Showing posts with label 1604-151. Show all posts
Showing posts with label 1604-151. Show all posts

Monday, May 15

Nine quick project updates

No matter what part of San Antonio you're driving in, chances are you're encountering a construction project. Though we have dozens of projects active right now, we needed to focus on the biggest jobs we have going.
If you've been bitten by the curiosity bug (or no someone who has), take a gander and share this with your friends. We're trying to keep each of these updates brief, so this should go pretty fast:


US 281
We ceremoniously broke ground on this project March 31 and have since been awaiting some paperwork that will allow Webber Construction to get rolling. That paperwork was resting with the Texas Commission for Environmental Quality and the Environmental Protection Agency, and we believe the paperwork is now on its way back to us. As soon as we get that paperwork in hand we'll be able to get working. Bottom line: we're hoping to be underway in June.


I-35 SAMMC
Some have called or emailed in regarding the southbound I-410 exit to Binz-Engleman, which has been closed since we moved traffic onto the new southbound I-35 connector to southbound I-410. Long story short we needed Lane Construction to rebuild the ramp to fit the new connector road, and that should be done here in the next few weeks (translation: mid-June).


1604-151
Work between Bandera and Culebra is long done, and now our work at the intersection of Hwy 151 and Loop 1604 is finished as well. In fact, lingering questions regarding the intersection of Alamo Ranch Parkway and Westwood Loop will not be addressed by our project; those will go to Bexar County Public Works instead. We are looking into some options for highway signs to get traffic from Hwy 151 to Culebra Road, though.


Loop 1604 Northwest
If you've not driven 1604 south of Hwy 151 lately ... well, you may be surprised by what you find. We've got Zachry Construction getting it done between Wiseman and Potranco, and Webber is at work between Potranco and US 90. Heck, they've been at it for six months already, and it's getting obvious. Webber is gearing up to set bridge support beams for what will be the southbound overpass at Potranco Road in the next few weeks, and Zachry continues to work hard to build those southbound lanes on the length of their project.


Potranco Road
The medians are intended to restrict left-turn movements, so if your top complaint is that you can no longer turn left where you wanted ... well, that means the median is doing its job. Yes, the cuts in the median were carefully thought out (read more on this here). We are very near finishing work here, and should be wrapped up and have a final product for you by the end of the month, weather permitting.


UTSA Boulevard
This is another project that's wrapping up. We're resurfacing the project between Ximenes and almost I-10 right now and hope to be out of there in June. The city's portion of the project (between Ximenes and Babcock) still has work to finish, but our end of things is nearly complete.


I-10 Leon Springs
The new eastbound exit ramp to Dominion Drive is open (as of Thursday last week) and traffic is finally in its final configuration between Ralph Fair Road and Dominion Drive. We still have a few minor things to wrap up, but we should be out of people's way. Expect to see Texas Sterling begin putting the final course of asphalt on the road later this week, if weather cooperates. That process should take no more than two weeks to wrap up.


151-410
Yep, we've got a ton of overnight closures in this area right now. Crews are working hard to get whatever bridge beams set they can and are working particularly hard on the bridge structures making up the new exit ramps along northbound and southbound I-410 around Culebra Road. The northbound ramp to Culebra that's been closed since late last year is progressing, and should be reopened in August. Overall completion for this project is still set for next year.


90-410
Williams Brothers is moving pretty darned fast on this project and are focusing on the foundational structures near the intersection of I-410 and US 90 itself. As this work ramps up (and work on US 90 between Loop 1604 and I-410 winds down over the next couple months) expect to see things hit the intensity we're now seeing at 151-410. The two projects are, after all, pretty darned identical. By the way, that mess on the southbound side between Hwy 151 and Marbach is something we're trying to get fixed. The redundant exit ramps will be a major item we address with the project.



Tuesday, February 7

2017: A year in preview

Last month we talked about what 2016 meant to us. Well, 2017 is a pretty darned special year. For those who don't already know, it's a pretty big birthday for TxDOT - but more on that later.

Out with the old
This is the year we finally wrap up work on I-35 between Windcrest and SAMMC. This project, which adjusts a ton of ramps and adds an auxiliary lane in each direction, kicked off back in 2013, was initially set to wrap up near the end of 2016. A slew of issues, ranging from discrepancies in the plan sheets to resource allocation by the contractor to utility conflicts, have plagued the project throughout. Most of these issues have been addressed and, by year's end, we should have this project wrapped up. Once work is complete our auditors and project staff will comb through project schedules and our documents to determine how much of the delay is on our end (TxDOT) and how much is with the contractor (Lane Construction). After this review process (which happens with every project) appropriate liquidated damages will be assessed.
For those driving the area, though, the big news will be the relief from construction-zone traffic so long sought after. The first item that should open up is the new direct connector for southbound I-35 to southbound I-410. Traffic is already basically in its final configuration with the right-hand exit, but has been using the old connector bridge. With the new bridge in use we'll be able to take out the old one and construct the new northbound exit to Rittiman Road.
We should see the remaining exit and entrance ramps between Rittiman Road and Walzem reopen so all those ramp revisions are finished. That also means the auxiliary lane we've been working on should be ready for traffic, which should open up traffic flow quite a bit.
The final area of work is on the north end of the project with some ramp revisions at Randolph Boulevard.
Another long-awaited completion (this one impacted by heavy utility conflicts and resource issues) is the work along I-10 in the Leon Springs area. Texas Sterling Construction should wrap up work on the frontage roads between Dominion Drive and Boerne Stage Road by this summer, if we're able to keep our current schedule. The biggest work item remaining at this point is the new set of eastbound ramps between Boerne Stage Road and Dominion Drive. We've also got some sidewalk work on the westbound side to wrap up. Once those ramps and sidewalks are in we'll see a final layer of asphalt laid project-wide and be done.
The first major project to wrap up, though, is the work on the intersection of Loop 1604 and Hwy 151. We're still working on the finishing touches, but for the purposes of this post we can affirm we'll be finished up in a matter of a few weeks.
We'll also wrap up work along US Hwy 90 between Loop 1604 and I-410 this summer. The main feature of this project is its conversion of the frontage roads to one-way, though we're also replacing the bridges over Medio Creek on the frontage roads and main lanes and adding auxiliary lanes to improve some traffic flow along the main lanes. Oh, and then there's the new west-to-east turnaround at Loop 1604.
Though we've still got frontage roads squeezed to a single lane in some areas, we're nearly in final configuration. As we work to wrap this job up expect to see a ton of work going on between Hunt Lane and I-410, particularly on the westbound side.
By the way, we've got some new barrels and barricades on US 90 near Loop 1604 - these are associated with the Loop 1604 project near there, which includes a direct connector from southbound Loop 1604 to eastbound US 90.

