Friday, September 7

Next Week's Construction-Related Closures

I-10 – West San Antonio
  • Sunday, September 9 until Monday, September 10. 9 p.m. until 5 a.m. Both directions from just south of Fair Oaks Parkway to just north of Ralph Fair Road for traffic barrier relocation. 
  • Monday, September 10 until Thursday, September 13. 9 p.m. until 5 a.m. Right mainlane in both directions from just south of Fair Oaks Parkway to just north of Ralph Fair Road for relocation of traffic barriers. 
  • Current until Monday, September 10. 7 a.m. until 5 p.m. Westbound left frontage road lane between La Cantera Parkway and Rim Drive will be closed for traffic barrier placement. 
  • Current until Friday, September 14. 9 a.m until 3 p.m. Both directions at Camp Bullis Road for concrete work. 
  • Friday, September 14 until Monday, September 17. 9 p.m. until 5 a.m. Westbound frontage road left lane from just north of Ralph Fair Road to just south of Fair Oaks Parkway. 
  • Friday, September 14 until Monday, September 17. 9 p.m. until 5 a.m. Eastbound right mainlane from just south of Fair Oaks Parkway to just north of Ralph Fair Road for ramp work. 
I-10 – East San Antonio
  • Tuesday, September 11 until Friday, September 14. 9 a.m. until 7 a.m. (continuous closure). The eastbound right frontage road lane between Woodlake Parkway to Martinez Creek will be closed for crossing work. DETOUR: Traffic will be diverted to a temporary configuration until the crossing is completed. 
I-410 – West San Antonio
  • Current and continuous until December 2018. Turnarounds, both directions, at Marbach Road. The turnarounds will remain closed while crews construct the new Marbach overpass bridge. Traffic will use the signalized intersection. 
  • Sunday, September 9 until Saturday, September 10. 9 p.m. until 5 a.m. All northbound mainlanes from SH 151 to Military Drive for bridge beam work. DETOUR: Traffic diverted to SH 151 exit, continue through intersection and reenter I-410 at Military Drive entrance ramp. 
  • Sunday, September 9 until Tuesday, September 11. 9 p.m. until 5 a.m. All southbound mainlanes from Military Drive to SH 151 for asphalt work. DETOUR: Traffic will be redirected to Military Drive westbound to Potranco, then southbound Potranco to SH 151. 
  • Sunday, September 9 until Monday, September 10. 8 p.m. until 5 a.m. All eastbound mainlanes between Hunt Lane and I-410 will closed for slope barrier work. DETOUR: Traffic will be detoured to the US 90 eastbound frontage road and re-enter the mainlanes. 
  • Sunday, September 9 until Friday, September 14. 8 p.m. until 5 a.m. All southbound main and frontage road lanes between US 90 exit ramp and US 90 bridge will be closed for bridge deck pour and removing overhangs work. The exit ramp will also be closed. DETOUR: Traffic will be detoured to the frontage road. 
  • Monday, September 10 until Tuesday, September 11.9 p.m. until 5 a.m. All northbound mainlanes from Military Drive to Culebra Road for bridge work. DETOUR: Northbound frontage road traffic will be diverted to Military Road entrance ramp, exit at Ingram Road and turnaround to I-410 southbound . 
  • Monday, September 10 until Thursday, September 13. 9 a.m. until 3 p.m. The left lane on the southbound frontage road between Waters Edge Street to Marbach Road will be closed for grading, hauling dirt and installing drainage boxes. 
  • Tuesday, September 11 until Wednesday, September 12. All southbound mainlanes from Military Drive to Culebra Road for bridge work. DETOUR: Southbound frontage road traffic diverted to Culebra Road entrance ramp to SH 151 westbound; 
  • Wednesday, September 12 until Thursday, September 13. 9 p.m. until 5 a.m. All southbound mainlanes from Culebra Road to SH 151 for work on two bridges. DETOUR: Southbound traffic will be redirected to Culebra Road exit, continue through intersections and reente rat SH 151 entrance ramp. 
