Friday, August 19

I-10 CLOSED AT SH 46 IN KENDALL COUNTY THIS WEEKEND

 


As part of the ongoing IH-10 frontage road construction the contractor is progressing into the next stage of construction which will require the realigning the I-10 mainlanes under SH-46 (Bandera Rd.) bridge.

The last stage of construction for the new SH-46 bridge will necessitate transitioning the I-10 mainlane traffic from their current location to the segment that is currently a work area closed to traffic.  The mainlane transition will place the eastbound mainlanes back in their natural configuration and the westbound mainlanes will be south of their existing orientation. 

The transition is necessary to construct the second half of the SH-46 bridge while maintaining a safe passage for motorists and all construction personnel.

Work is scheduled to start on Friday AUGUST 19, 2022 at 9:00 pm and is expected to complete by 5:00 am on Monday AUGUST 22, 2022, weather permitting.

The westbound mainlanes will be reduced to one-lane then forced to use Exit 540 (SH-46/Bandera Rd). Westbound frontage road traffic will continue through the SH-46 intersection then back onto the mainlanes at the next available entrance ramp located near Fredricks Creek. Off-duty uniformed officers will control the traffic movement at the SH 46 intersection.

The eastbound mainlanes will be reduced to one-lane then forced to use Exit 540 (SH-46/Bandera Rd).  Eastbound frontage road traffic will continue through the SH 46 intersection than back onto the mainlanes at the next available entrance ramp located ¼ west of the US 87 interchange. Off-duty uniformed officers will control the traffic movement at the SH 46 intersection.

For safety reasons, the active bridge on SH 46 at IH 10 will be closed requiring all traffic to turn right onto the frontage roads.

  • Westbound SH-46 traffic will be detoured to westbound I-10, to the Johns Road intersection, and back to Exit 540 SH-46 (see westbound detour route exhibit).
  • Eastbound SH-46 traffic will be detoured the eastbound frontage road, onto the eastbound I-10 mainlanes, to Exit 543 Scenic Loop, where traffic will use the turnaround to reach the westbound frontage road into Boerne/Main St. (see eastbound detour route exhibit).

Friday, July 1

TRAFFIC SWITCH COMING TO I-10 AND SH 46 IN KENDALL COUNTY THE WEEK OF JULY 5TH

 


WHAT’S HAPPENING: The last stage of construction for the new BUS 87 bridge will necessitate transitioning the I-10 mainlane traffic from their current location to the segment that is currently a work area closed to traffic.  The mainlane transition will place the eastbound mainlanes back in their natural configuration and the westbound mainlanes will be south of their existing orientation.  This phase will require the temporary closure of the westbound entrance ramp from Scenic Loop. 

The transition is to construct the second half of the Bus 87 bridge while maintaining a safe passage for motorists and all construction personnel.  The entrance ramp will also undergo construction to complete its final configuration that will include a longer merge lane for motorists entering I-10.

DETOUR: The westbound entrance ramp traffic will utilize the westbound frontage road, across the BUS-87 intersection (ALL-WAY STOP), then onto the next available entrance ramp near SH-46.  

WHEN: The mainlane traffic switch will begin Tuesday July 5, 2022, at 9:00 PM, weather permitting. Multiple nights may be required to complete the work between the hours of 9 PM – 5 AM.

 

ADDITIONAL INFORMATION:   http://txdotsanantonio.blogspot.com/

TxDOT San Antonio (@TxDOTSanAntonio) / Twitter

Friday, April 1

KENDALL COUNTY: WB I-10 ENTRANCE RAMP FROM SH 46 CLOSED UNTIL MAY 2022


 

As part of the ongoing IH-10 frontage road construction the contractor is progressing into the next stage of construction which will require the closure of the existing westbound I-10 entrance ramp from SH-46 (Bandera Rd.).