In with the new
One project starting in 2017 will overshadow all the others: the expansion of US 281 between Loop 1604 and Stone Oak Parkway.
(Please: Don't break the internet with your rejoicings, cursing or other exclamations as you read that sentence....)
That's right, we're finally getting after that whole 281 thing. We're adding overpasses at Redland Road, Encino Rio, Evans Road and Stone Oak/TPC Parkway. The main lanes will feature at least four lanes in each direction, with two of those lanes being carpool and transit lanes. We'll also keep the frontage road capacity right at about what US 281 has right now. The whole project will take about four years to build and will ceremoniously kick off at the end of March (you'll see equipment moving around in May). Webber Construction is currently our apparent low bidder for the project with a bid of $192.3 million. That bid will need to be accepted by the Texas Transportation Commission later this month before it's official.
Oh, yeah, and as part of this project we're building those four other direct connectors at 1604 and 281 - the ones that weren't built when the RMA had the interchange built a few years ago.
We've got a similar project slated for I-10 between Loop 1604 and Ralph Fair Road this year. That project adds two new lanes in each direction - one each being a carpool/transit lane - and will get going late summer this year. This project should last about three years.
The first major project to get going this year, though, has been at the intersection of US 90 and I-410. This project started in January and essentially repeats what we're doing at 151 and 410. That is, we're doing connectors for eastbound US 90 to northbound I-410 and for southbound I-410 to westbound US 90, and we're adding a lane in each direction to I-410 while rearranging some of the entrance and exit ramps to improve traffic flow. Williams Brothers Construction - the same contractor working at 151 and 410 as well as on Loop 1604 at Hwy 151 - is building this $120.8 million job and should have things wrapped up in 2019.

Aaaand ... we're officially "old"
Schoenen geburtstag fuer uns! (Random: did you know German immigrants accounted for San Antonio's initial growth surge in the 1850s and 1860s? True story - street signs were even in German, English and Spanish at the time as a result!)
The Texas Department of Transportation will celebrate this year 100 years of delivering a safe, reliable and integrated transportation system to move people and goods across this great state. There are a number of milestones we'll be celebrating as the year goes by, and we'll discuss where we've come from and where we're headed. There's been a lot of learning in our century of service, and we're excited to share our lessons learned with stories of yesteryear.

Thursday, January 12

Strategy for the ARP/WWL intersection

A few weeks ago we addressed the several emails, calls and other contacts received regarding the new Hwy 151 overpass at Loop 1604 as well as the intersection of Alamo Ranch Parkway and Westwood Loop. We left that response with a promise to follow up with our planned strategy; that's what this is about.
Again, if you're in the Alamo Ranch area and have had concerns about this intersection, please share this post. We're aware of the use of the NextDoor app and Facebook that happens out there. This would be a great post to share on those or other similar sites.
We fielded a number of suggested solutions for this area. Some of those were really quite good ideas and helped tremendously. Some suggestions were less constructive. We won't address those less constructive ideas, though Texas Highwayman did in one of his posts. He's also got great information on the background of this work and the overall hullabaloo surrounding this intersection.
What we will address, for the sake of brevity, is what we're going to do and why we landed on that solution. Here goes.

Lane alignment, eastbound ARP to eastbound Hwy 151
We had some issues with the two-lane ramp from Alamo Ranch Parkway onto eastbound Hwy 151 involving unclear lane markings. Initially we had two lanes of ARP through Westwood Loop, which tapered down to one lane between that ramp to Hwy 151 and the access road of southbound Loop 1604.
Well, we've already fixed this. If you're in the left lane of ARP through that Westwood intersection you're in a left-only lane. If you're in that right lane, you'll have the option to enter Hwy 151 or continue on to Loop 1604. Again, that striping is already in place. That doesn't help the advanced warning issue, which folks will no doubt raise. Bexar County Public Works is solving that by adding "shields" to the roadway as you approach the Westwood Loop intersection, which should help drivers get in the appropriate lane.

The ARP-WWL intersection itself
Our friends with Bexar County Public Works are already working on the traffic signal at this intersection, and it should be operational by early February.
Why not have the signals ready when we opened the overpass? It's a common question, and deserves a straight answer.
Initially we were planning to have the signal in place for the opening of the overpass. However, private development in the area (ahem, Santikos) caused some issues with the county's design of the intersection. Because of ensuing delays the county turned focus on a signal at the intersection of Shaenfield Road and Wildhorse Parkway. Meanwhile, we weren't able to simply halt our project while issues with the signal plans were figured out.
At any rate, our work progressed while the county worked out issues with the signal. Things actually worked out pretty well and the timing ended up lining up nearly perfectly. The all-way stop that's existed for years will be replaced with a fully signalized intersection within about 8 weeks of the overpass opening.
This work includes some resurfacing of the road, and Bexar County crews will control signal timing and work out traffic alignments at the intersection.

Westbound Hwy 151 into the ARP-WWL intersection
This is, perhaps, one of the largest frustrations for folks using the new roadway and intersection. There are several issues to address here, so we'll try to take them one at a time.
First, the approach to the ARP-WWL intersection itself. This has been a mess as folks ignore pavement markings to drive pretty much wherever they feel to drive. We have several drivers jumping over three lanes without much warning to get where they want. This happens particularly as those coming off Hwy 151 want to turn right onto WWL or those coming off the Loop 1604 frontage road are turning left toward the theater. Confusing? Yeah, it's because this is not supposed to happen. Yet folks are doing it anyway. Frustrating for us, for sure, and unnecessarily dangerous for others.
We already revamped the pavement markings, painting solid lines to tell folks they're not supposed to change lanes. Since that's not apparently getting it done, we're going to add Tuff Curbs with delineator paddles to keep cars from turning the intersection into a free-for-all in the future.
As for that whole left-turn only lane ... it's not going away. We're working on some advanced notice system, but we have to take care to not interfere with the lane that goes to the ramp connecting to the southbound frontage road of Loop 1604. We don't have room to make that left-only lane an optional left-turn lane; that would mean three lanes pushing through Westwood Loop and onto Alamo Ranch Parkway. ARP only has two lanes, and isn't going to get that third lane any time soon. Even adding a 1,500-foot stretch of a third lane isn't practical; it's more safe to have that traffic merging before the intersection than after.
The good news: once the signal is functional the pain of that stop sign will dissipate significantly.

Overall connectivity
We're finding a number of people are having a tough time finding a way to get where they're going as Hwy 151 reaches Loop 1604 and turns into Alamo Ranch Parkway. We have our traffic engineers looking to evaluate our wayfinding signs (those big green ones that tell you how to get where you're going). That should help some realize getting to Culebra is easier if you go the "old" way. Some things we simply can't sign, though.
For instance, if you're coming from Culebra Road or Loop 1604 and you want to get to the theater, do not use Alamo Ranch Parkway. Santikos has a driveway on the southbound frontage road of Loop 1604 just after ARP. Use that!
If you're planning a stop at Target or Lowes on your way home via Hwy 151, go to Culebra Road and Loop 1604 and turn around. It'll actually be a ton faster (not to mention safer) for you.
Headed to Wal-Mart from Hwy 151? Get on northbound Loop 1604, turn around at Shaenfield and you'll have an easy run to Wal-Mart.
If you're going to Kallison Ranch and that area along FM 471, why not bypass that Culebra traffic? You can continue straight on Alamo Ranch Parkway all the way to Roft Road or Alamo Parkway. Alamo Parkway has a signal that will help you get that left turn onto FM 471 and you'll be safely on your way.
And don't forget you can reach HEB by simply exiting for northbound Loop 1604 and keeping to the right. Pretty simple drive, really.

