Showing posts with label Loop 1604 northwest. Show all posts
Showing posts with label Loop 1604 northwest. Show all posts

Monday, August 17

FM 1560 Widening Project: Upcoming Traffic Switch

 We are continuing to make progress on the FM 1560 (Hausman) strip between SH 16 (Bandera) and LP 1604. As you may have noticed, the north side of the project is near completion. Looking over the work zone barrier, you will be able to see a fresh, smooth blacktop surface with new curb and sidewalk.  

It’s time the contractor turns their attention to the south side of the project. In order to do so, traffic must be switched to the newly paved surface between Magnolia Way and LP 1604 as highlighted in the image below.


The traffic switch will take place on Monday, August 24th.

Necessary improvements to the underground storm networks along the centerline of the roadway force us to eliminate the continuous left turn lane within those limits. 

However, you would miss it only temporarily. The contractor predicts that the opening of a continuous left turn lane would follow this change within a month and a half.  

We do understand the inconvenience eliminating the continuous left turn lane would cause. We have taken proactive measures and brainstormed all plausible alternatives but have concluded that it is the fastest and safest option moving forward for both the contractor and public.

Please note that this switch is weather permitting and subject to change.


Thursday, August 2

Update on Loop 1604 construction

If you hadn't noticed by now, there is quite a bit of construction on the northwest side of Loop 1604. Here's an update on some changes and closures you need to know about. We apologize for the inconvenience. We understand that no one likes construction. But we are trying our best to get these projects completed and traffic flowing. We appreciate your patience greatly!

Loop 1604 - Culebra Road to Potranco Road
If you are not a follower of TxDOTSanAntonio on Twitter you missed a tour of a traffic switch scheduled for this Saturday between 6 a.m. and 12 noon on Loop 1604 SB between Culebra Road and Military Drive. Have no fear, you can check out the video here.

Loop 1604 - Potranco Road to US 90
Tonight we do have a full mainlane closure at the interchange of Loop 1604 at US 90 for a deck pour for the southbound/eastbound direct connector. The closure starts at 9 p.m. and will wrap up by 5 a.m. DETOUR: Northbound traffic will have take a right onto the eastbound frontage road and then enter US 90 eastbound mainlanes; continue on US 90 to the Military Drive exit and take the turnaround and re-enter the US 90 westbound mainlanes and exit Loop 1604 and take a right onto the Loop 1604 northbound mainlanes.

Loop 1604 at SH 16 (Bandera Road)
The westbound frontage road turnaround will be closed starting on Monday, August 6th at 5 a.m.  This closure will be approximately 4 months in duration. The turnaround is being closed to allow for modification of the turnaround as part of the current project that will provide intersection operational improvements at this busy intersection by utilizing an innovative traffic engineering solution described as Displaced Left Turns (DLT). In a DLT, left turn traffic shifts to the left side of the road. Left turns are “displaced” at a new crossover signal prior to the frontage road intersection.  

Monday, May 21

Mail Bag: Why we use asphalt and not concrete

What work is currently happening at the turnaround by Ramsgate? Currently seeing it closed daily during the day.
Also, huge props to whoever finds the gifs for the blog!
- Kevin
Well, shucks. Thanks! We have fun with the gifs (and other graphics and references). We hope all y'all do as well.
The work at Ramsgate is a maintenance job to repair the concrete retaining wall and the bridge rail at and near the turnaround bridge. The work should be wrapped up by the first part of June. We know it's throwing off a few folks and their commutes - all highway maintenance tends to have that effect - but we're working hard to stay in touch with the USAA communications team to keep them in the loop. They are the top contributor to the traffic at the turnaround, after all, so we're doing what we can to coordinate the work with the good folks over there.


I travel Wurzbach Parkway to work. I see signs that talk about road closures beginning May 14. Can you tell me what to expect next week. Should I use 410 to travel to work?
- Rebecca
Rebecca, we're sorry this answer didn't come in time. We understand the work on Wurzbach has wrapped up at this point.
The closure was on Wurzbach Road and was done by the city of San Antonio, not us. They did a heckuva job getting word out and tried to be sure folks knew in advance of the closure.


