Friday, September 5

Next week's construction-related closures

Interstate 10

Tuesday-ThursdaySeptember 9-11

8:30 p.m. until 5:30 a.m.

Main lanes, both directions, at UTSA Boulevard (northwest San Antonio)

All lanes will close while crews set bridge beams. Traffic will exit UTSA Boulevard and run through the intersection, then reenter the highway. Expect long delays.

 

Monday-FridaySeptember 8-12

9 a.m. until 3:30 p.m. daily

Westbound frontage road between Huebner Road and Loop 1604 (northwest San Antonio)

Alternating lanes will close while crews move barrier and lay pipe. Expect delays.

 

Monday-FridaySeptember 8-12

9 a.m. until 3:30 p.m. daily

Eastbound frontage road between Huebner Road and Loop 1604 (northwest San Antonio)

Alternating lanes will close while crews move barrier and build storm drain. Expect delays.

 

Monday-FridaySeptember 8-12

8:30 p.m. until 5:30 a.m. nightly

Westbound frontage road between Huebner Road and Loop 1604 (northwest San Antonio)

Alternating lanes will close while crews move barrier and build storm drain. Expect delays.

 

Monday-FridaySeptember 8-12

8:30 p.m. until 5:30 a.m. nightly

Eastbound frontage road between Huebner Road and Loop 1604 (northwest San Antonio)

Alternating lanes will close while crews move barrier and build storm drain. Expect delays.

 

Monday-FridaySeptember 8-12

8:30 p.m. until 5:30 a.m. nightly

Eastbound main lanes between Loop 1604 and Fredericksburg Road (northwest San Antonio)

Alternating lanes will close while crews move barrier and place asphalt. Expect delays.

 

Monday-FridaySeptember 8-12

8:30 p.m. until 5:30 a.m. nightly

Westbound main lanes between UTSA Boulevard and Huebner Road (northwest San Antonio)

The right lane will close while crews widen the roadway. Expect delays.

 

Interstate 35

Sunday-FridaySeptember 7-12

9 p.m. until 4:30 a.m. nightly

Southbound main lanes between Solms Road and Schwab Road (Schertz)

Alternating lanes, two at a time, will close while crews resurface the roadway. Expect delays.

 

Sunday-FridaySeptember 7-12

9 p.m. until 5 a.m. nightly

Southbound frontage road at Rittiman Road (northeast San Antonio)

The left lane will close while crews move barrier and move trucks through the work area. Expect delays.

 

Sunday-FridaySeptember 7-12

9 p.m. until 5 a.m. nightly

Southbound frontage road at Fratt Road (northeast San Antonio)

Alternating lanes will close while crews lay asphalt. Expect delays.

 

Monday-FridaySeptember 8-11

9 a.m. until 4 p.m. daily

Southbound frontage road at Fratt Road (northeast San Antonio)

Alternating lanes will close while crews lay asphalt. Expect delays.

 

Sunday-FridaySeptember 7-12

9 p.m. until 5 a.m. nightly

Southbound main lanes between George Beach and Eisenhauer (northeast San Antonio)

Alternating lanes will close to allow trucks safe access to the project area. Expect delays.

 

Interstate 37

No closures scheduled.

 

Interstate 410

Sunday-FridaySeptember 7-12

9 p.m. until 5 a.m.

Eastbound exit to southbound I-35 (northeast San Antonio)

The right lane will close while crews build barrier. Expect delays.

 

Loop 1604

Monday, September 15

9 a.m.

Main lanes, both directions, at I-10 (east San Antonio)

Traffic will shift from the future northbound lanes onto the future southbound lanes as work begins to enter the next construction phase. This work is overseen by Bexar County Public Works.

 

U.S. Highway 90

No closures scheduled.

 

U.S. Highway 281

No closures scheduled.

 

Other roads

Tuesday-SaturdaySeptember 9-13

8 p.m. until 5 a.m. nightly

Medical Drive, both directions, between Ewing Halsell and Fairhaven Street (Medical Center)

Alternating lanes will close while crews do roadwork. Expect delays.

 

Tuesday-SaturdaySeptember 9-13

8 p.m. until 5 a.m. nightly

Fredericksburg Road between Louis Pasteur and Data Point (Medical Center)

Alternating lanes will close while crews do roadwork. Expect delays.

 

Monday-TuesdaySeptember 15-16

8:30 p.m. until 5:30 a.m.

DeZavala Road at I-10 (northwest San Antonio)

All lanes will close while crews pour concrete to form the eastbound overpass bridge deck. Traffic will turn right onto the frontage road in each direction and use turnarounds at the next intersection to reach its destination. Expect delays.

 

Friday-SaturdaySeptember 12-13

11 p.m. until 11 p.m. continuous

Jones-Maltsberger at Wurzbach Parkway intersection (north-central San Antonio)

All lanes will close while crews pave the intersection. Traffic will use Arion Parkway, the U.S. Highway 281 frontage road and Bitters Road to reach its destination. Expect delays.

 

Sunday, September 14

4 a.m. until 11 a.m.

Starcrest Drive at Wurzbach Parkway (north-central San Antonio)

All lanes will close, one direction at a time, while crews pave the road. Traffic will follow the posted detour. Expect delays.

 

All planned lane closures are pending weather.