Is the intersection safe?
The answer to this question is, unequivocally, yes! The county has had stop signs at this location for years. It's been an all-way stop for years. Folks driving the road know it's an all-way stop.
Some have pointed at a tragic crash the week before Christmas as evidence the intersection is unsafe. The Bexar County Sheriff's Office has yet to release its findings on this crash, but we can confidently say the condition of the intersection and the construction situation had absolutely no contribution to the cause of that crash. It's just that simple.
The intersection is as safe as the drivers using it - which is the best that can be said of literally every road on the entire planet. We remain confident in that.

The future of ARP
Will we ever see an overpass at this intersection? Great question - one we don't have an answer for ... and we won't have one until ARP is fully developed, which could take several years to accomplish and is mostly in the hands of private developers who continue to build up the Alamo Ranch area.

Thursday, January 5

Cold temps = no asphalt work this weekend

By now you've probably heard or seen our closures set for this weekend. If not, check this out and come back to this post.

So Mother Nature is throwing a wrench in the works on us. In order to lay asphalt - like, final surface asphalt - we need to have our temperatures above 50 degrees (actually, for the type of asphalt we were planning to lay on Hwy 151 between Lp 1604 and Wiseman, it's 50 degrees and rising). This weekend ... well, we won't be that warm.

That means we'll have to cancel the closures planned at Hwy 151 and Loop 1604. Bummer, we know. That means you can resume any plans you had to be out and about in the area this weekend (yay!). Right now we don't have a firm reschedule plan, but if we end up getting overnight temperatures that are favorable next week we might be able to get this work done overnight. No promises on that, though ... we may end up having to go for January 13-15 (basically just pushing back work a full weekend). If that's the case, review the plan in this video (and, yes ... PLEASE get this word out via NextDoor and Facebook if you're in this impacted area):
But what about concrete work? Or demolition work? Temperatures don't impact that work as much. We don't have heavy winds in the forecast, so we should be on like Donkey Kong for that massive closure you've been hearing about this week at I-35 and New Braunfels Avenue. And yes, we really are taking a Spurs Break with that closure.

We're also moving forward with the closure of the westbound frontage road of Hwy 151 between I-410 and Ingram Road Saturday night, so if that's your area ... well, be aware and be ready to take Military Drive instead.

Tuesday, January 3

Three major closures this weekend

Earlier today we took to Twitter to discuss a major closure on I-35 at New Braunfels Avenue, which will close all lanes of I-35 for most of the weekend. Well, all but Saturday evening - when crews will take a break from work to stay out of the way of traffic headed to the Spurs game that night.
The closure is the first of a handful that will take place over the next year as crews replace the old bridge, which sustained damage more than a year ago when hit by a big rig truck. While we're fixing it, we've decided to upgrade the thing as well - making it wider, higher and modernizing the look just a bit.
This weekend's closure starts 9 p.m. Friday and runs through 5 a.m. Monday, with a break between 4:30 p.m. and midnight Saturday while the Spurs take on the Hornets. I mean, hey ... it's the Spurs, right?
Anyway, here's the broadcast from today:

But that's not the only closure we've got this weekend that'll impact your drive, if you're planning to be out and about. We have two more:

151-410
This isn't a huge one, but if you're traveling at night and need to get to a local destination at the intersection of Hwy 151 and I-410 this may put a damper on things.
We'll have the westbound frontage road of Hwy 151 closed between I-410 and Ingram Road Saturday night into Sunday morning. Work will begin 9 p.m. Saturday and run until 9 a.m. Sunday so crews can pour concrete overhead. Traffic will need to use West Military and Potranco Road to get around the closure. You'll still have access to the businesses in the area, but it won't be quite as convenient.
The big traffic movement that will be changed with this is going from I-410 to westbound Hwy 151 - which uses this frontage road. Folks looking to do this will also be moved to West Military and Potranco - which means those intersections will be slow going.
The good news: This is all overnight and is one night only.

151-1604
Williams Brothers Construction is trying to place final asphalt surfaces on that area as Hwy 151 meets Loop 1604, and this weekend should be their opportunity. It also means folks should just avoid the area as much as they can. Here's the schedule, so if you do venture out you know what you'll be getting yourself into:
(Note: the original post had the closures written out; we made a quick tutorial video instead so the closure info is a bit more clear.)

Take note again: this area will not be fun to drive through this weekend. Please warn your neighbors (ahem, please share this info via NextDoor and Facebook!!) and plan to find something to do at home, if you can, rather than be out and about driving through this.
*UPDATE: This closure will be pushed back, probably to next week, due to cold temps forecast for the weekend. Asphalt work requires temps 50 degrees and rising, and we're projected to be colder than that (especially with windchill) until Monday.

Because we know you'll ask
Since we've brought up the 151-1604 intersection many are wondering about our plan at Westwood Loop and Hwy 151/Alamo Ranch Pkwy.
We'll post more details later this week on the long-term plan. In the short run, expect to see crews out there tomorrow (Wednesday) restriping some of the road between Westwood Loop and the southbound frontage road of Loop 1604. These new stripes will:

  • Eliminate the option to turn right onto Westwood Loop when you're headed west from Hwy 151
  • Eliminate the option to turn left into Santikos from the frontage road portion of Alamo Ranch Parkway coming off the Lp 1604 frontage road (those of you driving the area know what we're talking about)
  • Force that left lane on the eastbound side of Alamo Ranch Parkway to enter Hwy 151 in the left entrance lane
  • Offer the right lane of eastbound Alamo Ranch Parkway the option to enter Hwy 151 (via the right entrance lane) or continue to the southbound frontage road of Loop 1604
Again, we'll have more details published later this week (with pictures!), but do expect to see striping crews out there tomorrow.

Wednesday, December 28

Hwy 151, Alamo Ranch Parkway and Westwood Loop: a brief response

A large number of calls, emails and online messages have come regarding the new overpass guiding Hwy 151 over Loop 1604 into Alamo Ranch Parkway. Most have discussed the way the intersection of Alamo Ranch Parkway and Westwood Loop now operates.

Rather than individual calls and emails to respond, we hope folks will pass this message along on the same social media channels they've posted email addresses and phone numbers of government employees and others. That's right: we're hoping you post this to your NextDoor pages and community Facebook pages.

First of all, the tragic fatal crash occurring at the intersection of Alamo Ranch Parkway and Westwood Loop is still under investigation by Bexar County Sheriff's Office. Only those working with BCSO know the details regarding what happened. One real fact is clear: the crash did not involve the new overpass, nor did it involve changes to the intersection. That intersection has featured an all-way stop condition for at least three years* with stop signs in all directions. If all follow the rules, that intersection is absolutely safe.

