Thursday, May 31

Mail Bag: Chrostopher and AJ discover our Mail Bag....

When will you address the absolute nightmare at Fair Oaks Ranch bridge due to the closure of the frontage road? What is the progress of the work being done at Old Fred? You have been radio silent these past two weeks despite numerous calls.
- Michael
Where are the police that have been helping direct traffic on the FOR bridge during rush hour? They have disappeared this week this causing major delays once again. If I can’t get to work, I can’t pay taxes to fund this disaster you call road construction.
- Tina

So ... truth. We have received a number of phone calls and emails about the Fair Oaks Parkway overpass. On our end, we take one or two of those and reach out to project staff to have the issue addressed. We file away those couple of communications - and the dozen or more that follow - and move forward. We work to communicate as much as we are able, but cannot always keep up with the demands of some areas in our 12-county district.
We apologize that means the Fair Oaks community felt we were ignoring them. We assure y'all that was absolutely not the case. Our communications team simply has a larger swath of area to focus on - 12 counties! - with similar communication demands and we work hard to try keeping everyone we can in the loop on their projects.
All that said, a good bit of the issues y'all were seeing should have calmed now that Sundt has finished work on the frontage roads requiring the closure that complicated that area. What's more, you're about a month from being finished totally with work at the FOP intersection itself. We hope to have the frontage roads converted to one-way soon, which will open up the capacity of the frontage roads. It'll also mean the new exit ramps will be open, storing the traffic waiting at the FOP intersection onto the frontage road and getting that traffic off the main lanes.

Not a question today, just a compliment. I travel west on 151 every morning (between 0610 and 0710) and since the new flyover to NB 410 opened, it has been much less congested just as your folks planned. Thank you! It has reduced my commute time as well as any stress. I'm sure it will also improve safety in the area. Thanks again!
- Roy

We're as glad as anyone to see a plan work out! We're hoping to see a similar improvement when the direct connectors at I-410 and US 90 are finished in the next 18 months or so. We're getting so close to all that happening!
Also, Roy, thank you for reaching out. Comments like these really mean a lot to our guys in the field (and yes, they do actually read these posts)!

I have a plethora of questions! Now that I found this page I'll probably be emailing you a lot! (Sorry in advance).
151/ Alamo Ranch: I just read on one of your blogs that ARP is owned by the city and not the state, thus y'all (basically) have nothing to do with it. Yet, I have also know that SH 151 is potentially planned to extend to/ through SH 211 AND that ARP is basically built as future SH 151 access roads. So... I don't get it. Is TXDOT planning to in the near (or distant) future acquire/ incorporate ARP into 151?
SH 211: Are y'all at least considering extending SH 211 north to I-10 and south to 35? I think it's phenomenal that there is this active planning to acquire right of way and build this highway AHEAD of the growth, knowing the highway will be desperately needed in the near future. However, it seems like it could never be realized to its full potential/ usefulness without these connections (especially to I-10). Would an extension to I-10 be incorporated into or connect to the future highway planned as part of the "Kendall Gateway Study"?
- Christopher

We're excited for the plethora - and we hope to answer them all! We make one simple promise, Christopher: we'll be direct and honest. The answers may not be what folks love to hear, but they will be completely and unabashedly truthful.
On to the questions you've got. We'll start with the Hwy 151-Alamo Ranch Parkway question.
It seems very logical to continue Hwy 151 through Hwy 211 following the path of Alamo Ranch Parkway. However, that's not the case today. Frankly we've been working to get lane-miles off our system wherever possibly rather than adding roads to our grid.
That said, if the county (owner of ARP right now) includes the turnover of ARP to TxDOT as part of a larger transportation funding strategy in the future we would be happy to listen. Something like that would require a lot of folks to say "yes", though, including (but not limited to) the Alamo Area MPO, Alamo Regional Mobility Authority and the Texas Transportation Commission.
But as of right now, today, this moment ... us taking on Alamo Ranch Parkway isn't something we have written anywhere in our scheme.
As for Hwy 211 ... right now Bexar County Public Works is working to connect Potranco and Culebra roads. Beyond that ... we haven't had any detailed conversations at this point. Our recommendation if you feel this is a solution we should move aggressively on: get involved with the MPO and make comments at the Kendall Gateway meetings. We'll pass along the idea to our planners to ensure it's on the radar, but it's really going to take some local calls to make something like this viable.

