The eastern segment of Wurzbach Parkway is open for use this week. All that remains to complete the Parkway, moving forward, is the segment between West Avenue and Jones-Maltsberger.
To answer a question that's asked several times each week, we will open the full segment at one time; we will not open the remaining Parkway in sections.
In order to be ready to open the final segment - which should be in use this summer - we've got a few things yet to do, particularly along U.S. Hwy 281. This weekend that means closures on U.S. 281 likely to impact anyone driving through north-central San Antonio.
The closure:
Saturday-Monday, March 14-16. 4 a.m. until 5 a.m. continuous. All southbound main lanes of U.S. 281 will close between Bitters Road and Nakoma Drive while crews move barrier and restripe the road. Traffic will exit Bitters Road, pass through the Bitters and Nakoma intersections, and re-enter the main lanes. Officers will be used to control traffic at intersections and at the frontage road.
The work:
Williams Brothers Construction will move barriers and the lanes of U.S. 281 through this area. For the next several weeks, work will be done along the center median; the new barrier and the lane shift will provide a safe working area for these crews.
The new exit ramp for Wurzbach Parkway/Nakoma Drive will be opened when this closure is finished. The new ramp is located near Bitters Drive, pushing traffic onto the frontage road well ahead of the intersections drivers may need to reach.
With the lanes closed electricians will get in and connect light poles and overhead signs - trying to take advantage of the closure to take care of the work.
The future:
With barriers moved, Williams Brothers will be poised to do the work remaining in the median area of U.S. 281. Meanwhile, crews focusing on the construction of the new southbound exit ramp will be able to focus on the northbound ramps still under construction.
If crews are able to keep pace, we should be discussing the opening of new northbound ramps before the end of the school year.
Search This Blog
Wednesday, March 11
Tuesday, March 10
I-10 Huebner - the next major development
The eastbound main lanes should be in final configuration over DeZavala Road in time for crews to cheer on the Sweet Sixteen in the upcoming NCAA basketball tournament.
While the games won't be hosted by San Antonio, traffic headed to game-watching parties will have a full five lanes (plus an auxiliary lane) on the eastbound side of I-10 to the Fredericksburg Road exit. They'll also have the new eastbound entrance ramp from UTSA Blvd. (it's really not going to change much - just move a little further east), and the new eastbound exit to Fredericksburg exit (a two-lane exit) will be opened up.
The turnarounds at DeZavala and at UTSA Bouleavard will open later.
The turnarounds at DeZavala and at UTSA Bouleavard will open later.
Throughout this week Webber Construction will be removing concrete barrier while they wait for the new center median to cure. Barricades - the orange reflective barrels - will remain. By moving the barrier now, Webber will make their work to open up new lanes faster. That work is scheduled for Friday-Monday, March 20-22. Work will be done 7 p.m. Friday until 5 a.m. Monday.
Again, that's next weekend - March 20-22.
Again, that's next weekend - March 20-22.
Over the weekend's traffic switch, drivers can expect alternating lanes of I-10 to close while striping crews paint the road for the new lanes. This means the traffic configuration will change throughout the weekend. Drivers should slow down and pay special attention to surroundings to avoid confusion or crashes.
In the meantime, Webber is pushing to get those turnarounds opened at DeZavala Road. Recent sloppy weather has made remaining work - a final surface of asphalt and a large concrete slab - difficult. They are similarly struggling to finish come curb and barrier that's preventing them from opening a new east-to-west turnaround at UTSA Boulevard. No definite dates are set to open either, but we are hopeful these will be opened by the end of the month.
Friday, March 6
Next week's construction-related closures
I-10
- Saturday-Monday, March 7-9. 4 a.m. until 5 a.m. continuous. Main lanes, both directions, at Ralph Fair Road (northwest San Antonio). All lanes will close while crews pour concrete on the Ralph Fair Road overpass. Traffic will exit Ralph Fair Road, pass through the intersection, and re-enter the main lanes of traffic.