Construction of the new westbound I-10 entrance ramp will require the temporary closure of the existing westbound SH 46/Bandera Rd. entrance ramp onto I-10 to construct the new westbound SH-46 Entrance ramp and new Westbound Frontage Road that will tie into the new SH-46 pavement, bridge, and frontage road. School Street traffic will be diverted to SH 46. There will not be any additional changes to the intersection traffic configuration at this time.

Work is scheduled to start on Monday April 4, 2022 at 9:00 AM, weather permitting. Construction of the new ramp and westbound frontage road is estimated to take three (3) weeks, weather permitting.

DETOUR:  SH-46/Bandera Rd traffic will be detoured down the Eastbound Frontage Road to the Eastbound SH-46 Entrance ramp onto I-10 and will utilize the next Exit 543 Scenic Loop to be detoured down the eastbound frontage road to the Scenic Loop turnaround. Once under I-10 traffic will be directed back onto the westbound I-10 mainlanes using the existing westbound entrance ramp.


Wednesday, February 2

FULL CLOSURE OF I-10 AT SH 46 SCHEDULED FOR THIS WEEKEND IN KENDALL COUNTY

**THIS CLOSURE HAS BEEN RESCHEDULED FOR THE WEEKEND OF FEBRUARY 11, 2022.**


As part of the ongoing IH-10 frontage road construction, the contractor is progressing into the next stage of construction which will require the demolition of the existing SH-46 (Bandera Rd.) bridge.

In order to safely remove the bridge, a 56-hour continuous full mainlane closure of the I-10 eastbound and westbound travel lanes between SH-46 (Bandera Rd) and US-87 (Main Str.) will be required. The removal of this bridge will allow crews to start working on the new westbound SH-46 bridge structure.

Work is scheduled to start on Friday FEBRUARY 11, 2022 at 8:00 pm and is expected to complete by 5:00 am on Monday FEBRUARY 14, 2022, weather permitting.

The westbound mainlanes will be reduced to one-lane then forced to use Exit 540 (SH-46/Bandera Rd). Westbound frontage road traffic will continue through the SH-46 intersection then back onto the mainlanes at the next available entrance ramp located near Fredricks Creek. Off-duty uniformed officers will control the traffic movement at the SH 46 intersection.

The eastbound mainlanes will be reduced to one-lane then forced to use Exit 540 (SH-46/Bandera Rd).  Eastbound frontage road traffic will continue through the SH 46 intersection than back onto the mainlanes at the next available entrance ramp located ¼ west of the US 87 interchange. Off-duty uniformed officers will control the traffic movement at the SH 46 intersection.

For safety reasons, the active bridge on SH 46 at IH 10 will be closed requiring all traffic to turn right onto the frontage roads.

  • Westbound SH-46 traffic will be detoured to westbound I-10, to the Johns Road intersection, and back to Exit 540 SH-46 (see westbound detour route exhibit).
  • Eastbound SH-46 traffic will be detoured the eastbound frontage road, onto the eastbound I-10 mainlanes, to Exit 543 Scenic Loop, where traffic will use the turnaround to reach the westbound frontage road into Boerne/Main St. (see eastbound detour route exhibit).

 

Tuesday, December 28

I-10 Eastbound Frontage Road in Kendall County Closing from Menger Springs to US 87

 


As part of the ongoing IH-10 frontage road construction, the contractor is progressing into the next stage of construction which will require the complete closure of the existing Eastbound Frontage road from Menger Springs to US-87 (Main St.) in order to construct the new Eastbound Frontage Road approaching US-87.

The closure is scheduled to start on Monday January 3, 2022 at 9:00 AM, weather permitting. 

This will allow TxDOT’s contractor to construct the new Eastbound Frontage Road and new US-87 Southbound bridge approach work. Estimated completion Spring 2022.

DETOUR: Eastbound Frontage Road traffic will be detoured at the new Eastbound Entrance ramp onto IH-10 and will return to the Eastbound Frontage Road using the Exit 543 Scenic Loop exit.