As with all construction projects, I know things change as progress is made. What are the current timelines for the I-10 corridor projects? Namely:

  • Ralph Fair to Fair Oaks
  • Old Fred intersection
  • Fair Oaks intersection
  • activation of one-way frontage roads through Fair Oaks
  • HOV lanes (I remember reading that this project will be opened in phases with first section to take a year, but progress seems to be moving rather quickly.)
Is there a webpage where I can read about the planned stages?
Thanks!
- AJ

Hey, AJ! You've reached out via email, but we're going to answer all these questions on the blog so all can benefit. You can look at the details of what we're doing on each project online here.
As for updated timelines, this blog is the go-to source. With that in mind, here's the latest schedule:
  • Ralph Fair to Fair Oaks will wrap up this fall
  • Old Fred intersection is open for business, though we still have that signal to install and have our traffic division turn on
  • The intersection of Fair Oaks itself is set to be finished by Independence Day, but we have to wait for the frontage road conversion to open the intersection to full capacity
  • We're still nailing down a firm timeframe for the frontage road conversion and hope to have something firm to discuss next month; right now we're leaning toward opening things in four stages with the Old Fred intersection being the divider ... the determining factor will really be the new exit and entrance ramps
  • The expansion of I-10 to include HOV lanes between Ralph Fair and La Cantera is still on its initial pace; they expect to open up one lane each way as soon as 2019, with final completion and that fourth lane opened early 2021

I noticed the 2015 animated video showed two "managed lanes" on each side and the 2017 video shows one HOV. Any background on the change?
- AJ

We're guessing you're talking about the I-10 project on this. Honestly, we don't build where we're not wanted and, in this case, the local input was such that we change the plan from two managed lanes each direction to a single HOV lane and a traditional non-tolled express lane.

Why is the bridge over the Guadalupe River on 281 Spring Branch closed and when will it open again? Are repairs going to be made? Nothing has been done in weeks except traffic is now down to one lane over the River. You need to notify folks if roads are going to close.
- Trudy

We're totally reconstructing the southbound bridge, Trudy. It'll take us a while to get it all done out there - we've been trying to keep in touch with local media to keep folks up-to-date. When we shut down the bridge we found some pavement failures we didn't expect. Those are now fixed so we've moved our contractor on to the actual bridge.
As for the work ... we're tearing the bridge down to its skeleton, basically, and reconstructing everything around the frame. It won't be expanded with this one, but will be upgraded significantly.
The bridge will remain closed for the duration of work, which will be over a year.

What are the planned closures for I-10 west out of San Antonio [both NB and SB] the weekend of Memorial Day, specifically Saturday May 26, 2018 after 5:00 pm - need to get into and out of Boerne and Cordillera Ranch.
- Linda

We didn't have any closures! We actually avoid any major closures on major holiday weekends, period.
We're sorry we didn't reply sooner, Linda. Mail bag questions are collected and answered on this forum and not a place we offer immediate answers with direct emails. In the future you can check our weekly closures post online, or follow us on Twitter for real-time issues or answers.


Thank you for finally making a promise date, and opening up the WB access road at Old Fred on the 25th.
- Dave

We're as thrilled as anyone to see that kind of progress. We're hoping to keep the momentum! Right now Sundt is focusing on the new exit and entrance ramps so they can begin a successive chain of frontage road conversions. We're hoping to have all the major work done out there by the end of summer, though it's likely you'll still see equipment moving around into the fall just a little bit.
Bottom line: we're with y'all on this one. Fast is good when it comes to project delivery, and we're pulling all the levers we can to make it happen!

Is I-10 East still scheduled to be closed starting June 1? I saw something about it on your blog post from earlier in May. Just wondering if that is still the plan.
- Brad

It is - check out our latest closures list for updated plans.

