Friday, May 12

Next week's construction-related closures


I-10 – Kerr County

  • Current until Friday, July 7, at 5 p.m. Westbound exit ramp to FM 783 (Ingram Road) and eastbound entrance ramp from FM 783. The ramps will remain closed while crews rebuild the roadway. Traffic will use FM 783, Hwy 27 and Hwy 16 to reach its destination (the route is marked).

I-10 – Seguin

  • Current through Monday, May 29 at 4 p.m. Westbound frontage road between Business 123 and Grein Place. Alternating lanes will close while crews convert the frontage road to one-way only. This closure includes the intersection of Guadalupe Street as needed.

I-10 – East San Antonio

  • Sunday-Monday, May 14-15. 9 p.m. until 5 a.m. Eastbound frontage road at I-410. The right lane will close while crews remove barrier.

I-35 – Northeast San Antonio

  • Current until Tuesday, August 1 at 5 a.m. Turnarounds, both directions, at Walzem Road. The turnarounds will remain closed while crews do overhead bridge work.
  • Monday-Tuesday, May 15-16. 9 p.m. until 5 a.m. Northbound main lanes between George Beach and the I-410 overpass. The left lane will close while crews pull power lines.
  • Monday-Friday, May 15-19. 9 a.m. until 4 p.m. daily. Southbound exit ramp to AT&T Center Parkway. The ramp will close while crews do concrete work. Crews will ensure the ramp is open for traffic headed to major events at the AT&T Center. Traffic will use the next exit and turn around to reach its destination.
  • Monday-Friday, May 15-19. 9 p.m. until 5 a.m. daily. Main lanes, both directions, between I-410 and Eisenhauer Road. Alternating lanes will close while crews do road work.

I-35 – Downtown

  • Current until Wednesday, May 31. 9 p.m. until 5 a.m. nightly. Main lanes, both directions, at U.S. Hwy 90. The left lane will close while crews do bridge work.
  • Monday, May 15. 9 a.m. until 3 p.m. Southbound main lanes between I-410 and Broadway. The two left lanes will close while crews install guardrail.
  • Tuesday-Friday, May 16-19. 9 a.m. until 3 p.m. daily. Northbound main lanes at AT&T Center Parkway. The right lane will close while crews do concrete work.

I-410 – East San Antonio

  • Current until Wednesday, May 31. 9 p.m. until 5 a.m. nightly. Southbound connector ramp to eastbound I-10. The ramp will close while crews move barrier. Traffic will exit Houston Street, turn around and approach eastbound I-10 from the northbound lanes.
  • Sunday-Monday, May 14-15. 9 p.m. until 5 a.m. Southbound connector to eastbound I-10. The connector will close while crews remove barrier. Traffic will use the next available ramp and turn around to reach its destination.

I-410 – Northwest San Antonio

  • Current until August 31. Northbound exit to Culebra Road. The exit will close while crews widen the main lanes and frontage road. Traffic will exit Ingram Road, turn around and get to Culebra on the southbound frontage road.
  • Saturday, May 13 at 5 a.m. until Sunday, May 14 at 5 a.m. Southbound main lanes between Ingram Road and Hwy 151. The two right lanes will close while crews place steel beams over Leon Creek. This closure includes the exit ramps to Military Drive and Hwy 151 and the entrance ramp from Culebra Road. Traffic will turn around at Marbach and approach their destinations from northbound I-410.
  • Monday-Friday, May 15-19. 9 p.m. until 5 a.m. nightly. Main lanes, both directions, between Ingram Road and Hwy 151. The two left lanes will close while crews work on the median barrier.
  • Monday-Friday, May 15-19. 9 p.m. until 5 a.m. nightly. Southbound frontage road at Hwy 151. The right lane will close while crews do overhead bridge work.
  • Thursday-Friday, May 18-19. 9 p.m. until 5 a.m. Southbound main lanes between Ingram Road and Military Drive. The two right lanes will close while crews hang concrete bridge beams. This closure includes the entrance ramp from Culebra Road and the exit ramp to Military Drive. Traffic will use the next available ramp.

U.S. Hwy 90 – West San Antonio

  • Wednesday-Thursday, May 17-18. 8:30 a.m. until 3 p.m. Eastbound frontage road between Hunt Lane and Carlitos Way. The left lane will close while crews set barrier.

U.S. Hwy 90 – Downtown San Antonio

  • Current through June 1. Eastbound exit ramp to I-35. The ramp has been reduced to a single lane while crews do bridge repair work.
  • Current until Wednesday, May 31. 9 p.m. until 5 a.m. nightly. Eastbound exit ramp to northbound I-35. The ramp will close while crews do bridge repair work. Traffic will exit Theo Malone and turn around to reach northbound I-35.

U.S. Hwy 281 – North-central San Antonio

  • Monday-Friday, May 15-19. 9 p.m. until 6 a.m. Southbound main lanes between Hildebrand and St. Mary’s. The exit ramp to Hildebrand and entrance ramps from Hildebrand, Mulberry Road and St. Mary’s will close as needed while crews resurface the road. Traffic will use the next available ramp and to reach its destination.
  • Sunday-Wednesday, May 14-17. 9 p.m. until 6 a.m. Southbound main lanes between I-35 and I-410. The right lane will close while crews resurface the road.
  • Monday-Tuesday, May 15-16. 9 p.m. until 6 a.m. Northbound exit and entrance ramps around Jones-Maltsberger. The ramps will close while crews resurface the road.

Hwy 151 – Northwest San Antonio

  • Current until August 31. Westbound exit ramp to Hunt Lane. The exit will close while crews work on retaining walls. Traffic will exit Ingram Road and follow the frontage road to reach its destination.
  • Monday-Friday, May 15-19. 9 p.m. until 5 a.m. nightly. Eastbound frontage road between Ingram Road and I-410. The left lane will close while crews do overhead bridge work. This closure includes the entrance ramp from Ingram Road. Traffic will use the next available ramp.

Other roads – Seguin

  • Current until August 31. Austin Street between Martindale and Seidman. The road will be converted to one-way only, moving southbound only, while crews do road work. Northbound traffic will use Guadalupe Street to reach its destination.
  • Saturday, April 29 at 6 a.m. until Sunday, April 30 at 6 a.m. The intersection of Rosemary Street and Austin Street. The intersection will close in all directions while crews install utility lines. Traffic will follow the posted detour route.

Other roads – Boerne

  • Sunday-Friday, May 14-19. 9 p.m. until 5 a.m. nightly. Hwy 46, both directions, between Ammann Road and Rust Lane as well as between Loubach Run and Oak Cliff Drive. Alternating lanes will close while crews move barrier.

Other roads – Northeast San Antonio

  • Friday, May 19 at 9 p.m. until Sunday, May 21 at 5 a.m. Walzem, both directions, at I-35. All lanes will close while crews do overhead bridge work. Traffic will use the frontage road to the next intersection and turn around to reach its destination.
All closures are pending weather.