- Sunday-Friday, March 8-13. 8:30 p.m. until 5:30 a.m. nightly. Main lanes, both directions, between Huebner Road and UTSA Boulevard (northwest San Antonio). Alternating lanes will close for road work.
- Sunday-Friday, March 8-13. 8:30 p.m. until 5:30 a.m. nightly. Frontage road, both directions between Loop 1604 and Huebner Road (northwest San Antonio). Alternating lanes will close for road work.
- Monday-Friday, March 9-13. 9 a.m. until 4 p.m. daily. Frontage road, both directions, between Loop 1604 and Huebner Road (northwest San Antonio). Alternating lanes will close for road work.
I-35
- Saturday, March 7. 5 a.m. until 10 a.m. Main lanes, both directions, between Copeland Drive/Hormel Drive and Binz-Engleman (east San Antonio). The right lane will close in each direction while crews survey the roadway.
- Sunday-Friday, March 8-13. 9 p.m. until 5 a.m. nightly. Northbound main lanes between George Beach and Rittiman Road (northeast San Antonio). Alternating lanes will close while crews restripe the roadway.
- Sunday-Friday, March 8-13. 9 p.m. until 5 a.m. nightly. Southbound main lanes between Rittiman and George Beach (northeast San Antonio). Alternating lanes will close while crews move barrier.
- Monday-Friday, March 9-13. 9 a.m. until 3:30 p.m. daily. Southbound frontage road between Rittiman Road and George Beach. Alternating lanes will close while crews repair the roadway.
- Monday-Friday, March 9-13. 9 a.m. until 3:30 p.m. daily. Northbound exit ramp to westbound I-410 (Windcrest). The right lanes will close while crews place guardrail.
- Monday-Friday, March 9-13. 9 a.m. until 3 p.m. daily. Southbound frontage road between Binz-Engleman and Seguin roads (east San Antonio). Alternating lanes will close while crews build temporary light poles.
I-37
- Monday-Tuesday, March 9-10. 9 a.m. until 3 p.m. daily. Northbound main lanes between Southton Road and U.S. Highway 181 (south Bexar County). The left lane will close while crews work on the cable median barrier.
- Monday-Wednesday, March 9-11. 9 a.m. until 3 p.m. daily. Southbound main lanes between mile markers Hardy Road and FM 536 (north Atascosa County). The left lane will close while crews work on the cable median barrier.
I-410
- Saturday, March 7. 7 a.m. until noon. Eastbound exit ramp to northbound I-35 (Windcrest). The right lane will close while crews repair crash cushions.
- Sunday-Friday, March 8-13. 9 p.m. until 5 a.m. nightly. Northbound connector to northbound I-35 (northeast San Antonio). All lanes will close while crews move barrier. Traffic will exit Space Center and move through the Rittiman Road intersection, then enter the northbound I-35 main lanes.
- Sunday-Friday, March 8-13. 9 p.m. until 5 a.m. nightly. Northbound frontage road between Binz-Engleman and Rittiman Road (northeast San Antonio). Alternating lanes will close while crews build curb and place asphalt.
- Monday-Friday, March 9-13. 9 a.m. until 3:30 p.m. daily. Northbound frontage road between Binz-Engleman and Rittiman Road (northeast San Antonio). Alternating lanes will close while crews build curb and place asphalt.
U.S. Hwy 281
- Friday-Monday, March 6-9. 9 p.m. until 5 a.m. continuous. Southbound main lanes between Jones-Maltsberger and Hildebrand (north-central San Antonio). Alternating lanes will close while crews repair the roadway.
- Saturday, March 7. 3 a.m. until 5 p.m. Northbound frontage road between Nakoma Drive and Bitters Road (north-central San Antonio). All lanes will close while crews pour concrete for the future northbound exit ramp to Bitters Road. Traffic will use Nakoma Drive, Jones-Maltsberger and Bitters Road to reach its destination.