Those stop signs are being replaced with traffic signals to improve traffic flow. Bexar County Public Works has already started that work and have indicated to us the signal should be operational by the end of January (weather permitting). As the independent Texas Highwayman noted, a private developer contributed some delays prohibiting the signal from being ready when the overpass was opened, and leaving the finished overpass closed would have caused just as much of an uproar.

We are also working with Bexar County folks to improve the lane alignment situation of Alamo Ranch Parkway at the Westwood Loop intersection - including discussing some of the ideas that have been submitted by the folks who've reached out. We're committed to improving traffic flow and, as Texas Highwayman said, sometimes what works well on paper doesn't always translate to reality.

The big takeaway: we are working on solutions, and once we have something ready to set in stone we will publish it here.

*An earlier version of this post made the claim this all-way stop was in place for five years or more. As resident Jason showed us, initially ARP traffic was allowed to flow and only cross traffic was stopped.

Thursday, December 15

The new Hwy 151 overpass

We're nearing that moment everyone involved with any of our projects looks forward to: completion.

Background
Williams Brothers started the expansion of Loop 1604 between Bandera and Culebra roads back in March of 2014, and signed an option to the contract for the interchange of Hwy 151 that December. Work on the interchange started February of 2015. They opened the new Loop 1604 main lanes in May of this year and the new direct connector to eastbound Hwy 151 the end of July.
Every step of the way WB has been ahead of their set targets. The last remaining targets: open the new Hwy 151/Alamo Ranch Parkway overpass and finalize the job. They have until the first quarter of next year to do both.
If the project manager for WB has his way, that new overpass will be open and in use by the start of next week. This means we'll have some alternating lane closures at the intersection this weekend, particularly on Hwy 151 (both directions) between Wiseman and Lp 1604 and right there at the southbound Lp 1604 frontage road at ARP.

Gettin' it done
We won't hold a media event for this opening. Heck, right now we don't have a for-sure opening time or date and we recently told the folks in Alamo Ranch we didn't expect it to happen until after New Year. Inclement weather that week after Thanksgiving really slowed work down, but crews have been working like crazy to recover that time. If you drive the area routinely, you've likely noticed the flurry of work over the last couple of weeks.
At any rate, just like we did with the southbound 1604 connector to eastbound Hwy 151 we just want to have it ready for you and get it open. When it happens, we'll post it to Twitter and probably call it good.
Most of the big stuff is finished (though crews are still laying that last bit of asphalt this week). We have a lot of little things still to happen. When the opening takes place there will be barrier to move and lanes to stripe.
Those using that direct connector can expect a slight change to the way their lane meets up with Hwy 151 when the overpass is opened; drivers do need to be aware of changing scenarios over the next several days.

What it'll look like
This overpass will carry Hwy 151 traffic over Loop 1604 and land it directly into Alamo Ranch Parkway. Those taking this route will notice a bunch of large yellow signs as they approach Loop 1604 that read, "FREEWAY ENDS".
At the top of the overpass we've got a traffic signal. Yes, you read that right. Traffic coming from westbound Hwy 151 wanting to hit southbound Loop 1604 will have a protected left-turn signal atop the overpass and will have a ramp landing them with the southbound frontage road traffic as it prepares to merge onto the main lanes.


Of course, traffic along Alamo Ranch Parkway will have a series of traffic signals to go through. Take a look at our quick Periscope broadcast about the signals:


Backup plans
If for whatever reason Williams Brothers isn't able to get this overpass finished for next week, we will likely see its opening pushed to the start of January. We try to avoid closures as much as we can between December 15 and January 2 because of the holiday traffic volumes. That might prohibit us getting that overpass done by Christmas should work push very far into next week.

Finishing up
Even if the overpass is opened and finished before Christmas, expect to see WB crews working on finish items through February. A few orange barrels and some of the orange signs will be maintained until the contract is finished up (which can often be a few months after work has actually completed). Although work is about to finish, just know those orange signs will remain for a little while - not too long - while the paperwork end of the project is getting finished up.

Illumination on Loop 1604
Because it's related but doesn't warrant a separate post, we want to address a small string of those median light poles that aren't working right there around Braun Road. All the infrastructure is in place - the wiring, the light poles, light bulbs, everything - for those lights to work. CPS Energy has to connect the circuit to turn the lights on. The contractor's work has been done for a while at this point and we're still waiting on CPS. They are aware of the work item request, it just hasn't reached its turn in their work queue.

Putting a rumor to bed
Just because it keeps coming up when we talk with neighborhood associations in the area, we should put something out there on the topic. Right now TxDOT has not been asked, nor are we planning, to develop Hwy 151 along Alamo Ranch Parkway any further.
The idea has been discussed as savvy folks look at the map and realize as ARP continues to develop it could potentially link to the county's extension of Hwy 211, which will connect Potranco and Culebra roads.
The idea isn't totally crazy - particularly when keeping the future growth and development of the area in mind. It's simply not something that's on our radar at TxDOT. ARP isn't a state-maintained roadway and has been developed, to date, by private builders as the Alamo Ranch area has been built.

Thursday, August 25

Mail Bag: Alamo Ranch and Hwy 151

Great work on the 1604 to 151 connector! I was curious about how things will work down the line though for those that are coming out of the Alamo Ranch shopping center by Target. Will they be able to access that fly-over as they exit from down by Chick-fil-a or even Culebra on that frontage road eventually, or will they have to continue down the service road to the 1604/Wiseman intersection now that the light is gone there by the construction zone? If I recall, there's going to be a light in the final piece by Casa Blanca/Alamo Ranch Pkwy that will allow access to 151, but that hasn't been built. Is that traffic just forced to Wiseman/1604 for now if they want to get back on 151? Thanks again!
- Rick
Why did you close down the traffic light at 1604 and 151? Traffic is now a nightmare there! All those cars funneled into a single lane to enter 1604 from Alamo Ranch ? Whose bright idea was that? It took over an hour to get to 151 this morning (August 1)! And looking at it now at 4:30 p.m. with that map link you gave, traffic is already RED for that whole "extra 2 miles" and you are saying it'll be this bad until next year? Great planning there!
- Angry Driver
Why was there no direct connector planned from westbound Hwy 151 to northbound Lp 1604 in the current project? Will there be one in the future? The traffic is clearly alleviated during the morning commute now the flyover is complete, but the afternoon traffic gets worse and worse as the 151 traffic shares the entrance with the 1604-Culebra exit traffic.
- Greg
There was a question concerning connecting FM 471 (Culebra) to Hwy 151 earlier that still has not been addressed. The folks that live on Culebra have no access to 151. The ramp that was built was blocked off to them and the light that was in place was taken down. Why was this done before the link with ARP was complete? Are there any plans on giving this growing community access to 151 in the interim?
- Matt


Y'all pose some great questions, and we know several share some of the frustrations that are expressed here. To answer these questions, we posted a video earlier this week to YouTube (it was plugged into our last post). Matt, you're right - it took us a bit too long to get this done. We should have had a vid like this posted two weeks ago.
Better late than never, though. Without further ado, here you go:


Tuesday, August 23

Transportation Tuesday - a roundup of projects

Tuesdays are filled with project status meetings along the west and northwest of San Antonio, and today we jumped from project to project to get the latest on what's happening.