Have they determined what caused the longitudinal cracking on I-10? I'm no engineer, but from the photos, it looks like when the contractors excavated material from the roadway edge, they failed to support that edge as it bore the weight of the Jersey barriers. Recent heavy rains probably didn't help either, eroding the exposed base material and surrounding soils.
- Mark
You kind of hit the nail on the head, Mark. The contractor is using, per plans, soil nail walls to support the edge of our excavation. In this instance the equipment for those soil nail walls bogged down and Flatiron's excavation team got a little ahead of things. This is a gamble literally every contractor takes on a project like this, and more than 99 percent of the time it pays off and we see no problems.
As you pointed out the rain didn't help here, and we saw a failure. It wasn't catastrophic, but any failure has potential of becoming that way. We worked hard to prevent the catastrophic failures that could have caused safety hazards.
Here's the silver lining: the delay is extremely minimal. Flatiron lost about a day and a half of production and that's it. On a three-year project that's amazing.
The long-term, permanent fix for the issue is literally designed into the construction plans. When it comes to roadway failures on a construction project, this was pretty much the best possible scenario.


Regarding the nearly complete NE 410/35 project between George Beach and Walzam, I give the project an A-. I no longer fear for my life on south bound lanes as the Rittman traffic no longer tries to zip across 5 lanes of traffic to get to 410 South and traffic seems to move pretty well through that section (the clog is now between Walzam and O'Connor on Northbound).
My only complaints are minor and as you have pointed out before, not necessarily needed. That is the street lights. Many in that section still don't work and one pole in front of Texas Thrift blinks constantly. And having some sodium lights and some LED is kind of tacky. Other than that, great job on this project!
- Jeff
Thanks, Jeff! We'll take it!
It kills us the project took as long as it has to finish, and we've done some internal reviews to see how we can prevent a lot of the delays we've seen on the job for future projects.
Having the new lanes open has been a huge milestone for us - and the big reason for the job in the first place. Well, those and the ramp revisions we've done along the corridor. With a little luck we'll have everything in place and be done - like done done - by mid-summer.
The includes the lights which, as we've said, will be burning as soon as we can get them connected to power. Thanks for your patience on it!


I know there a lot of construction going on 1604 between 90 and 151. Same thing for almost every intersection that have lights except Wiseman. It looks like they are not working on it and look pretty much the same for like couple months. Any idea what going on?
- Daryl
We had some work on retaining walls and drain structures that kept us from digging into Wiseman the way we've done at the other intersections over the last two months.
That will change here in the next couple of weeks, and southbound Loop 1604 will switch onto the frontage road just south of Hwy 151 here in June. That will let Zachry Construction go nuts on the new overpasses. Once the new southbound overpass is ready we'll flip traffic over - Zachry has been working on ways to provide incremental improvements to traffic as they're available (Webber also) on this project, effectively fast-tracking an already aggressive schedule.


The WB I-10 frontage road closure at Old Fred has caused the traffic to back up at the Fair Oaks Ranch bridge almost a 1/4 a mile. Having one exit/entry for 4 major neighborhood was the worst idea ever. Please open up the frontage road M-F 7-9am and 4-6pm. What is being done to alleviate this? This cannot be the norm for a month or more.
- Christina
This closure HAS to be a constant closure. Opening intermittently as you've suggested simply isn't physically possible. To install the pipes we're putting in the ground the road itself was torn up for about 500 feet.
Sundt is working to get this work finished quickly and should have it open by the end of this month. We know it has been really, really rough this month and we thank everyone for their patience.