Thursday, December 16

New Roads Opening at SH 46 & I-10 In Kendall County

 


As part of the ongoing IH-10 frontage road construction the contractor is progressing into the next stage of construction which will open the new Eastbound Exit 540 to SH 46/Bandera Rd. and the new Eastbound Frontage Road approaching SH 46. 

Exiting traffic will be able to turn in either direction onto SH 46. There will not be any additional changes to the intersection traffic configuration at this time.

Work is scheduled to start on Monday December 20, 2021 at 9:00 AM, weather permitting. 

This will allow TxDOT’s contractor to shift traffic onto the portion of the new bridge and new pavement that has been built so that the old SH 46 bridge can be demolished and the remainder of the new 6 lane bridge and approach work can be completed. Estimated completion Spring 2022.


Thursday, November 4

Eastbound I-10 Exit 540 to SH 46 Closing for 5 Weeks


As part of the ongoing IH-10 frontage road construction, the contractor is progressing into the next stage of construction which will require closing the existing Eastbound Exit 540 to SH 46/Bandera Rd. in order to construct the new Eastbound Exit 540 and new Eastbound Frontage Road approaching SH 46. 

There will not be any additional changes to the intersection traffic configuration at this time. 

This complete closure is anticipated to take 5 weeks to construct the new Eastbound Exit 540 to SH 46/Bandera Rd., weather permitting.

DETOUR: Eastbound mainlane traffic trying to use Exit 540 SH 46/Bandera Rd. will be detoured at the new US-87 exit, down the eastbound frontage road to the Scenic Loop turnaround. Once under I-10 traffic will be directed back onto the westbound I-10 mainlanes to the existing westbound Exit 540 SH 46/Bandera Rd.

Work is scheduled to start on Monday November 8, 2021 at 12:30 AM. 

This will allow TxDOT’s contractor to shift traffic onto the portion of the new bridge and new pavement that has been built so that the old SH 46 bridge can be demolished and the remainder of the new 6 lane bridge and approach work can be completed. 

Estimated completion of the project is currently Spring 2022.


Wednesday, September 1

MAJOR CLOSURE OF EASTBOUND I-10 FRONTAGE ROAD AT SH 46

 


As part of the ongoing IH-10 frontage road construction, the contractor is progressing into the next stage of construction which will require the complete closure of the Eastbound Frontage Road at the SH 46 (Bandera Rd) intersection, and a complete closure of Upper Balcones Road at the Eastbound Frontage Road intersection.

This work is scheduled to start on Sunday September 19, 2021 at 6:00 am, and will remain closed for approximately 6 weeks.

Once complete, this work will allow TxDOT’s contractor to shift traffic onto the portion of the new bridge that has been built so that the old SH 46 bridge can be demolished and the remainder of the new 6 lane bridge and approach work can be completed. Estimated completion of the bridge is Spring 2022. 

This closure will not affect the SH 46 through traffic across the bridge, but during this closure there will be no through traffic onto the Eastbound Frontage Road.

Johns Road will be the primary detour route for traffic headed east on IH-10 toward San Antonio or to the Eastbound Frontage Road.

Eastbound Frontage Road local business access will be from the SH 46 turnaround bridge off of the Westbound Frontage Road. *Chili’s Restaurant will have access from SH 46.

SH 46 Traffic

  • SH 46 traffic going east on IH-10 towards San Antonio will use the Johns Road detour to enter IH-10
  • Eastbound Frontage Road traffic will use the Johns Road detour to get to the new Eastbound US 87 Exit ramp under SH 46 to access Grand Blvd., Menger Springs Road and the hospital.

Westbound IH-10 Traffic

  • Westbound IH-10 traffic will utilize the new SH 46 turnaround bridge to access Eastbound Frontage Road local business, Grand Blvd. and Menger Springs Road.

Upper Balcones Rd.

  • There will be no through traffic to the Eastbound Frontage Road but will be open to access the local business.


Note: Construction is subject to change and weather permitting. 