I-10 Leon Springs
Texas Sterling Construction has a few hot spots of work remaining, and the most visible (painful?) is the little bridge over Leon Creek on the westbound side. You know, that bridge over by Rudy's - the one that's a two-way bridge but we've got it cut to a single lane, westbound only.
Texas Sterling Construction prepares to set
beams on the Leon Creek bridge near Rudy's.
The bridge was limited to a single lane back in February with the aim to reconstruct it to meet current design standards. Initially we had some issues with some utility conflicts and weren't able to actually begin construction until late April. Since then Texas Sterling has been able to get the first half of the bridge done and have made the second half a priority work item.
Yes, we said we hoped to have the bridge reopened to two-way traffic in time for the school year. Clearly that hasn't happened. Our current target is Halloween. The next major item on the bridge will be setting bridge support beams, and that happens the week of September 9. (Peek behind the curtain of operations ... The beams were slated to be set this week, but rains made the work impossible. Trucks couldn't be scheduled again until September, pushing this back more than just a few days.)
Work on the eastbound frontage road will
cross several driveways the next two months
Texas Sterling also has crews working on the eastbound frontage road between Boerne Stage Road and Dominion Drive, running across a series of driveways. Access to businesses will be maintained while this work is done, but crews will be hitting these driveways one-at-a-time through September.
Overall project completion is currently on pace for the end of this year - only five months behind the original schedule, despite several months' impact from utility delays and an onslaught of rain storms since the project began.

I-10 Fair Oaks Ranch

This is a project that's simply progressing steadily - a good thing. Westbound traffic was shifted to allow working space for Sundt Construction as they prepare to enter phase two, which builds the new overpass at Old Fredericksburg Road, a few weeks ago. The eastbound side was scheduled to be shifted over this week, but heavy rains over the last week or so pushed that back. Once crews have finished some drain structures just south of Buckskin Drive they'll be able to finish the asphalt to allow that shift. Expect that to happen here by mid-September, but don't expect it to impact your drive too much. Again, you'll continue to have two lanes of traffic on the main lanes.

UTSA Boulevard
Curran is about to wrap up work on the first phase of work, which expands UTSA Boulevard to the south a bit and adds a meandering sidewalk as a hike and bike trail. They're looking for some ways to shave off some time from the overall schedule (they're currently looking at finishing by the end of 2017), but their plan has a lot of factors to be considered. Once we have a solid feel for the implications of what they're proposing we'll discuss details - including how it would impact your personal commute through this thoroughfare.
Remember we're not the only ones working out here ... the city has its own expansion project on UTSA Boulevard, stretching from Babcock Road to Ximenes Avenue.

1604 Northwest
This project is finished! Well, you'll see some occasional workers doing some small tasks to tidy up the work area, but we're done with this project. A quick heads-up, though: we are set to begin segments two (Culebra to Potranco) and three (Potranco to US 90) of the expressway expansion this fall. Those projects will both take a little more than two years to complete.

1604-151
Rather than read a long post, here's a video that answers several questions that've come in to us of late:

US 90
The new bridge over Medio Creek
is open on the westbound side.
Hunter Industries opened up the westbound frontage road bridge over Medio Creek earlier this summer, relieving considerable traffic strain for the folks headed to Kriewald Road. With that done, they've started focusing efforts on the widening work along the main lanes on both sides of the highway. Well, that and completing the west-to-east turnaround at Loop 1604.
The turnaround is the priority work item on the project right now, and Hunter is hoping to have it ready to open up by early October. Crews are working on some concrete features now, and asphalt crews are getting ready to get their work on at that west end of the project.
Crews work on concrete facing on
the new turnaround at Lp 1604
First those paving crews will hit the new outside lanes of the main lanes, which were primed for asphalt last week. Once the asphalt on the main lanes is down traffic will be shifted to allow for continued work along the project area. That shift will open up traffic on the westbound side to three lanes - two through and one auxiliary - between Hunt Lane and Loop 1604.
The westbound main lanes are almost ready
to be shifted to allow a short third lane.
Traffic on the eastbound side will remain two lanes for now. Road crews still have a considerable amount of work around Medio Creek before we can get that extra lane open there. The entrance and exit ramps along this side are set to be rebuilt in the upcoming weeks as well. Some of this work won't be finished until early 2017, which will allow Hunter to work on the inside lanes of the Medio Creek main lanes bridge.
One other change upcoming is on the westbound frontage road at Hunt Lane, where the frontage road will be straightened out and the irregular sweep to the right at that spot will be taken out. That little bit of work should come early in September.
The overall project, which adds an auxiliary lane to the main lanes in each direction, constructs a turnaround at Loop 1604 and converts the frontage roads to one-way, is scheduled to wrap up by the end of summer 2017.

151-410
This is another project, like I-10 Fair Oaks Ranch, that's simply progressing. No major traffic shifts are planned for the immediate (next couple of months) future, and we don't have any major closures scheduled.

Wednesday, July 27

New direct connector nearly ready

Thursday update: Williams Brothers has scheduled for the new direct connector to be opened Saturday afternoon (July 30).

This week's small storm may push this back a day or two, but Williams Brothers Construction is just about set to open the new southbound Loop 1604 connector to eastbound Hwy 151.
That's right. The new direct connector - the primary feature of the work at the intersection of Loop 1604 and Hwy 151 - is nearly ready to open (photos to come soon...). It could, in fact, be ready for use as early as Monday's morning commute.
That is, if weather allows.

What's left
Several small items remain to be finished up before the connector can open, but Williams Brothers crews are working around-the-clock to get this open. These are the same crews that managed to open the main lanes of Loop 1604 between Bandera and Culebra up at least six weeks early.
Still, for the curious, here's a list of notable items remaining:

  • Overhead highway sign support columns, particularly near the approach to the ramp along southbound Loop 1604
  • Installation of all appropriate highway signs
  • Completion of concrete barrier along the north face of the connector (requiring overnight closures of Loop 1604 announced earlier)
  • Asphalt tie-ins at both ends of the connector
  • Moving and removing barrier
Some of this work will require some closures that may disrupt weekend travels. If you're planning to be around Culebra or Hwy 151 this weekend, please plan on some delays.

How it'll impact you
For those using southbound Loop 1604 to reach eastbound Hwy 151, this will be a total game-changer. Your exit ramp will still be at about the same spot - the ramp will accommodate folks heading for either Hwy 151 or Alamo Ranch Parkway, as it does today - but you won't be stacked up on the frontage road or stuck waiting on a traffic signal.
That said, it is a single-lane ramp and folks will be driving it at reduced speeds. Don't expect to make the transition from Loop 1604 to Hwy 151 at a constant 60 miles per hour here. It should be a fluid flow, though.
For everyone else, your commute will be much different. Let us explain.
With the new connector in play Williams Brothers will be able to shut down the traffic signal at 1604 and 151. Expect to see concrete barriers set up to prevent its use altogether. This is permanent.
Traffic from Culebra or Alamo Ranch will need to head south on Loop 1604 to Wiseman, turn around, then get to Hwy 151 from northbound 1604. This adds a little more than two miles to your drive.
You won't be competing with traffic from southbound Loop 1604, though. And this isn't a permanent arrangement. As soon as the new overpass is open Alamo Ranch Parkway will be connected to Hwy 151. More on that in a moment.
By the way, if you're one who heads south on Loop 1604 through Hwy 151 you won't have any traffic signals until you reach Wiseman. 