In your May 1 post, you talked about the traffic lights, but since you were talking about Buckskin, were the lights there? If so, what about the Fair Oaks Parkway lights?
Also, you talked about quadrants and stages, neither of which means anything to me without a definition. Also, the map showed some orange sections of roads with some white markings around them. What do they mean?
- Al Koppen
We are building traffic signals at Buckskin Drive. The construction contract doesn't have us turning them on - that will fall to our traffic operations folks.
Sounds convoluted, we know. It has to do with the warrant for the signal, which you can read all about here. Right now we don't have a warrant for the signal - mostly because the intersection doesn't completely exist. Once the intersection opens we're confident the warrant will be met, but we technically have to wait for that to happen.
Traffic signals are indeed being built at the Fair Oaks Parkway intersection and will become active here in June (based on the current schedule). The signal configuration will be identical to that of the current Ralph Fair intersection.
As for quadrants and stages, we apologize if that graphic wasn't clear enough. Here it is, once again, for your benefit:
The orange areas are the areas where work is being done. You'll note the white/orange markings are construction barricades, indicating the area is blocked off for construction.
Every intersection mimics the x-and-y axis planes we learn about in math class growing up. Each intersection has four quadrants. In the graphic to the left, these are labeled as Quadrant I (quadrant 1), Quadrant II (2), Quadrant III (3) and Quadrant IV (4). The first quadrant is where the X and Y axes both have positively valued coordinates. The second quadrant is where the Y axis coordinate is positive but the X axis coordinate is negative. The third quadrant features two negative coordinates and the fourth quadrant features a positive X axis coordinate and a negative Y axis coordinate.
Most of the time, when we talk of intersection quadrants, we talk in terms of direction so we can keep things simple
 For the intersection of Old Fred/Buckskin Drive and I-10 that means a north quadrant (where the work is happening right now as noted with the long horizontal orange mark), a south quadrant (basically between Buckskin Drive and Indian Hills), an east quadrant (the one that was closed for like four months) and a west quadrant (the one we opened up most recently).
We're sorry this description wasn't clear enough in the first post and hope this explanation helps you keep everything straight.


Regarding the 10 east frontage rds. In particular the frontage road intersection with FM 1516 and Green Rd:
It seems this one-way conversion has greatly inconvenienced people that live and work on Green Road. I often see people going the wrong way on the access road the short distance to 1516 so they can use the underpass to go west on 10. There is also a large dirt area in front of the truck dealership that has become an impromptu thoroughfare to cut over to 1516 from Green Road in addition to cutting through the truck dealership parking lot.
Is there a solution or idea in place to alleviate this inconvenience?
- Marshall
First of all, shame on all those drivers who are making illegal and, more important, unsafe driving decisions. Seriously - all that is to save what, two minutes of drive time? Five?
The long-term fix is to complete the project. That'll open the frontage roads to two lanes (still one-way) and an increased traffic volume here will prevent this heinous behavior. The wider frontage roads will mean effective turnarounds and an easier path to get to the main lanes.
In the meantime, stepped up law enforcement may help those sacrificing the safety of everyone around them for their own convenience make better choices.


I noticed all the new overpass additions/reconstructions have been done with concrete main lane approaches (Old Fred Rd/Buckskin and Boerne Stage/Scenic Loop. Why isn't the entire project from Ralph Fair to La Cantera not being completely converted to concrete? It lasts so much longer with less maintenance. This patchwork appearance looks cheap and out of date.
- Pete
You're absolutely right, Pete. Concrete paving has a better lifespan, requires less maintenance and has a bit simpler repair than traditional asphalt roads.
They're also exponentially more expensive up front.
There's a definite case to be made the cost for concrete paving is lower in the long run - say, over a period of 30 or 50 years - but that doesn't help us get the project done today.
The business savvy folks out there can see the difficulty here. In many industries it might make sense to go with the larger up-front expenditure to save money over the course of time. If we met our break-even point in the next three to five years the concrete option would probably make sense on all our roads.
That's not the case, though. Right now, as inexpensive as asphalt is, the break-even point is decades away.
Bridges and approaches have been and will continue to be done with concrete for a number of reasons. On stretches of road built on top of ground we can use the traditional asphalt, so that's what we're doing.


What happened to the project guide tour for the 410 to 151 flyover that was supposed to be out on Thursday per the report?
- Chris
We did it! We have it posted on YouTube as well. Take a look - although everything you're seeing is now wide open and in use (Chris wrote us a couple of weeks ago).


