Friday, February 4

New displaced left turn lanes on westbound FM 306 (Creekside Crossing) set to open on Feb. 7

The new partial displaced left turn lanes on westbound FM 306 (Creekside Crossing) at I-35 will be operational for the traveling public on Monday, February 7, 2022 by 11:59 p.m. 

Drivers who wish to turn left on I-35 southbound from FM 306 westbound will no longer go straight, under the I-35 overpass. They will be navigated to the new two displaced left lanes beginning near the Whataburger and Panda Express. As part of the displaced left turn lanes, drivers can expect new traffic lights in the area.

For safety, police officers will be present for a few days to assist drivers as they adjust to the new configuration. The overall operational improvement project is expected to be completed the summer of 2022.

For more about this project, visit: my35.org/alamoproject-guadalupe-river-fm306.htm.

Friday, April 16

Upcoming Traffic Switch on FM 306 from Town Center Drive to I-35 Northbound Frontage Road

Construction crews will reconfigure the traffic lanes on Creekside Crossing (FM 306) between the I-35 northbound frontage road and Town Center Drive. The lane reconfiguration will start Sunday, April 18 at 8:30 p.m. and will stay in place until approximately the end of July. Crews will be widening and reconstructing the roadway and driveways in front of Buc-ee's during this phase of work. 

Two through lanes will remain open on Creekside Crossing (FM 306) in each eastbound/westbound direction. Motorists traveling eastbound on Creekside Crossing (FM 306) will be able to make a right or left turn or continue straight at the signalized intersection of Creekside Crossing (FM 306) and Town Center Drive.

For more information: http://www.my35.org/alamo-project-guadalupe-river-fm306.htm

Monday, March 8

I-35 exit and entrance ramps to be relocated at FM 2252 and FM 1103

On March 10, 2021, starting at 8:30 p.m. several ramp closures will be in place on I-35 between FM 2252/FM 482 and FM 1103 (Hubertus Road). Ramp closures are necessary so crews can build the new northbound exit ramp from I-35 to FM 1103 (Hubertus Road), along with the new southbound entrance ramp from I-35 to FM 2252/FM 482. Work will consist of constructing new ramps, retaining walls, drainage structures and pavement. The ramp closures will be in place for approximately two to three months. Completion of work is dependent on weather.


I-35 Northbound:
Closure - The existing entrance ramp at FM 2252/FM 482 to I-35 northbound will be closed.
Detour - To access I-35 northbound from FM 2252/FM 482:
  • Northbound traffic on I-35 at FM 2252/FM 482 will continue north on the frontage road.
  • Traffic can access the I-35 northbound entrance ramp just past FM 1103 (Hubertus Road).

I-35 Southbound:
Closure - The existing exit ramp at FM 2252/FM .482 from I-35 southbound will be closed.
Detour - To access FM 2252 (Hubertus Road)/FM 482 from I-35 southbound:
  • From I-35 Southbound, take Exit 178 (FM 1103/Hubertus Road).
  • Travel along the I-35 South frontage road to reach FM 2252 (Hubertus Road) / FM 482.

For More Information about this project: http://www.my35.org/alamo-project-fm2252-schwab.htm 

Thursday, January 21

Southbound I-35 Mainlane Overnight Closure

The southbound I-35 mainlanes from the southbound I-35 Watson Lane/Old Bastrop Rd exit ramp (Exit 195) to the I-35 entrance ramp at Conrads Lane will be closed overnight on the following dates:
  • 9 p.m. Friday, Jan. 22 through 5 a.m. Saturday, Jan. 23
  • 9 p.m. Monday, Jan. 25 through 5 a.m. Tuesday, Jan. 26


During this operation, traffic will detour by taking the southbound I-35 Watson Lane/Old Bastrop Rd exit ramp (Exit 195) to the southbound I-35 frontage road and use the I-35 entrance ramp at Conrads Lane to return to the mainlanes. This operation will allow for improvements to the new overpass at the Parkway intersection which is scheduled to open at the end of 2021.

Want to keep up with progress on this project? Continue to check here for blog updates, as well as follow us on Twitter(@TxDOTSanAntoio). Also, you can sign up for email updates by subscribing here http://eepurl.com/gRtrwn.




Wednesday, December 9

Northbound I-35 Mainlane Overnight Closure in New Braunfels

The northbound Interstate 35 (I-35) mainlanes from the northbound I-35 Kohlenberg Road/Conrads Lane exit ramp (Exit 193) to the northbound I-35 entrance ramp at Old Bastrop Road will be closed overnight from 8 p.m. Saturday, Dec. 12 through 10 a.m. Sunday, Dec. 13.

During this operation, traffic will detour by taking the northbound I-35 Kohlenberg Road/Conrads Lane exit ramp (Exit 193) to the northbound I-35 frontage road and use the I-35 entrance ramp at Old Bastrop Road to return to the northbound I-35 mainlanes. This operation will allow for improvements to the new overpass at the Parkway intersection which is scheduled to open at the end of 2021.