The overpass
The final visible feature of this project will be completed by the end of this year. Williams Brothers Construction has until early the first quarter of 2017 to finish the project. They're likely to finish a little early, though, allowing their resources to move to other projects (like the 151-410 connectors they're building for us).
Expect the biggest flurry of activity for the upcoming few months to be right there on Alamo Ranch Parkway itself. With the existing lanes of the parkway moved to allow for the new overpass approach, you should see crews working hard to build walls and the man-made hill that leads into the overpass.

Tuesday, July 12

Mail Bag: Marbach extensions, that ramp from Ralph Fair Road, development of I-35 and of Lp 1604

When Marbach will be extended west of Loop 1604? Please provide schematic. Thank you.
- Edwin
Edwin, you've asked a pretty easy question! The answer is "we don't know". Marbach is a city or a county facility and is not maintained nor developed by TxDOT. For the area you're looking, we recommend reaching out to the good folks at Bexar County.
To be perfectly honest, new roads aren't really built by the county or the city. In a situation like this, that development would be done by the private developers building up the Marbach area. Just take a look at Alamo Ranch Parkway and its extension for a current example, or look at the way Wiseman was built much before that.
So, if you're wondering when Marbach will be extended ... well, get in touch with the private developers continually building that area out.

I know there have been some questions regarding the east bound on ramp at Ralph Fair Road. I'm curious why the on ramp isn't like the one shown in the TxDOT design manual. Figure 3-29 shows 1,050 ft (450 ft and 600 ft) and I think you're much shorter. How come? Isn't this what's making it dangerous?
- Joe
Well that's about as loaded a question as could be asked, isn't it? And, in fairness, this question was asked quite a while ago - we wanted to be sure to have a good scientific answer for you.
For starters, we're not much shorter than the guidelines in the TxDOT design manual. If you take a look at the notes our engineers made just for this post, you'll note the actual distances are 397 feet from the end of gore to the end of hash lines, and another 563 feet from end of hash lines to the end of taper.



For those keeping track at home, that's a total of 970 feet - less than 8 percent off the suggested dimensions in the design manual. When considering constraints here with drain structures and bridges (this ramp is sandwiched between Nochols and Leon creeks), that's pretty darned awesome.
Bottom line: we stand by our initial response to this issue with confidence.

Just read your mailbag post. Great stuff! I'm just curious if you had any info on the 151/1604 project. I seem to recall that there was some mention of the direct connector being projected to be operational sometime in June. Obviously I'm sure the weather has delayed that, but any word on an ETA?
- Felix
Construction seems to have stopped on the elevated connector from SB 1604 to EB 151. At one point, it was scheduled to open in June 2016. What's the updated schedule to open that connector?
- Trevor 

At the new construction 151-1604 interchange, I see the southbound 1604 exit to 151 flyover looking like it's progressing well. However, it looks as if the new eastbound (from Alamo Ranch Parkway) to 151 connection will run right into the structural member holding up the aforementioned flyover ramp. Was this a mistake in construction, or will the entire east-bound left lane get scrapped and/or relocated?
- Glenn

Felix and Trevor are right, we did boast a tentative opening of the end of June (thanks, Felix, for the kind words!). That was before we got hammered with the rains in April and May, though. Weather shifted the contractor priority to wrapping up work along Loop 1604. That work's deadline was mid-June, and going beyond the deadline carried financial disincentives. Work goes where the money is, and that meant crews being pulled to finish up those main lanes and frontage roads.
Right now the projected opening of the direct connector is in August, though we don't have an exact date. We should note overall completion isn't due until early 2017 - and the contractor isn't really obligated to open this incrementally (though doing so will certainly help them progress their work).
As for the eastbound connector, Glenn ... take a look at this:
If you look closely you'll see hard lines or squares across the direct connector (curved red road). You'll note one of those hard lines lands right up against where the abutment for the Hwy 151 overpass at Lp 1604 sets (blue and read meet, top-center of picture).
These hard lines are the column caps and abutments for the bridge structure. The one you're seeing will be just to the right of what you're seeing. Heck, we've even got the bridge spans in place now so you can see it when you drive through.
Just so we're clear, the overpass over Lp 1604 that merges Hwy 151 with Alamo Ranch Parkway is set to open to traffic by the end of this year.

Many salutations! I am called Damon Mason. I have been driven along the McDermott Freeway and am very impressed with how that highway has been revised to have five lanes in both directions between downtown San Antonio and Loop 410. One question that bugs me is why I-35 has not been revised in the same five-lanes coming-and-going manner that has been done with the McDermott Freeway. Why has that not been done, AAMPO?
- Damon
Why can I-35 not be revised so that freight truck traffic and private auto traffic are using separate levels? Most of the vehicular collisions are caused by private motorists behaving recklessly around freight trucks which have a mass of 80K pounds (or even heavier!); one solution is for freight trucks to have a level of the highway where there are no hydraulic-decelerated vehicles allowed and for private automobiles to have a level of the highway where there are no air-decelerated vehicles allowed. Why has that not been put into practice?
- Damon
Damon (he wrote us twice), this really is a question for the Alamo Area MPO. While we have a seat at that table, we're just one of several. That, and we're not the controlling agency of the MPO - the MPO is independent.
The need on I-35 is clear, and we've got several options being considered. Ultimately it'll be up to the MPO to determine when we'll move on I-35 and how that work will be funded.

What it's going to happen with 1604 between Bandera Road and I-10? With the construction between Culebra and Bandera finishing, traffic here has gotten even worse with increased traffic and accessibility. Are improvements for this stretch stuck in environmental study or funding limbo?
- Andrew

In a word, Andrew, yes.
The real need here is an upgrade - a significant upgrade - to the intersection of I-10 and Loop 1604. While the expansion of Loop 1604 has helped traffic on the far northwest side, it's also rushed traffic into the already existing logjam leading up to I-10 (and, frankly, all the way to US 281). The whole problem requires three major solves.
First, we need an additional lane of traffic for each direction of Loop 1604 between I-10 and US 281 at a minimum (and between Bandera Road and I-35 at a practical level). We know that. Infortunately, we don't have finances to construct that additional lane (though the MPO has been developing ideas for it, as you can see on page 9 here). 
Next, we need a significantly upgraded intersection at I-10. We're solving the problem at US 281 already; the cloverleaf at I-10 is outmoded by far at this point. This is another situation that's in need of significant funding to address. A typical interchange like we need at that location can easily top $500 million. Unfortunately, we're not the kind of agency that just carries that kind of cash on us. We're looking for ideas to get that price tag down - and one way is to build the full interchange in phases. We've already got one phase identified for development next year, at a price tag of about $110 million.
Finally, we need to do some "operational improvements", or adjust the way the ramps are set up and reverse ramps where possible. This means reversing some of the ramps to fit the Super X configuration you see on expressways across the city. This could be something we do as a stop-gap to improve (though, admittedly, only slightly) issues between now and a larger fix. This is all stuff to go through the MPO, though - and it's all being considered. Seriously, just check out the list of projects the MPO has on its wish list. Quite frankly, we just need money to do this.