Someone posted this question on nextdoor.com, and I am curious as well (and would like the correct info instead of people's opinions on social media):
Anyone know why the several miles of asphalt that was laid down between Boerne Stage and La Cantera mall was all ripped out? Also, any idea how far back that puts the construction timelines?
- Leslie
We asked our project staff about this question and they said they don't have a long stretch of asphalt we've torn out on the main lanes of the highway. We think he question is likely a reference to asphalt laid down during a previous project. We've taken out parts of the shoulders to tie the existing road with the expansion to the inside and the outside of the road.
We've also got some spots we're putting some temporary pavement on each side of the road so we can shift existing traffic lanes over to give our crews some elbow room to safely build what we're building.
This project - to widen I-10 between La Cantera Parkway and Ralph Fair Road - is still running on pace to finish up early 2020. We've not had anything that's pushed our construction timeline back - not even the asphalt issue from earlier in the month.

Wednesday, May 2

That other direct connector is about to open (and other fun stuff)

Pardon our shameless cliffhanger, but we won't get to the good stuff until later.
This morning's conference call revealed some big-time closures over the upcoming weeks. We'll give you the Cliffs Notes from what we had:


I-10 at Camp Bullis
Full closure of the westbound main lanes beginning Friday night, May 18, and continuing through Monday morning, May 21. We'll have a full closure of the eastbound main lanes June 1-4. During both closures we'll have Camp Bullis closed under I-10.
These closures are to set bridge support beams for the expansion of the main lanes. Traffic will exit Camp Bullis, continue through the intersection and re-enter the highway.
We are ensuring proper coverage by off-duty police to control traffic at the Camp Bullis intersection.


US Hwy 281
On the southbound frontage road of US Hwy 281 at Loop 1604, the left-turn lane will remain closed continuously through May 26. The south-to-north turnaround remains open.
This allows crews to work on bridge support structures overhead.


I-35 at New Braunfels Ave
We have one more bridge pour coming, but no timeframe yet from the contractor. We're working to get that so we can get the notice out and finish this project up.


Loop 1604 northwest
Expect routine overnight closures at Wiseman Boulevard while crews reconstruct the intersection and install new signal poles.
Nightly closures of the US Hwy 90 main lanes at Loop 1604 will happen through the next week or so; we'll also close nightly the west-to-east turnaround at Loop 1604. All this is for bridge work.
By the way, that little spot on the northbound main lanes of Loop 1604 just north of Marbach, where traffic squeezes down to a single lane, should open back up to two lanes by the middle of May. Webber Construction ran into a utility conflict while doing some road expansion work and have gotten that conflict resolved. Look for that to open up and provide the relief folks have clamored for by the middle of this month.
Also ... that south-to-north turnaround at US Hwy 90 should be opened by the end of the month. We know it's a month later than we'd hoped; we ran into some issues with the new traffic signals system.
Thank you for your patience on this one, and thanks for not breaking out the hammocks when stuck in traffic.


I-410 at US 90
No major closures happening beyond the nightly closures of all main lanes of I-410 at US 90; we should be done pouring concrete there by the end of next week if all goes well.


I-35 SAMMC
Overnight work continues to finish the overhead highway lights mounted to the center median. We're also working on some ramps and the frontage roads. All of this should only impact overnight traffic.
On the bright side, Lane Construction is saying they should be finished with all work by the end of June.


I-410 at Hwy 151
Here's the big one:
The new eastbound Hwy 151 connector to northbound I-410 will open this weekend.
That's right; it's happening. And it's happening much earlier than expected. The overall project completion wasn't set to happen until the end of this summer ... but we're seeing enough light at the end of the tunnel to believe we'll have this one knocked out by mid-summer at the latest. We even reported an estimated completion of this one direct connector as the end of this month when we toured the project with our staff last month, and we still beat that expectation date.
If you ask us, that's pretty cool.
Of course, in order for us to get that connector opened up we'll need major closures on eastbound Hwy 151 and northbound I-410 starting Friday night and wrapping up by Monday morning.
The bottom line: Monday's morning commuters won't have to go through the intersections of Hwy 151 and I-410 or of I-410 and Military Drive to reach the northbound lanes of I-410. Traffic will be in its final configuration instead.
This leaves one last spot of work for the project: the southbound I-410 entrance from Culebra Road. You'll see increased effort on that ramp and should see it open up by the end of June if all goes well.
Once that ramp is done Williams Brothers will go back and lay the final surface of asphalt for the project. Yes, traffic is in its final configuration ... but the road surface itself isn't final. Please don't call us to tell us how bad it is - it's temporary until the project is finished.