Also note these additional overnight closures:
  • The northbound I-35 entrance ramp at Kohlenberg Road/Conrads Lane will be closed beginning 5 p.m. Saturday, Dec. 12
  • The turnaround lanes at FM 306 over the I-35 mainlanes will also be closed during this operation
Want to keep up with progress on this project? Continue to check here for blog updates, as well as follow us on Twitter(@TxDOTSanAntoio). Also, you can sign up for email updates by subscribing here http://eepurl.com/gRtrwn.


Thursday, December 3

Work on turnarounds at I-35 and FM 306 (Creekside Crossing) to start Dec. 6, 2020

What improvements are taking place?
The I-35 turnarounds at FM 306 (Creekside Crossing) in both the northbound and southbound directions will be closed starting Sunday, December 6 at 9 p.m. The turnaround closures will be in place for approximately two weeks to allow crews to construct drainage facilities, widen the turnarounds, and repave and restripe the turnaround lanes. Completion of work is dependent on weather.

Detours:
  • Southbound traffic on the I-35 frontage road will make a left turn at the signalized intersection at FM 306 (Creekside Crossing) to access I-35 northbound.
  • Northbound traffic on the I-35 frontage road will make a left turn at the signalized intersection at FM 306 (Creekside Crossing) to access I-35 southbound.
Please note: Two lanes will remain open on the I-35 frontage road in both directions from FM 306 (Creekside Crossing). There will be no change to current traffic patterns on FM 306 (Creekside Crossing) during this work phase.

Wednesday, October 14

I-35 Frontage Road Construction Expanding North in Comal County

We are extending the northern limit of the two- to one-way I-35 frontage road conversion in Comal County. Work for this conversion began Tuesday, Oct. 13. The new limit will move north to York Creek Road/FM 1102, with the southern limit remaining at Kohlenberg Road. The previous northern limit of the conversion ended at the bridge crossing at Watson Lane.


Appropriate signs, pavement markings and construction barrels will be utilized to guide traffic safely through the construction zone. Conversions began at the project onset in March 2020 with the speed limit dropping from 55 to 45 miles per hour. 

To stay informed, you can receive regular lane closure updates to your email by subscribing here (http://eepurl.com/gRtrwn).

Thursday, October 1

Long-Term Northbound I-35 Mainlane Traffic Switch

The northbound Interstate 35 (I-35) mainlanes from Conrads Lane to south of Watson Lane will be shifted out onto temporary detour lanes with work beginning at 8 p.m. on Friday, October 2. This traffic switch follows a similar operation completed on the southbound I-35 mainlanes that took place in August 2020. 

For the traffic switch to occur, two northbound mainlanes will be closed to allow for crews to work on the transition. The traffic switch is scheduled to be complete the morning of Sunday, October 4. This detour will allow for the construction of new northbound I-35 mainlanes and the new overpass at the Parkway intersection which is scheduled to open at the end of 2021.

Want to keep up with progress on this project? Continue to check here for blog updates, as well as follow us on Twitter(@TxDOTSanAntoio). Also, you can sign up for email updates by subscribing here http://eepurl.com/gRtrwn.

Friday, September 11

Upcoming Traffic Switch on FM 306 from Town Center Drive to I-35 North Frontage Road

The traffic thru lanes on westbound FM 306 / Creekside Crossing from Town Center Dr. to the I-35 northbound frontage road will be switched to the eastbound lanes starting Sunday, September 13 at 8:30 p.m. The traffic switch will be in place for approximately three months, until mid-December. Crews will be widening and reconstructing the roadway pavement and driveways during this phase of work.

Two thru lanes will be open on FM 306/Creekside Crossing in each direction. Both westbound and eastbound traffic will be moved to the eastbound lanes. At the signalized intersection of FM 306 / Creekside Crossing and Town Center Dr., motorists will be able to make a right or left turn or continue straight. Eastbound traffic will not be allowed left turns through this work zone.

For more information on this project click here on the My35 project page.

Monday, April 20

Long-Term Northbound I-35 Watson Lane Exit Ramp Closure


The northbound Interstate 35 (I-35) Watson Lane exit ramp will close long-term beginning 8 p.m. Wednesday, April 22. Scheduled to reopen Summer 2021, the closure will continue our phasing for construction of the new Parkway intersection. The intersection will add dedicated turnarounds to the frontage roads between Kohlenberg Road/Conrads Lane and Watson Lane.

During this time, traffic will be detoured to the northbound I-35 Kohlenberg Road/Conrads Lane exit ramp before the Watson Lane exit ramp.


Want to keep up with the latest on this project? Continue to check here for blog updates, as well as follow us on Twitter. Additionally, you can sign up for email updates by subscribing here http://eepurl.com/gRtrwn.