I-10 – Boerne
  • Wednesday, October 18 at 9 p.m. until Thursday, October 19 at 6 a.m. Westbound main lanes at Exit 540. The right lane will close while crews resurface the road.
I-10 – Fair Oaks Ranch
  • Monday, October 23 from 9 a.m. until 4 p.m. Friday, December 29. Westbound frontage road at Old Fredericksburg Road. All lanes will close while crews replace drain structures. Traffic will follow the signed detour route to reach its destination.
I-10 – Leon Springs
  • Monday-Thursday, October 16-19. 9 p.m. until 5 a.m. nightly. Main lanes, both directions, between Ralph Fair Road and La Cantera Pkwy. The left lane will close while crews lay asphalt.
I-10 – East San Antonio
  • Saturday, October 14 between 8 a.m. and 9 p.m. Frontage roads, both directions, between Foster and Graytown roads. Alternating lanes will close while crews convert the frontage roads to one-way only. This change is permanent. When work is finished each frontage road will have only one lane until the project is finished.
  • Saturday, October 21 at 6 a.m. until Monday, October 23 at 5 a.m. Main lanes, both directions, between Foster Road and FM 1516. All lanes will close while crews set bridge support beams. Eastbound traffic will exit Foster Road and westbound traffic will exit FM 1516. Both directions will follow the frontage road and re-enter the highway at the next available ramp. Please note the frontage roads on both sides will be a single lane.
I-10 – Northwest San Antonio
  • Monday-Friday, October 16-20. 9 a.m. until 3 p.m. daily. Eastbound frontage road between West Hollywood and Fredericksburg Road. The right lane will close while crews do concrete work.
I-35 – New Braunfels
  • Tuesday, October 17 from 10 a.m. until 3 p.m. Main lanes, both directions, at York Creek and Alligator Creek. Alternating lanes will close while crews replace the curb.
I-35 – Selma
  • Current until October 2018. Frontage roads, both directions, at FM 1103. The right lane will close while crews replace the FM 1103 overpass bridge.
  • Wednesday-Thursday, October 11-12. 9 a.m. until 5 p.m. daily. Southbound frontage road at FM 1103. Alternating lanes will close while crews restripe the road to a single lane. This closure includes the exit ramp to FM 1103. The ramp will reopen by the end of the day; the frontage road will remain at a single lane until the end of 2018.
I-35 – East San Antonio
  • Current until Monday, October 23. 9 p.m. until 5 a.m. nightly. Northbound main lanes between George Beach and Thousand Oaks Drive. Alternating lanes will close while crews lay asphalt.
  • Sunday-Friday, October 15-20. 8 p.m. until 5 a.m. nightly. Northbound main lanes between Broadway and I-410. The two left lanes will close while crews work on bridge joints.
  • Sunday-Friday, October 15-20. 9 p.m. until 5 a.m. nightly. Southbound main lanes between I-410 and Broadway. Alternating lanes will close while crews seal coat the shoulders.
  • Monday-Friday, October 16-20. 9 a.m. until 3 p.m. daily. Southbound frontage road connector to the southbound I-410 connector ramp. The left lane will close while crews work on guardrail.
I-37 – Downtown San Antonio
  • Current and continuous until Friday, December 1 at 5 p.m. Northbound exit ramp to Florida and Carolina avenues (exit 140A). The ramp will close while crews rebuild the slope near the exit. Traffic will exit Cesar Chavez (exit 140B) and turn around to reach its destination.
I-410 – Northwest San Antonio
  • Sunday-Friday, October 15-20. 9 p.m. until 5 a.m. daily. Eastbound main lanes between Vance-Jackson and Blanco roads. Alternating lanes will close while crews do concrete work. This closure includes entrance and exit ramps as needed. Traffic will use the next available ramp to reach its destination.
I-410 – West San Antonio
  • Current until Tuesday, October 31. Northbound exit to Culebra Road. The exit will close while crews widen the main lanes and frontage road. Traffic will exit Ingram Road, turn around and get to Culebra on the southbound frontage road.
  • Sunday, October 15 until Friday, November 3. 9 p.m. until 5 a.m. nightly. Main lanes, both directions, between Hwy 151 and Culebra Road. The left two lanes will close while crews work on overhead highway sign structures.
  • Monday, October 16 at 9 p.m. until Tuesday, October 17 at 5 a.m. Frontage roads, both directions, between Hwy 151 and Culebra Road. Alternating lanes will close while crews work on traffic signals.
  • Friday, October 20 at 8 p.m. until Monday, October 22 at 5 a.m. Southbound main lanes between Hwy 151 and US Hwy 90. All lanes will close while crews shift traffic over Marbach Road. Traffic will exit Marbach Road, continue along the frontage road and use the next available ramp to re-enter the highway. Left turns onto Marbach will be restricted during this closure.