Mail Bag: Apologetic replies to some tough questions on I-10 at Scenic Loop, Camp Bullis and on Loop 1604 at US 90

Last the Hillcrest residences saw on this blog was that there was going to be a temp turn around (to get Northbound on Lp 1604) between Marbach and
US 90 by mid April and the permanent turn around by the end of April. Are we still on track for those completion dates?
- J Sutfin

Clearly that didn't happen by the end of April, as we're now in May. Webber Construction is now saying they'll have it ready by the end of May.
Webber encountered a conflict with a signal pole and a drain structure when building and had to make some adjustments to the plans. They've also had some struggles with the signal control boxes that are now being fixed.
The new northbound lanes on Loop 1604 have been paved but need the signals to be operational before we can move traffic over. We're waiting to switch traffic to build the new turnaround.
It's all contingent, bottom line, on the signals. We've had our electricians at work on the issue through the last few weeks, and we're confident we'll get it done before the end of may.
Were it not for the conflict we didn't catch in the plans, we'd have had this set and ready by now - we do regret the delay and understand the direct impact it has on the lives of those in the Hillcrest subdivision.


Did you really think closing ALL of I-10 was a good idea? We will be avoiding Texas on our way back from Florida, and I hope somebody gets fired! Nobody else does this stupid stuff and then posts "Sorry".
- Roy

You guys close I-10 by Camp Bullis on a weekend? I had to pass by there this morning around 8:45 and no one is working. I passed by there again around 10:30 and 12:00 and still no one is working on the highway. How can you close I-10 on an weekend and no one is working on the construction?
The only people that were there were some cops helping direct traffic?
- Marc
I-10 Closure at Camp Bullis -- You have the lights set at Camp Bullis on flashing Red effectively running and entire interstate trough a stop sign. Can we please get a flashing yellow to keep the flow moving and not have all complete stops. The cross road under the bridge is closed so flashing yellow is more appropriate.
- Tim
First of all, we're always - always - going to have a major closure like this over a weekend rather than do it during the middle of the week. Full closures of the highway are a very normal thing across the United States as we safely construct the roads. We say "sorry" because we know it's inconvenient and we want to recognize the frustrations of others. Sorry, Roy, but nobody got fired over having that closure that was planned and publicized.
We were supposed to have officers directing traffic at the intersection to keep traffic flowing. We understand there was a small gap in coverage on that during a shift change; we've since addressed that issue (one that's unacceptable to us as well).
The bottom line: the closure was necessary (and it's something you'll see happen again as the summer nears). It's also something we know how to do well, and we know the hang-ups weren't reflective of the job we know how to do. We'll do better the next time.

WTH is the delay on the work under I-10 at Scenic Loop? They just completely stopped the work months ago, and now they just push dirt around occasionally. I was by there this past week and I saw a worker literally sleeping in his work truck.
- Joe (via Facebook)
Joe, to quickly recap the way this project has gone we started with working on the storm drain system, installed drain inlets, tore out the old roadway to rebuild it then build curb and sidewalks. Some of that work is more visible and obvious than other work is.
Right now the weather is the determining factor on when we'll have the final surface of asphalt in place - if we have dry enough weather we'll be able to lay asphalt this week. That means we'll have it all striped by mid-May and be out of the way and gone.
That, of course, depends heavily on weather. We can't very well lay asphalt or paint in wet weather.
As for the guy in the truck, there's a good chance he was doing paperwork and looked like he was out cold. Our inspectors office out of their white TxDOT trucks and can often be seen with their head down while working on their project paperwork.
That said, if you ever do see any of our guys, in their white TxDOT trucks, sleeping while in their trucks please let us know directly. Unless it's during the normal lunch hour timeframe - those guys work long and hard hours and may be taking a much-needed power break, but we need to make sure they're doing the jobs they're paid to do.

Friday, April 6

Major closures to watch for this weekend

The full closures report will come later - likely late tonight - but there's a slew of closures happening this weekend. These are the types of closures folks like to know about well in advance.