Wednesday, August 18

I-10 IN BOERNE CLOSED THE WEEKEND OF AUGUST 20 FOR BRIDGE DEMOLITION

Beginning Friday, August 20 – 9 p.m. and ending Monday, August 23 – 5 a.m., I-10 will be closed from SH 46 to Scenic Loop Road as crews demolish the US 87 bridge.   



This weekend, the Texas Department of Transportation (TxDOT) is scheduled to close both directions of I-10 from SH 46 to Scenic Loop Rd. in Kendall County as crews demolish the US 87 bridge.

In order to safely remove the bridge, crews will need approximately 56 hours of continuous full mainlane closures of both eastbound and westbound I-10 in Boerne. The removal of this bridge will allow crews to start working on the new US 87 bridge.

The work is scheduled to start on Friday, August 20, 2021 at 9 p.m. and is expected to be completed by 5 a.m. on Monday, August 23, 2021, weather permitting.

Detours:

·      Westbound traffic. The westbound mainlanes will be removed at exit 542 Business US 87 and will be directed along the westbound frontage road to the next available entrance ramp prior to SH 46. 

·      Eastbound traffic. The eastbound mainlanes will be removed east of SH 46 and will be detoured along the eastbound frontage road. Drivers will be allowed to enter back onto the mainlanes just east of Scenic Loop Rd. 

During this closure, there will be no through traffic at Scenic Loop Rd. under I-10. All traffic will be directed to turn right onto the frontage roads.

·        Northbound traffic on Scenic Loop Rd. will be detoured to Balcones Creek intersection.

·        Southbound traffic on Scenic Loop Rd. will be detoured to the SH 46 intersection.

Southbound Main St/Business US 87 traffic will not be allowed to cross over I-10 and will be directed to turn right onto the westbound frontage road to the SH 46 intersection.

These closures are part of scheduled work on the I-10 Kendall Extension project. The project includes frontage road and overpass improvements along I-10 from SH 46 to Fair Oaks Parkway in Kendall County.

Friday, July 16

Work Continues on I-10 Kendall Extension Project with Changes Coming to I-10 WB Frontage Road & Scenic Loop Rd.



As part of the ongoing IH 10 frontage road construction in Kendall County, the contractor is progressing into the next stage of construction which will require reconstructing the IH 10 Westbound Frontage Road near Scenic Loop and Cascade Caverns.

The existing outside lane of the westbound frontage road at Scenic Loop will be closed for reconstruction, and traffic will be transferred onto the newly constructed inside lane to maintain frontage road operations.

Traffic will remain as a single lane from Scenic Loop to the new US-87 exit ramp (Exit 542). Additionally, Cascade Caverns will be closed for reconstruction between the westbound frontage road and Old San Antonio Road. Traffic will be detoured to Scenic Loop to access the IH-10 Westbound Frontage Road.

This work is scheduled to start beginning Monday, July 19, 2021weather permitting.

Once complete, this construction will allow TxDOT’s contractor to complete the westbound frontage road widening from Scenic Loop to US-87 (Main Street). This segment’s estimated completion is Summer 2021.


Tuesday, June 29

MAJOR CLOSURE COMING TO SH 46 AT THE I-10 INTERSECTION IN BOERNE

 


Beginning on Tuesday, July 6, the I-10 Kendall Extension project will move into the next phase of construction with several upcoming roadway and lane closures that are required to facilitate the completion of the new 6-lane bridge at SH 46 and I-10. This phase of construction is estimated to take place over 12 weeks.

The first six weeks of this construction phase will include the following closures on SH 46 from Home Depot to the I-10 eastbound frontage road:

  • Closure of the right-turn lane in front of Whataburger on approach to the eastbound frontage road; 
  • Traffic shift onto the temporary pavement; and, 
  • Closure of the Whataburger driveway.

During this phase, two-way traffic will be maintained on the approach to and across the existing SH 46 and I-10 bridge.