Other roads
- Friday-Monday, March 6-9. 7 p.m. until 5 a.m. continuous. Medical Drive, both directions, between Ewing Halsell and Fredericksburg Road (Medical Center). Alternating lanes will close for concrete work.
- Saturday-Monday, March 7-9. 5 a.m. until 5 a.m. continuous. Ralph Fair Road, both directions, between Old Fredericksburg Road and I-10 (northwest San Antonio). All lanes will close while crews pour concrete on the Ralph Fair Road overpass bridge deck. Traffic will use Old Fredericksburg Road to Aue Road or to the I-10 frontage road.
- Monday, March 9. 8 a.m. Alameda Street, both directions, at Loop 1604 (northwest San Antonio). All lanes will close for three weeks while crews build the roadway. Traffic will reach Alameda Street off of Braun Road.
- Monday, March 9. 9 a.m. until 4 p.m. West Avenue, both directions, at Wurzbach Parkway (north-central San Antonio). The left lane will close while crews work on water lines.
- Monday, March 9. 7 a.m. until 4 p.m. Wurzbach Parkway, both directions, between Starcrest Drive and Jones-Maltsberger (north-central San Antonio). The left lanes will close while crews paint median barrier.
- Monday-Monday, March 9-16. 7 p.m. until 5 a.m. nightly. Medical Drive, both directions, between Ewing Halsell and Fairhaven (Medical Center). Alternating lanes will close for road work.
- Monday-Monday, March 9-16. 7 p.m. until 5 a.m. nightly. Fredericksburg Road, both directions, between Louis Pasteur and Data Point (Medical Center). Alternating lanes will close for road work.
- Wednesday-Friday, March 11-13. 9 a.m. until 3 p.m. daily. Southbound U.S. Highway 181 between I-37 and Max Road (southeast Bexar County). The left lane will close while crews work on the cable median barrier.
- Friday-Monday, March 13-16. 7 p.m. until 5 a.m. continuous. Medical drive, both directions, between Ewing Halsell and Fredericksburg Road (Medical Center). Alternating lanes will close for concrete work.
Comal County round-up
Recent weather has pushed back some huge milestones across Comal County - particularly in and around New Braunfels - but big developments are still taking shape. The result is a flurry of activity inside a two-week window, set to start late next week.
Here's a run-down, in no particular order:
Lp 337 (Rueckle Road)
For two months folks have been using a finished product that expanded Lp 337 between I-35 and Altgelt Road, but barricades have remained blocking a portion of the overpass bridge. This has limited traffic from the northbound frontage road to a single left turn lane and traffic crossing the bridge over I-35 to a single lane.
The goal of the project, however, was to expand the bridge to allow for two through lanes plus a left turn lane for traffic coming from Rueckle Road and headed north (or west, depending on your perspective) on Lp 337. That was hampered by a slight elevation difference between what used to be the south-to-north turnaround bridge and the existing overpass bridge. The difference, which is only a matter of an inch or so, was noticed when the concrete barrier was demolished as part of the project requirements.
The specialized subcontractor for the work to correct the elevation difference, which happens to fall right in the middle of the wheelpath of one of the lanes, was scheduled to solve the issue this week. Cold and wet weather has pushed that back, and they are now expected to be working on the bridge by the start of next week.
Once work on the bridge begins we'll need about a week to have everything opened up. Call it a St. Patrick's Day gift.
FM 306
Hunter Industries continues to work toward completing the expansion of the roadway and construction of overpasses at the UPRR crossings near Hunter Road and Goodwin Lane in time for summer. Right now that's exactly what will happen.
Crews have been pouring concrete to form the concrete barriers along the overpass near Hunter Road and are working to do the same near Goodwin. This may require temporary or sporadic closures as trucks enter or exit the roadway, but nothing lasting or long-term at all. At most, these closures will last 10 minutes.
Hunter is on pace to have the work complete by the end of the school year (and start of the summer river floating season).