Wednesday, January 25

Mail Bag: Lots of 1604 questions, 410-151, frontage roads and more

On Loop 1604 South between Wiseman and Potranco, there is only one left turn lane onto Wiseman heading east and Potranco heading east. Can you make the middle lane a left turn/ straight ahead option lane? There is a big backup on 1604 because there is only one left turn lane onto the these two streets.
- Jaime
The short answer to your question ... is no, we can't make that left through lane an optional left/through lane.
But we're not always about brevity here. We like to explain things, and you're here because you want to hear (ahem, read) what we have to say. Right?
The biggest reason for not going with the optional left-through lane (which do exist on Wiseman and on Potranco, by the way) is signal phasing. There's a whole manual for this (which you can read, if you want). These intersections are currently five-phase intersections, meaning the signals change five times each cycle. It works to maximize the flow of traffic in all directions. The five phases are:
  1. Southbound Lp 1604 (with left turn)
  2. Southbound and Northbound Lp 1604 (no left turns)
  3. Northbound Lp 1604 (with left turn)
  4. Eastbound Wiseman/Potranco (with left turns)
  5. Westbound Wiseman/Potranco (with left turns)
The cross streets have that optional left-turn lane ... the major street does not. That's by design! If we were to add the optional lanes to Loop 1604, we'd have some issues and you'd actually see greater delays. Here's why:
  1. Southbound Lp 1604 only
  2. Northbound Lp 1604 only
  3. Eastbound cross street
  4. Westbound cross street
By doing this you're lacking the major traffic movement with this arrangement - that extra phase of traffic where the through traffic is allowed to flow through the intersection. Sure, by just looking at things we'd only have four phases ... but that means you're looking at 20-30 fewer seconds given to that through traffic for each cycle. That traffic would instead simply stack up on queues on the main lanes, bogging down traffic on Lp 1604 even more.
That's why we don't do an optional left-turn lane on any location comparable to Loop 1604 here (think of Loop 337 in New Braunfels or Northwest Military at Wurzbach Parkway).
Here's the good news: you may have noticed we're working on the overpasses at Wiseman, NW Military and Potranco. It'll take some time to get to where those overpasses are in use, but they are your long-term solution. By the way, when we have those overpasses in we'll be able to employ your suggestion and move to a four-phase cycle (which is standard for expressway intersections).


One issue that seems to be ignored is the lack of a good connection for people leaving AR wanting to head north on 1604. The best way now is Wiseman, out the "back" of the area, although it is generally backed up at rush hour.
It appears to me that a simple clover, eastbound just pass the overpass, onto 1604 headed north, would solve the problem. There doesn't appear to be any right-of-way issue, when might this project be put in place?
- Richard
The issue wasn't ignored at all; the current strategy is to route traffic down to Wiseman like you're doing today. When the project was studied and designed the demand (and projected demand) for that move wasn't very high. Remember these plans go back over seven years, so a lot of what you're seeing now wasn't known of during those plans.
Once we were ready for construction, financial constraints kept us from adding more features to the project (and bridge work is really expensive).
The current option will improve dramatically when the overpass at Wiseman is constructed and, as you know, we're working on that now. When that's done (the project is set to wrap up in 2019) we'll take a new look at traffic movements to determine needed improvements in the future.


You posted some information on your blog sometime around October 2015 regarding a lane being eliminated on the frontage roads of the I-410 just north of TX-151 due to construction work. It said that work would be completed around 2017. I know there is still construction work going on around this area, however I would like to know if this lane elimination is still there or if it has been lifted. I have also pasted in the information that was shown on the blog. Thank You.
- Jay
Those frontage road lanes is still eliminated, and we're still working to fill the promise of having that lane reopened this year. That will happen when we've got the new ramps finished - a task on this project that's prioritized right now. The closures are designed to help crews widen the frontage roads and the main lanes, fitting them to new ramp configurations that are being pushed to be in place this summer (if all goes well).


Why is there no plan for an east bound exit for Boerne Stage Road? Everyone going to HEB or Walmart has to sit through the Ralph Fair stop light. I'm not surprised the bridge needed expansion but a lot of that was due to two streets worth of traffic forced to go through the same exit and light.
Could you please let me know why this is the plan?
- Reid
Right now it's really a matter of geometry. You're familiar with the area; you know the on-ramp from Ralph Fair Road (which gets more than its fair share of use) takes up most of the space between Ralph Fair Road and Leon Creek. Yes, there's a big gap between Ralph Fair Road and that on-ramp, but that's filled by the auxiliary lane allowing turnaround traffic to blend with traffic off the bridge - preventing us from moving that entrance ramp anywhere.
Those unfamiliar with what's going on out there can check out our schematic of the area here.
It's a tough situation, for sure - but not one that has been taken lightly by our folks at all. The situation will likely improve for you when we convert that frontage road between Old Fredericksburg Road and Ralph Fair Road to one-way; it'll open up some capacity along the frontage road and improve the signal operations a bunch.


