of Loop 1604 will be closed for asphalt work. DETOUR: Traffic will have to take a left on the eastbound frontage road and reenter east of I-410.
  • Sunday, June 30 until Wednesday, July 3. Nightly 8 p.m. to 5 a.m. All eastbound frontage road lanes between Ray Ellison Drive and I-410 and ramp to I-410 southbound frontage road will be closed for overlay hot mix work. DETOUR: Traffic will be detoured to the frontage road and enter at the next entrance.
SH 151 – Far West San Antonio
  • Friday, June 28 until Saturday, June 29. Nightly 9 p.m. to 5 a.m. The intersections between Ingram Road and Westover Hills for mill and inlay work. Ramps will be closed as needed.Sunday, June 30 until Wednesday, July 3. Nightly 9 p.m. to 5 a.m. The intersections in both directions between I-410 and Wiseman Boulevard will be closed for mill and inlay work. Ramps will be closed as needed.
  • Monday, July 1 until Tuesday, July 2. Daily 9 a.m. to 4 p.m. Alternating westbound frontage road lanes between W. Military Drive and west of W. Military Drive for curb work.
PA 1502 – Wurzbach Parkway
  • City of San Antonio closure for Hardberger Park Landbridge project. Monday, June 30 until Wednesday, July 3. Daily 9 a.m. until 4 p.m. Right lane in both directions from FM 1535 (NW Military Hwy.) to FM 2696 (Blanco Road) for construction truck and equipment access.
  • City of San Antonio closure for Hardberger Park Landbridge project. Saturday, July 6. 7 a.m. until 5 p.m. Right lane in both directions from FM 1535 (NW Military Hwy.) to FM 2696 (Blanco Road) for construction truck and equipment access.
FM 1976 – Walzem Road
  • Current until further notice. Daily 7 a.m. until 7 p.m. Alternating southbound lanes from Woodlake Parkway until Gibbs Sprawl Road for barrier work (existing seven total lanes narrowed to three, with one in each direction and a two-way turn lane in the middle).
Loop 13 – WW White Road/West Military Drive
  • Monday, July 1 until Wednesday, July 3. Daily 9 a.m. until 4 p.m. Northbound right lane in both directions from Springfield Road to Seale Road for sidewalk and driveway work.
SH 16 – Bandera Road
  • Sunday, June 30 until Wednesday, July 3. Nightly 9 p.m. until 5 a.m. Alternating lanes in both directions from Quincy Lee to Legend Trail for pavement marking and striping work.
SH 16 – Southern Region
  • Monday, July 1 until Friday, July 5. Daily 8 a.m. until 5 p.m. Alternating southbound lanes between Tilden and FM 624 (mile markers 680-690) for guard fence installation and excavation work.
  • Monday, July 8 until Friday, July 12. Daily 8 a.m. until 5 p.m. Alternating southbound lanes between Tilden and FM 624 (mile markers 680-690) for guard fence installation and excavation work.
SH 46 – Boerne/Kendall County
  • Current until further notice. 9 p.m. until 5 a.m. Eastbound left lane from East Sharon Drive to Charger Boulevard for traffic switch (drivers diverted to the right side for construction access on the right side; left turn lane remains open).