FM 1101
The expansion of FM 1101 between Hwy 46 and FM 306 has been on hold nearly six months while we await utilities to be moved out of conflict. The deadline for that is in April, and we'll then release Hunter Industries to begin work.
The project will last about a year and a half, with most of the work happening during the summers of 2015 and 2016. Since three schools are along this work zone, it's critical we reduce our impact during the school year.
The final product will feature a new center left-turn lane, expanded shoulders for bike use and sidewalks.
I-35 ramp reversals
Dan Williams Company is running slightly ahead of schedule and is ready to open the new northbound entrance ramp from FM 306 around St. Patrick's Day. This new on-ramp is located near Conrads-Kohlenberg and will require the current exit to Conrads-Kohlenberg to close. Traffic to Conrads-Kohlenberg will exit FM 306 and pass through the intersection.
Naturally, that means an uptick in traffic at an already stressed intersection. However, the north-to-south turnaround at FM 306 will open - permanently - and the intersection should see some relief.
The new exit ramp, located near FM 306 (designed to capture the truck traffic headed to the WalMart transfer warehouse), is set to open by the first weekend of April.
Meanwhile, Dan Williams is beginning to set up for work on the southbound side. This is about two months ahead of schedule. They have more work to do on the southbound side than they did on the northbound side, so drivers shouldn't expect such an early finish on the southbound side. We initially planned about six months for each side. We are sticking with the six-month schedule on the southbound side for now.
Walnut Avenue
The city of New Braunfels has approved a proposal brought by us on behalf of the contractor, Dean Word Company, to close Walnut Avenue completely between Grandview and Floral avenues. That closure should take place the week after St. Patricks Day.
Once Walnut Avenue is closed, Dean Word will begin expanding the road through the canyon and will install storm drain features on the uphill and downhill sides of the canyon. The phase of work - and the closure - is expected to last about nine months.
The closure will shorten the overall project duration, however, by about six months. Work began earlier this year and will wrap up before the summer of 2016.
U.S. 281 at Hwy 46
We have received occasional calls asking about the progress on this project that constructs turnarounds for U.S. 281 traffic at Hwy 46 in Bulverde.
CRG is the contractor out there, and they are indeed running behind schedule. As is typical in a situation like this, TxDOT is assessing liquidated damages against the contractor to the tune of a little under $1,000 per day. This is the strongest leverage the department has to help motivate a contractor to accelerate production of a project.
Lately the delays on the project have been due to an equipment breakdown that took several weeks to get repaired. Once the machinery that broke down was ready to work again, weather tackled the area and stopped any productive work from happening.
Project managers are pointing to a completion date early this summer, if all goes well.
Here's a run-down, in no particular order:
Lp 337 (Rueckle Road)
For two months folks have been using a finished product that expanded Lp 337 between I-35 and Altgelt Road, but barricades have remained blocking a portion of the overpass bridge. This has limited traffic from the northbound frontage road to a single left turn lane and traffic crossing the bridge over I-35 to a single lane.
The goal of the project, however, was to expand the bridge to allow for two through lanes plus a left turn lane for traffic coming from Rueckle Road and headed north (or west, depending on your perspective) on Lp 337. That was hampered by a slight elevation difference between what used to be the south-to-north turnaround bridge and the existing overpass bridge. The difference, which is only a matter of an inch or so, was noticed when the concrete barrier was demolished as part of the project requirements.
The specialized subcontractor for the work to correct the elevation difference, which happens to fall right in the middle of the wheelpath of one of the lanes, was scheduled to solve the issue this week. Cold and wet weather has pushed that back, and they are now expected to be working on the bridge by the start of next week.
Once work on the bridge begins we'll need about a week to have everything opened up. Call it a St. Patrick's Day gift.
FM 306
Hunter Industries continues to work toward completing the expansion of the roadway and construction of overpasses at the UPRR crossings near Hunter Road and Goodwin Lane in time for summer. Right now that's exactly what will happen.