We are new to the area and keep hearing rumors about SH 211 extending to Culebra. I saw something that there is a project out there that has been on and off for years. Is there anything in the future for this effort?
- Matthew
This is a discussion that's been had by the Alamo Area MPO, Bexar County and us quite a bit over the last several years. The effort is currently in the hands of Bexar County. They have information posted online here.


Bitters Road between Blanco and 281 is down to two lanes and it is a nightmare for traffic, particularly for parents and school buses who have to use Bitters to reach Hidden Forest Elementary. I have not seen any public notice about the scope of this project, although there has been intermittent resurfacing on parts of the road. What's going on right now and how long is it going to take?
- Haley
Haley wrote this in a few weeks ago. The work to which she referred was being done by the city of San Antonio.
Y'all, we know it can be confusing regarding who is in charge of what road. Heck, we get it wrong from time to time. A good rule of thumb: if it has an FM (Farm-to-Market) road designation, it's a TxDOT road. These designations feature the big white boxes with black numbers you'll see on the large green directional signs when you're running down the Interstate highways. If it doesn't have that designation, it's not ours.
If it's not ours and it's in the city limits, it belongs to the city of San Antonio. If it's beyond city limits, it goes to Bexar County Public Works.
It's tough to keep straight for us all, but we try to manage. We have cheat sheets that help, too!
All that said, the city had responded to others asking similar questions and should have had the issue resolved a while ago.


So since the new on ramp has opened on 1604 and Bandera headed west, I've seen many, many people leave the Stonefield Place street and interrupt traffic to get on the highway. The street is passed the entrance ramp so they have to drive up and cross over the 3 lanes to get on. I've seen people almost get hit several times in the last week alone. Any way something could be done to alleviate this?
- Leah
Don't let this be your commute. Be safe. Drive smart.
Unfortunately there aren't a lot of options to deal effectively with these very rude, very selfish, very dangerous drivers. And that's what they are - rude, selfish and dangerous. They are putting their own wants ahead of the safety of all of us on the road, aren't they?
Sadly, Leah, this is a driving behavior displayed all over the city. What's more, it's not even against the law (as Texas Highwayman points out) in Texas, though it is elsewhere. Here it's just an obnoxious lane change. Just because it's not illegal doesn't mean it's the right thing to do, though, and this sort of mentality has simply got to be eradicated. At this location specifically, going through that signal at Bandera only takes a few extra minutes and could extend life expectancy of they motorist by years. Decades, even. That's a heck of a return-on-investment!
We design and build the roads and include with our building a set of instructions (pavement markings, highway signs...). When those instructions are not followed, the results are almost always disastrous.
Update: Looking at this location a second time based on feedback from Texas Highwayman, we need to point out this movement is, in fact, an illegal movement. Coming out of Stonefield to get to the entrance ramp to northbound/eastbound Loop 1604 means crossing the "gore", which is absolutely illegal. And unsafe. And selfish. And reckless. And everything we mentioned above.
We can try to install some sort of barrier to stop this - like the Tuff Curb and delineator paddles we're planning to put in on Alamo Ranch Parkway near Westwood Loop, but this shouldn't be a necessary strategy.
Let us be clear: this reckless, dangerous, selfish, childish, rushed and illegal driving behavior exists all over San Antonio. We stripe the roadway to let folks know this is unacceptable, but are criticized because drivers completely ignore the striping. This leads to pressure to put up these positive barriers - which we can absolutely do, when needed - at a higher cost to you, the taxpayer, and at an absurd cost to repair, replace and maintain as we go. To see what we mean, take a look at US 281 north of Loop 1604, where we've installed these curbs and paddles to stop selfish and disrespectful drivers from doing the same thing up there. We've had to replace those paddles routinely, as drivers ignore them and figure the damage to their own car is minimal, so they simply drive over them.
Installing a small concrete curb isn't an option, either - those are only to be used on roads with posted practical speeds under 45 miles per hour. The frontage road here is now posted at 50, and drivers are often exceeding that posted limit.
This gets us to the point of actual solutions for you, Leah. Option one: tell your neighbors to stop being so dang selfish, rude, dangerous, reckless, careless and more. Option two: encourage your local law enforcement agencies to up the enforcement on this maneuver, writing tickets for those who do it.
In the interim, we'll pass along some comments on this issue to our engineers for a fix.


Any idea when construction to widen Loop 1604 from I-10 to FM 1346 might begin? Thanks!
- Todd
Right now that's included in our long-range wish list and is penciled in for the year 2020. To be honest, that mark will likely move - it's placed on the list for the year 2020 so it's considered and scored for prioritization. We are working on it, but at the moment we have other demands to fill.