I-10
We'll have full closures of I-10 on both sides of San Antonio. Those passing through the region ... well, we're sorry. Both closures start 9 p.m. Friday and will wrap up no later than 5 a.m. Monday. We're hoping things don't go that long, but folks should expect it.
On the east side of town the closure will be the main lanes at Foster Road. We'll have traffic exit Foster Road, pass through the intersection and re-enter the highway. Thing is, the frontage road is just a single lane through this area. Expect this to be pretty slow in both directions.
On the west side of town the closure will be the main lanes at Camp Bullis. We'll have traffic exit Camp Bullis, pass through the intersection and re-enter the highway.


I-410 at Hwy 151
Another full closure of the highway ... this will allow crews to set bridge support beams overhead. The good news: this one is overnight only, so daytime traffic will be unaffected. This is 9 p.m. until 5 a.m. each night. That's Friday night, Saturday night and Sunday night.
Since we'll have the main lanes closed, both ways, at Hwy 151, we'll exit all traffic at Hwy 151. Traffic will move through the intersection then re-enter the highway.


Hwy 151 between I-410 and Hunt Lane
So ... we have a lot of work going on at this interchange. The good news: when we're finished with the work on Hwy 151 this weekend traffic will be in its final configuration - minus the new direct connectors - and we'll be all but finished with construction on Hwy 151 through here. Daily commutes are about to get that much better.
Beginning Friday at 9 p.m. and running until 9 p.m. Saturday we'll have the westbound main lanes closed to restripe the road and remove barrier. Traffic will exit Hunt Lane, move through the intersections and re-enter the highway at the next available ramp.
Beginning Saturday at 9 p.m. and running until 9 p.m. Sunday we'll do the same thing on the eastbound side. Traffic will exit I-410, pass through the intersections and re-enter the highway at the next available ramp.
We'll have officers on hand to minimize the impact of traffic being diverted from the I-410 main lanes.


Northbound I-35 to westbound I-410
There are two interchanges with I-35 and I-410, and it can be confusing as to which we're talking about sometimes. To clear that up, just think of the Windcrest area near Thousand Oaks and Walzem.
We'll have the northbound I-35 exit to westbound I-410 closed all weekend. The closure will start 9 p.m. Friday and wrap up no later than 5 a.m. Monday.
Traffic will need to head north to Weidner and turn around to reach its destination. There are a few other ways to get around this closure, but that's the easiest to describe. If you're a local resident and know a better way, feel free to use it.


US Hwy 90 at Loop 1604
We're working hard to reconstruct the intersection of US 90 and Loop 1604 right now, including getting the new northbound Loop 1604 bridge at US 90 opened for traffic later this month. That means another in a long line of weekend-long closures in this neck of the woods.
The westbound US 90 frontage road will close 9 p.m. Friday and reopen by 5 a.m. Monday for this reconstruction. Traffic will head out on the main lanes to Montgomery, then turn around and head back to Loop 1604 to get where it needs to go. This includes folks headed to Kriewald from the main lanes of US 90.


Frontage road long-term stuff coming
We have two spots with long-term frontage road closures about to begin. Both are on I-10 between Loop 1604 and Fair Oaks Parkway.
The first is the west-to-east turnaround at Camp Bullis. That'll close Wednesday morning, April 9, and remain closed through mid-May. This is the first in a series of turnaround closures between Camp Bullis and Ralph Fair, so expect your turnaround closure to come up pretty soon if this one doesn't impact you. Without the turnaround, of course, traffic will simply use the signalized intersection to do its thing.
The other is the westbound frontage road - well, the frontage road on the westbound side - at Old Fredericksburg Road and Buckhorn Drive. The good news: that spot that's been closed is finally opening up over the weekend (we're told).
That means we'll need to work on another quadrant of the new intersection, which will start Monday morning. That new quadrant is that little slot on the Fair Oaks Parkway side of Buckskin Drive along the eastbound main lanes.
Sundt Construction is telling us they have significantly less work to do on this quadrant so it won't be a several-months-long closure like the last one was. They're talking about 4-6 weeks to do the work they need to do.