The second six weeks of construction will include additional closures as crews begin the reconstruction of roadway approaches to the SH 46 bridge. More information on additional closures will be shared in the coming weeks.

Once complete, this phase of construction will allow crews to shift traffic onto the portion of the new SH 46 bridge by Fall 2021. Following the traffic shift, crews will begin demolition of the old SH 46 bridge and construct the remainder of the new 6-lane bridge and approach. The new SH 46 bridge is currently estimated to be completed by Spring 2022. 

The I-10 Kendall Extension project is a $100 million investment to increase mobility and enhance safety for drivers on I-10 in Kendall County. The project includes plans to improve frontage roads, ramps, bridges, overpasses, and interchanges along I-10 from SH 46 to Fair Oaks Parkway in Kendall County.

Stay Connected

Thursday, May 20

*CANCELED* FULL CLOUSRE OF I-10 IN BOERNE SCHEDULED FOR THE WEEKEND OF JUNE 11

 *THIS CLOSURE HAS BEEN CANCELED AND WILL BE RESCHEDULED AT  A LATER DATE.* 


As part of the ongoing IH-10 frontage road construction, work is progressing into the next stage of construction which will require the demolition of the existing US-87 (Main Street) bridge. 

In order to safely remove the bridge, crews will need approximately 56 hours of continuous full mainlane closure of the IH-10 eastbound and westbound travel lanes between SH-46 (Bandera Rd) and Scenic Loop. The removal of this bridge will allow crews to start working on the new US-87 bridge.  

The work is scheduled to start on Friday June 11, 2021 at 9:00 pm and is expected to be completed by 5:00 am on Monday June 14, 2021, weather permitting.

The westbound mainlanes will be removed at Exit 542 Business US-87 and will be directed along the Westbound Frontage Road to the next available entrance ramp prior to SH-46, and

The eastbound mainlanes will be removed near SH-46 and will be detoured along the Eastbound Frontage Road and will be allowed to enter back onto the mainlanes east of Scenic Loop.  

During this closure, there will be no through traffic at Scenic Loop under IH-10. All traffic will be required to turn right onto the frontage roads.

  • Northbound Scenic Loop traffic will be detoured to Balcones Creek intersection and
  • Southbound Scenic Loop traffic will be detoured to the SH-46 intersection.

As a reminder, all construction work is subject to change. 

    Need Additional Information?

    Construction Update “Go Ahead!” Bloghttp://txdotsanantonio.blogspot.com/

    Twitter: @TxDOTSanAntonio 

    Thursday, May 6

    FULL CLOSURE OF I-10 IN BOERNE STARTING FRIDAY, MAY 14

    *DUE TO WEATHER, THIS CLOSURE HAS BEEN POSTPONED TO THE WEEKEND OF JUNE 11.*




    As part of the ongoing IH-10 frontage road construction, work is progressing into the next stage of construction which will require the demolition of the existing US-87 (Main Street) bridge. 

    In order to safely remove the bridge, crews will need approximately 56 hours of continuous full mainlane closure of the IH-10 eastbound and westbound travel lanes between SH-46 (Bandera Rd) and Scenic Loop. The removal of this bridge will allow crews to start working on the new US-87 bridge.  

    The work is scheduled to start on Friday May 14, 2021 at 9:00 pm and is expected to be completed by 5:00 am on Monday May 17, 2021, weather permitting.

    The westbound mainlanes will be removed at Exit 542 Business US-87 and will be directed along the Westbound Frontage Road to the next available entrance ramp prior to SH-46, and

    The eastbound mainlanes will be removed near SH-46 and will be detoured along the Eastbound Frontage Road and will be allowed to enter back onto the mainlanes east of Scenic Loop.  

    During this closure, there will be no through traffic at Scenic Loop under IH-10. All traffic will be required to turn right onto the frontage roads.

    • Northbound Scenic Loop traffic will be detoured to Balcones Creek intersection and
    • Southbound Scenic Loop traffic will be detoured to the SH-46 intersection.
    As a reminder, all construction work is subject to change. 