SH 16 (Bandera Road) – West San Antonio
  • Current until December 2018. 24 hour closure. The westbound to eastbound Loop 1604 turnaround will be closed for modification of the turnaround as part of the operational improvements. 
SH 151 ­– Far West San Antonio
  • Sunday, September 9 until Monday, September 10. 9 p.m. until 5 a.m. Westbound mainlanes from I-410 until Ingram Road for bridge work. 
US 90 – West San Antonio
  • Sunday, September 9 until Friday, September 14. 8 p.m. until 5 a.m. All westbound frontage road lanes between I-410 to Horal Street will be closed for cap work. DETOUR: Traffic will be detoured US 90 eastbound frontage road to Military Drive turnaround and entrance ramp to US 90 westbound mainlanes. 
  • Wednesday, September 12 until Thursday, September 13. 9 p.m. until 5 a.m. All mainlanes in both directions from I-410 southbound to Military Drive for bracket installation work. 
US 87 (Rigsby Road)
  • Monday, September 10 until Friday, September 14. 9 a.m until 4 p.m. Eastbound right lane from Grobe Road to Holmgreen Road for sidewalk and driveway work. 
Loop 1604 – West San Antonio
  • Monday, September 10 until Friday, September 14. 9 a.m. until 3 p.m. The northbound right lane between N. Ellison Drive and Northwest Vista College will be closed for striping work. 
  • Monday, September 10 until Friday, September 14. 9 p.m. until 5 a.m. Alternating northbound lanes between Wiseman Boulevard and SH 151 will be closed for traffic realignment work. 
Loop 1604 – North San Antonio
  • Saturday, September 8. 2 a.m. until 7 p.m. Full closure (all lanes) westbound from US 281 north exit ramp to US 281 north frontage road for direct connector work. 
  • Sunday, September 9 until Friday, September 14. 9 p.m. until 5 a.m. Eastbound frontage road between US 281 North exit ramp to US 281 South frontage road for direct connector work. 
  • Tuesday, September 11 until Friday, September 14. 9 p.m. until 5 a.m. All three westbound frontage road lanes from US 281 North exit ramp to US 281 North frontage road for direct connector work. 
  • Saturday, September 15. 2 a.m. until 7 p.m. All three westbound frontage road lanes from US 281 North exit ramp to US 281 North frontage road for direct connector work. 
  • Saturday, September 15 until Monday, September 17. Eastbound at Redland Road for beam work. 
U.S. Hwy 281 – Far North San Antonio
  • Sunday, September 9 until Friday, September 14. 9 p.m. until 5 a.m. Northbound alternating mainlanes from Donella Drive entrance ramp to Sonterra Boulevard exit ramp for direct connector work. 
  • Sunday, September 9 until Friday, September 14. 9 p.m. until 5 a.m. Southbound left mainlane from Sonterra Boulevard entrance ramp to Donella Drive exit ramp for direct connector work. 
I-10 – Boerne
  • Sunday, September 9. 9 p.m. until 11 p.m. The westbound exit ramp for US 87 will be close for repair work. 
  • Sunday, September 9 until Wednesday, September 12. 11 p.m. until 5 a.m. The westbound mainlane between ½ mile west of Scenic Loop to US 87 for installing single slope barrier work. 
Other roads – Helotes
  • Current and continuous until Friday, September 28. Northbound SH 16 at FM 1560. The left turn lane will close while crews do road work. No left turns will be permitted. Traffic will continue to the next intersection and turn around to reach its destination. Cross traffic from Circle A is also blocked. 
Other roads – Atascosa County
  • Tuesday, September 4 continuous until November 30. 7 a.m. until 8 p.m. Two lanes of northbound I-37 between Atascosa/Live Oak county line to one mile north of US 281A for pouring concrete, paving and guardrail installation. DETOUR: Northbound traffic on I-37 will be diverted at Exit 98 (FM 541); westbound traffic on FM 1099 will be diverted to US 281A. 

ALL CLOSURES WEATHER PERMITTING