U.S. Hwy 90 – West San Antonio
  • Monday-Tuesday, October 16-17. 9:30 a.m. until 4 p.m. daily. Westbound main lanes between Medio Creek and Loop 1604. The left lane will close while crews do concrete work.
  • Tuesday-Thursday, October 17-19. 9 a.m. until 3 p.m. daily. Westbound frontage road between Herbert Lane and Leon Creek. The left lane will close while crews drill for support foundations.
  • Thursday, October 19. 9 a.m. until 3 p.m. Westbound frontage road between Leon Creek and old US 90. The right lane will close while crews drill for support foundations.
  • Thursday, October 19. 9 a.m. until 3 p.m. Westbound frontage road between Rockgate and Colt Street. The left lane will close while crews drill for support foundations.
U.S. Hwy 281 – North San Antonio
  • Saturday, October 21. 8 a.m. until 10 p.m. Southbound frontage road between Sonterra Road and Loop 1604. The left lane will close while crews set barrier.
  • Monday-Friday, October 23-27. 9 p.m. until 5 a.m. nightly. Northbound main lanes between Frontage Road Exit and Sonterra Road. Alternating lanes will close while crews set barrier.
U.S. Hwy 281 – Near north San Antonio
  • Monday, October 16 at 9 p.m. until Tuesday, October 17 at 6 a.m. Main lanes, both directions, between I-37 and I-410. The right lane will close while crews work on guardrails.
Hwy 151 – Northwest San Antonio
  • Wednesday-Friday, October 18-20. 9 p.m. until 5 a.m. nightly. Frontage roads, both directions, at Ingram Road. The right lane will close while crews work on traffic signals.
Loop 1604 – North San Antonio
  • Monday-Friday, October 16-20. 9 p.m. until 5 a.m. nightly. West-to-east turnaround at US 281. The turnaround will close while crews do bridge work. Traffic will use the signalized intersection to reach its destination.
  • Monday-Friday, October 16-20. 9 p.m. until 5 a.m. nightly. Westbound main lanes at US 281. The right lane will close while crews set barrier.
  • Monday-Friday, October 16-20. 9 p.m. until 5 a.m. nightly. Eastbound main lanes between Stone Oak Parkway and Cold Canyon Road. The right lane will close while crews set barrier. This closure includes the direct connector to southbound US 281. Traffic will exit northbound US 281 and use the frontage roads to reach southbound US 281.
  • Monday-Friday, October 23-27. 9 p.m. until 5 a.m. nightly. Westbound frontage road between US 281 and Stone Oak Parkway. Alternating lanes will close while crews set barrier.
Loop 1604 – Northwest San Antonio
  • Current until Friday, January 26, 2018. North-to-south turnaround at Bandera Road. The turnaround will remain closed while crews do road work. Traffic will use the signalized intersection to turn around.
  • Monday-Friday, October 16-20. 9 p.m. until 5 a.m. nightly. Eastbound frontage road at Bandera Road. The right turn lane will close while crews do road work.
  • Saturday, October 21. 9 a.m. until 3:30 p.m. Southbound main lanes at Medio Creek. The right lane will close while crews set bridge support beams.
Other roads – New Braunfels
  • Monday, October 16 until Friday, October 27. 9 a.m. until 4 p.m. daily. Southbound Hwy 46 between County Road 127 and Cloud Lane. The right lane will close while crews drill support structures for new traffic signals.
Other roads – West San Antonio
  • Friday, October 13 at 8 p.m. until Monday, October 16 at 5 a.m. Marbach Road, both directions, at I-410. All lanes will close while crews wreck overhead bridge structures. Traffic will turn right onto the frontage road, turn around at the first available intersection and return to Marbach to reach its destination.
  • Sunday, October 16 until Friday, November 3. 9 p.m. until 5 a.m. nightly. Hunt Lane, both directions, at Hwy 151. All lanes will close while crews work on the overhead bridge. Traffic will turn right onto the frontage road and turn around at the next available intersections.
  • Friday, October 27 at 8 p.m. until Monday, October 30 at 5 a.m. Marbach Road, both directions, at I-410. All lanes will close while crews wreck overhead bridge structures. Traffic will turn right onto the frontage road, turn around at the first available intersection and return to Marbach to reach its destination.
Other roads – Northwest San Antonio
  • Monday-Friday, October 16-20. 9 p.m. until 5 a.m. nightly. Southbound Bandera Road between Legend Trail and Stonecroft. The right lane and right turn lane will close while crews do road work.