We'll have more later this week....

Tuesday, June 28

Mail Bag: 151 direct connector, turn lanes at Boerne Stage Road, 281-46 progress

It's been a while since our last Mail Bag post, so we're sifting through the questions now. We hope to have another round of questions answered next week - keep telling us what you want to know!

In the March 16 post you stated, "the direct connector for southbound Lp 1604 to eastbound Hwy 151 is the most visible piece of the intersection improvements, and is on pace to be ready for use this fall." Does this intersection have an estimated completion date and any word on the southbound 1604 to eastbound 151 connector opening early still?
- Kevin
Great question, Kevin. Some of us have been asking the same thing as May rain storms really pushed back work across the district.
The overall completion for this intersection has a deadline of early 2017, but is still on pace to wrap up before the end of the year. As for the new direct connector, it's clearly not going to open by the end of June. By the end of summer, though? That's a distinct possibility.

When will you stripe the two left turn lanes onto Beorne Stage Rd? Right now it's quite likely someone in the right turn lane won't go far enough out not to clip the inside turn lane.
- Chris
This is a problem, quite frankly, even where we have the final striping in place. In many states, it's the law to turn lane-to-lane. That is, if you start in the far left lane to turn left, you had better land in the far left lane of the road you're turning onto.
For whatever reason, Texas law isn't written the same. (By the way, we're not advocating any law here - just pointing out what drivers from other states experience.)
The bottom line: drivers here are woefully unaccustomed to the safe practice of turning into the same lane from which you've turned. Frankly, drivers need to take the responsibility and catch up with best practices implemented by drivers across the nation. But that aside, those pavement markers are darned important.
We'll make sure those are in place and maintained properly moving forward for you!

Now that you've addressed the no right turn rationale on BSR, can you attempt to explain the dual turnaround lane configuration at RFR? The issue is that you have two lanes of the feeder set to turn left onto RFR in addition to the dedicated turnaround lane. The left most left turn lane, the left turn only, turns directly into another left turn only lane making it another turnaround. The middle lane on the feeder that is straight or left turn is directed into the middle lane which is straight through the light into Rialto Village. This center lane that is straight or left always backs up with the people going straight through, so a lot of us turning left will use the left lane, and just cross the other two lanes to turn right to head north on the feeder. The issue is that sometimes there is someone actually turning left from that center lane.
- Dan
A lot of this has to do with what you'll have, final product, when we're all done with the frontage road and new overpass work between Ralph Fair and Fair Oaks (actually, turning that optional lane into an optional left/straight lane was a modification of the original plan, based on public input). Remember when we're all done you'll not be turning left on Ralph Fair to turn right onto what will then be the eastbound (only) frontage road.
We're also trying to take into account the future development at that location. While you're right that the left-left option effectively creates a dual turnaround, folks coming from the actual turnaround shouldn't be trying to skip across a few lanes to reach the Whataburger right there. Those folks should use the left-left lanes you've mentioned.
So we really do have a method to the madness.
That said, we can take a look at the layout and have our engineers try to find a way to address the issues you've brought up.

When will the turn-around at 281/46 be completed in Comal county? Why has this project progressing at such a slow rate?
- Donald
For those not familiar with this project, this is the construction of new turnarounds for US 281 at Hwy 46 in Bulverde. The contractor out there is CRG, and should have finished up about a year ago. To be frank, since this project started an entire commercial development - including a Wal-Mart store and its surrounding infrastructure - has been constructed.
Unfortunately we don't have a good answer for why the project has progressed as slowly as it has. We've been working to encourage CRG as much as we can, including assessing liquidated damages for late completion of the project.
The good news: our current schedule shows we should be all done out there before the start of the school year.

Tuesday, April 19

Mail Bag: Questions on city and county projects, work on northwest side

What are the plans and ETA of the Potranco Road expansion and connecting of Hwy 211?
- Noel (via Twitter)
Great question, Noel. The Potranco Road expansion between Lp 1604 and Hwy 211 is being done as a pass-through project and is overseen (actually, pretty much completely managed) by Bexar County Public Works. According to their project page the project just got going and will wrap up the end of 2018.
As for details on the project as it continues ... those questions should go to Bexar County. When the project is finished, TxDOT will maintain responsibility for upkeep.

Can you give us an update on the Tezel/Grissom construction?
- Jeremy (via Twitter)
If you're asking about the work Tezel Road, that's a city project and they have updates posted on their Web site. If you're asking about the work on Culebra Road ... well, that's ours.
On the Culebra project our crews are laying the final surface of asphalt. We're all done with the curbs and medians (and have been since around Christmas), and as long as we get some dry weather we could be done in as little as three weeks of solid work.

Yesterday on Blanco & Midnight Drive there was a long progression of traffic cones (3' high ones) that seems to stretch for miles north (didn't confirm but it was definitely more than a mile. I don't see any scheduled construction on your blog. Can you shed any light on this?
- Shawn (via Blog)
We got a few calls on this one, and we're still scrambling to find a clear answer. We checked with Bexar County, who maintains this segment of Blanco Road, and they don't have work at that location. That leaves possible suspects as utilities companies like CPS Energy and SAWS.
One thing we do know is the project isn't a TxDOT project - last year the state handed over control of Blanco Road north of Wilderness Oak to Bexar County Public Works.

Are there any plans for (FM 471 or FM 1560) or a signal on FM 471 at Stillwater Ranch?
- Pete (via Twitter)
The short answer: YES.
Longer answer ... well, we're working with the county on several options. For FM 471, we have plans that are more impending. That work will be done as a pass-through project (just as Potranco Road is being done) and Bexar County will manage that work. That expansion is a $16.8 million project set to start later this year and wrap up (most likely) early 2018. It'll expand FM 471 to match what's there by Taft High School and extend from FM 1560 almost to Talley Road. More info is here.
As for FM 1560, we're working on an expansion project to run from Galm to FM 471. A firm timeline isn't ready yet, but it'll expand FM 1560 to two lanes with a center left-turn lane. We also know there's a need for expansion between Galm/Shaenfield and Bandera Road, so we're looking at that. The biggest challenge for that will be right-of-way acquisition (which hasn't yet begun).

Once the new overhead connector between 1604 and 151 eastbound is complete, will cars using it be able to exit at Wiseman or will the first available exit be beyond that point?
- Bob (via blog)
In short, you'll use the next exit (Westover Hills) and turn around to get to Wiseman from Alamo Ranch Parkway. Because pictures are worth a thousand words, here's a look (it helps to click on the image and make it bigger):

So excited about the highway opening! Wondering if you know anything at all about what the process looks like for getting the addresses changed to 1604 now that it's complete. Thanks!
- Jamye (via blog)
We actually don't know the process - it's odd. We made several calls to the folks in our department and the overwhelming consensus was to work through your local Postmaster General. There is an interesting blog post on the topic, though.