Tuesday, August 16

Mail Bag: Potranco Road traffic, city and county projects, I-10

Could you tell me how many cars drive down Potranco Road daily? I mostly interested in the part of Potranco behind Redbird Ranch. Thank you!
-Kristi

Kristi, you're asking a question we typically get via phone. It's a great question! And, to help you really get the info you're wanting, I'll give you source material.
We have, posted online, a five-year record of our traffic counts. This will allow you to see what that segment of Potranco has been doing for five years, giving you an idea of what to expect in the future. (We don't house more than five years online for two reasons: first, records retention requires five years posted like this; second, we already host tens of thousands of pages of data online, and capping info at five years helps us minimize our IT expense.)
That said, it's worth noting there's a trick to using the data we've got posted.

When will UTEX from UTSA Blvd and the I-10 access road be completed? 
-Tim
This question is really a question for the city of San Antonio - UTEX is a city roadway. That said, the work there may be more associated with private development than with city work. That's a question to ask the folks with the city's TCI group when you visit with them.

I see construction on 471 is to begin 8-15. Is there a map of the project and what's being done, and for how long? Also, what is the plan for connecting 151/Alamo Ranch/211? and when does that start?Thanks.
- Michael
You've got a few different questions going on here, Michael. So, one at a time.
First, the Culebra Road work (FM 471) that started this week is being handled entirely by Bexar County. They've got our logo up on the project sign boards because we approved the design and, when the county is done with the project, we'll buy it back from them. It's a funding option that gets projects delivered through local participation called pass-through financing, but we digress (to be clear, this application of pass-through financing does not involve tolls). Bottom line: the county has a project information page available here, and if you've got questions at all they can be reached here.
The county also has some information about the extension of Alamo Ranch Parkway on that same info page. The biggest thing to note is ARP is being developed by private developers as they continue to build up the area and add homes (and shopping options). This is not being built by your tax dollars. Though, when developers finish, they turn it over for public maintenance. Because it's being built by private folks, though, we don't have an exact timeline on when to expect ARP to reach Hwy 211.
Oh, yeah, and Hwy 211 needs to be extended so ARP can actually connect with it. That $24 million effort is also being done by Bexar County and isn't slated to start until next year, provided all the funds match up next year.

What will happen to the (I-10) access roads from Ralph Fair Road toward 46 going west? Will they switch to one way? Will they remain two way? Right now they are still working on them. Will they widen them eventually?
What will happen at Old Fredericksburg Road coming toward the access road from Village Green and Fallbrook? Will there eventually be and underpass or overpass? I have heard both stories. Will they improve the Fair Oaks Bridge across 10. It's shaky!
- Mike
So back in March we started work on a project between Ralph Fair Road and Fair Oaks Parkway. Basically we're converting the frontage roads to one-way (which requires some widening for shoulders, curbs and sidewalks) and adding an overpass on I-10 at Old Fred Road - it'll take I-10 over a new intersection that connects Old Fred with Buckskin Drive.
We're also reconstructing the bridge at Fair Oaks and I-10, basically expanding it a la Ralph Fair. That project starts here in the fall and will wrap up in 2018.
What about beyond Fair Oaks Parkway? Well, eventually we will have one-way frontage road. Our goal is to eliminate one-way frontage roads wherever we've got a developed, metro area. We're not quite ready to do that - we need more money first - but it is on the agenda. Once we're nearing that work beyond Fair Oaks Parkway, we'll host a series of open house discussions to show y'all what we've got.

Concerning the work activity at hwy 46 and hwy 281: There needs to be a sign informing east bound Hwy 46 traffic that two lanes will merge to one. The existing one was removed for construction and has not been replaced.
Thank you for addressing this matter. It will require a follow-up with the poorly performing contractor that is presently on site. With out this sign there will be a collision and a fair amount of road rage played out.
-Tom
I'll start with the really good news: we've only got a few really light items left to have this job finished (finally) and it looks like we should wrap up this month. We're seeing CRG on the site daily (with the exception of Monday, due to weather) and we're seeing good progress. Rest assured they'll be held very accountable for dragging this project out the way they have, but we're looking at a finish in a matter of days.
As for the sign? We checked the plan sheets and no such sign is called for in the plans. That said, we've made our maintenance guys and our operations guys aware of the issue so we can have it addressed as appropriately and quickly as possible.