      Need Additional Information?

      Construction Update “Go Ahead!” Bloghttp://txdotsanantonio.blogspot.com/

      Twitter: @TxDOTSanAntonio 

      Monday, April 26

      POSTPONED: FULL CLOSURE OF I-10 IN BOERNE STARTING FRIDAY, APRIL 30

      THIS CLOSURE HAS BEEN POSTPONED DUE TO WEATHER. 
      THE WORK WILL BE RESCHEDULED FOR THE WEEKEND OF MAY 14 - 16. 


      As part of the ongoing IH-10 frontage road construction, work is progressing into the next stage of construction which will require the demolition of the existing US-87 (Main Street) bridge. 

      In order to safely remove the bridge, crews will need approximately 56 hours of continuous full mainlane closure of the IH-10 eastbound and westbound travel lanes between SH-46 (Bandera Rd) and Scenic Loop. The removal of this bridge will allow crews to start working on the new US-87 bridge.  

      The work is scheduled to start on Friday April 30, 2021 at 9:00 pm and is expected to be completed by 5:00 am on Monday May 3, 2021, weather permitting.

      The westbound mainlanes will be removed at Exit 542 Business US-87 and will be directed along the Westbound Frontage Road to the next available entrance ramp prior to SH-46, and

      The eastbound mainlanes will be removed near SH-46 and will be detoured along the Eastbound Frontage Road and will be allowed to enter back onto the mainlanes east of Scenic Loop.  

      During this closure, there will be no through traffic at Scenic Loop under IH-10. All traffic will be required to turn right onto the frontage roads.

      • Northbound Scenic Loop traffic will be detoured to Balcones Creek intersection and
      • Southbound Scenic Loop traffic will be detoured to the SH-46 intersection.
      As a reminder, all construction work is subject to change. 

      Need Additional Information?

      Construction Update “Go Ahead!” Bloghttp://txdotsanantonio.blogspot.com/

      Twitter: @TxDOTSanAntonio

      Monday, December 14

      MAJOR CLOSURES PLANNED ON I-10 IN NORTHWEST BEXAR COUNTY THIS WEEK

       


      Beginning this Tuesday, December 15, the Texas Department of Transportation (TxDOT) is scheduled to perform major closures on I-10 in northwest Bexar County. The closures are expected to greatly impact traffic flow and drivers are encouraged to avoid the area. Details on the specific closures are listed below.

      Tuesday, December 15 – 9:00 p.m. to 11:59 p.m.  

      • Full closure of eastbound mainlanes from Ralph Fair Rd. to Dominion Dr.
      • Full closure of eastbound entrance ramp just before Ralph Fair Rd. and exit ramp to Boerne Stage Rd.


      Wednesday, December 16 – 12:00 a.m. to 5:00 a.m.

      • Full closure of eastbound mainlanes from Dominion Dr. Camp Bullis Rd.
      • Full closure of eastbound entrance ramp just before Boerne Stage Rd. and exit ramp to Dominion Dr.


      Wednesday, December 16 – 9:00 p.m. to Thursday, December 17 5:00 a.m.

      • Full closure of westbound mainlanes from Dominion Dr. to Boerne Stage Rd.
      • Full closure of westbound entrance ramp just before Dominion Dr. and exit ramp to Boerne Stage Rd.
      • Full closure of westbound exit ramp to Old Fredericksburg Rd.


      All traffic will be detoured to frontage roads and law enforcement will provide traffic control at intersections.

      These closures will allow crews to install wiring for digital message boards as part of scheduled work on the I-10 Expansion project. The project transforms the I-10 northwest corridor from four mainlanes to eight mainlanes by adding one general purpose lane and one HOV lane in each direction.

      The I-10 Expansion project has a total estimated cost of $70 million. Construction began on the I-10 expansion project in 2017 and reached substantial completion in Fall 2020. Flatiron Construction is the contractor on the project.