Have surveys been done to figure out why the (morning) rush hour traffic eastbound I-10 from Fair Oaks Ranch Parkway to around Camp Bullis, and the (evening) rush hour traffic on the westbound side anywhere from UTSA Blvd to La Cantera through Camp Bullis is as terrible as it is? ...What is being done to alleviate that traffic?
- Gerard (via blog)
If you're asking if we've been conducting traffic studies along that corridor, the answer is yes. To put a not-too-fine point on the issue, the real cause here is a rapid increase in development and population along the I-10 corridor.
We've got an active project converting frontage roads between Dominion Drive and Boerne Stage Road, which includes some ramp rearrangements that will help traffic flow once the project is done later this summer.
But that's probably not going to fix everything you're talking about - which involves pinch points at Loop 1604 and at Camp Bullis. One fix that's coming for that is an expansion of I-10 between La Cantera Parkway and Ralph Fair Road. That's coming next year, if all goes well. As for improving the interchange at Loop 1604 ... well, we're working on that one.

Thursday, February 18

Mail Bag: Safety cables, sidewalks and traffic signals - and a whole lot more....

I was wondering when the median cables on I-10 between the Bexar County line and Leon Springs would be repaired. Quite a few are down or are bent. When they are like that is does not seem to protect like they are supposed to. Thank you.
- Michael

Michael, thanks for your note. We have similar issues with our new cable median barriers along Hwy 151 as well - they've become victim to car crashes. We are issuing work orders as quickly as we can to get these barriers repaired.

Just how important is the safety of the Schertz residents during the construction of these sidewalks (along FM 3009)? How rude can the construction crew be and how much screaming are they allowed to do at pedestrians who are trying to walk to work safely? My son, walked on the dry sidewalk for safety reasons, was screamed at to get off, and almost hit by two cars. The construction along the entire length of FM 3009 is so messed up, no safe place for people to walk safely along the road now exists. At least before the sidewalks began it was possible for people to walk to work and not be hit by oncoming traffic. Now the only options are to get hit or get screamed at. Your construction crew have no right to be screaming at anyone. Let them work in the street so the pedestrians may safely walk. They owe many, many apologies! Even as a driver who had to pull over into one of the closed lanes I was yelled at. We don't need sidewalks this badly, if this is how we have to get them. Send your crew packing!
- Therese

Therese, thank you for writing. I hope you'll note we did our best to keep your whole message to us intact - we want to be fully transparent here. We did edit for clarity of your issue.
Let us first apologize for the way it appears you've been treated. We will discuss the matter with our contractors - they need to be better ambassadors than that. Courtesy should be held at all times, by all parties.
That said, we should address a few issues. First, at no time should any vehicle ever pull into a lane closed for use as an active construction zone. This is a serious safety hazard. While drivers who do so absolutely do not deserve to be verbally accosted, they are rightly asked to move along by construction crews. Let all other drivers take note: pulling over into a closure area is unsafe and should never be done. Look for an empty parking lot to pull into if you're looking to pull over for any reason whatsoever.
Prior to this project starting no safe route to walk along FM 3009 existed. The purpose of this project is to create one. While concrete may appear to be dry, it was likely a fresh pour from the prior day or two. While walking on the sidewalk may not leave footprints, it's still not an opened sidewalk. It's part of an active construction zone and is dangerous to walk in.
To be clear: no pedestrian should ever walk in or through an active construction zone except where a specifically marked pedestrian detour route has been laid out. In this case, no pedestrian detour route was put into place because the area had no prior pedestrian facilities. That said, we can look into options to help that situation out so your son can reach his destination as intended.

Any plans to relieve the congestion on FM1560 between Bandera Road and Shaenfield Road?
-Zane
In a word: yes! The problem is funding. While we don't have anything programmed for that area right now, we do have this on our radar. In order to accomplish that we'll need to acquire right-of-way and go through the whole process of designing and public meetings ... we're a few years away.
Here's the good news: the work on Lp 1604 is only a few short months from finishing up, and a lot of the excess traffic that's on FM 1560 to escape the construction delays will return to a much more efficient Lp 1604 at that time. While that should help, it won't solve anything.
Which is why we're working with the city of Helotes to find a way to expedite work that otherwise may wait five years or more.

Regarding the eastbound I-10 on-ramp from Scenic Loop Road, the ramp seems too short and barricades block the shoulder so merging traffic doesn't have space to speed up. Can anything be done to help?
- Resident
Truthfully, the ramp hasn't changed in length whatsoever - it's been untouched in our traffic control plan for the reconstruction of that intersection. The concrete traffic barrier was placed at that location due to a drop-off that would be a serious safety issue, so moving the barrier isn't a viable solution. That said, we'll keep a watchful eye out to see if there are any issues we can address during the construction phasing to improve the area and ensure drivers are able to adequately speed up to the posted limit of 70 miles per hour prior to needing to merge.

I realize that it's always been two lanes of Boerne Stage Road under I-10. That's the problem: two lanes is not enough with current traffic loads. When does TxDOT plan to open up all four lanes under I-10? That would greatly relieve the current traffic nightmare there.
- Andy

You're absolutely right, Andy. Having all four lanes open will help. That's why we're building them! We're hoping to have some more lane configurations open up along that whole project next month. We'll have more on the blog next week to describe what all is happening and what folks in the area may expect.

What's going on with the traffic light at New Guilbeau and 1604? Why was it out for so long?
-Zane
For those not familiar with the area, Zane is referring to a malfunction of the signal control box that occurred late Monday and wasn't fixed until mid-morning Tuesday this week. Such a delayed response is highly uncharacteristic, and is partly due to the project staff not even learning about the malfunction until Tuesday morning. Once the malfunction was discovered by project personnel they had crews in place to address the issue within a few short hours.
Several folks - some of us here at TxDOT included - were caught in the traffic delays and spent as much as 45 extra minutes to get through New Guilbeau Road that morning.
The good news: lesson learned. We were able to get officers on site relatively quickly Tuesday morning to direct traffic. What's more, we've got methods in place to be more diligent about inspecting these signals, even during holidays. We shouldn't see this problem again.
Better news: we should all be driving on the overpasses and expressways before the school year lets out, so this sort of thing won't be such an impact should it happen again in the future.

Will there eventually be a better way to get on Wurzbach Parkway going east from 281? Right now, you have to do the turnaround to get to the east entrance.
- Pam 
Pam, you must be talking about the southbound US 281 to eastbound Wurzbach Parkway movement. Honestly, no - this is the configuration we've had planned for years. Because of the proximity to the airport we can't build the much taller direct connectors (requiring at least two additional levels of roadway, increasing our elevation by some 60 or more feet) that would ease that movement. What's more, we simply don't have the $500 million in the bank to construct direct connectors for Wurzbach and US 281.
So, for the foreseeable future (10 years or more), the current arrangement is what we'll have out there for you - just as we'd discussed from day one with the project.