Crews have been pouring concrete to form the concrete barriers along the overpass near Hunter Road and are working to do the same near Goodwin. This may require temporary or sporadic closures as trucks enter or exit the roadway, but nothing lasting or long-term at all. At most, these closures will last 10 minutes.
Hunter is on pace to have the work complete by the end of the school year (and start of the summer river floating season).
FM 1101
The expansion of FM 1101 between Hwy 46 and FM 306 has been on hold nearly six months while we await utilities to be moved out of conflict. The deadline for that is in April, and we'll then release Hunter Industries to begin work.
The project will last about a year and a half, with most of the work happening during the summers of 2015 and 2016. Since three schools are along this work zone, it's critical we reduce our impact during the school year.
The final product will feature a new center left-turn lane, expanded shoulders for bike use and sidewalks.
I-35 ramp reversals
Dan Williams Company is running slightly ahead of schedule and is ready to open the new northbound entrance ramp from FM 306 around St. Patrick's Day. This new on-ramp is located near Conrads-Kohlenberg and will require the current exit to Conrads-Kohlenberg to close. Traffic to Conrads-Kohlenberg will exit FM 306 and pass through the intersection.
Naturally, that means an uptick in traffic at an already stressed intersection. However, the north-to-south turnaround at FM 306 will open - permanently - and the intersection should see some relief.
The new exit ramp, located near FM 306 (designed to capture the truck traffic headed to the WalMart transfer warehouse), is set to open by the first weekend of April.
Meanwhile, Dan Williams is beginning to set up for work on the southbound side. This is about two months ahead of schedule. They have more work to do on the southbound side than they did on the northbound side, so drivers shouldn't expect such an early finish on the southbound side. We initially planned about six months for each side. We are sticking with the six-month schedule on the southbound side for now.
Walnut Avenue
The city of New Braunfels has approved a proposal brought by us on behalf of the contractor, Dean Word Company, to close Walnut Avenue completely between Grandview and Floral avenues. That closure should take place the week after St. Patricks Day.
Once Walnut Avenue is closed, Dean Word will begin expanding the road through the canyon and will install storm drain features on the uphill and downhill sides of the canyon. The phase of work - and the closure - is expected to last about nine months.
The closure will shorten the overall project duration, however, by about six months. Work began earlier this year and will wrap up before the summer of 2016.
U.S. 281 at Hwy 46
We have received occasional calls asking about the progress on this project that constructs turnarounds for U.S. 281 traffic at Hwy 46 in Bulverde.
CRG is the contractor out there, and they are indeed running behind schedule. As is typical in a situation like this, TxDOT is assessing liquidated damages against the contractor to the tune of a little under $1,000 per day. This is the strongest leverage the department has to help motivate a contractor to accelerate production of a project.
Lately the delays on the project have been due to an equipment breakdown that took several weeks to get repaired. Once the machinery that broke down was ready to work again, weather tackled the area and stopped any productive work from happening.
Project managers are pointing to a completion date early this summer, if all goes well.
Thursday, March 5
Wurzbach Parkway progress
Wednesday morning electricians activated the traffic signals at the intersection of Wurzbach Parkway and Jones-Maltsberger (the signals at Starcrest and Wurzbach were activated a few days earlier). These lights will be on a "flash" setting for about a week before they go to full-cycle.
Here's what this means: Wurzbach Parkway will be completely open between Jones-Maltsberger and Wetmore by the middle of next week. Eastbound traffic is already active on this segment.
This marks an end to a tumultuous project that started back in 2010. In 2012 the original contractor, Ballenger Construction, defaulted on all their projects and filed for bankruptcy. By spring 2013 the bonding company, Liberty Mutual, had Texas Sterling Construction under contract to finish the project. Texas Sterling spent the first few months cleaning the project and assessing the needs of the job.
Over the last several months, Texas Sterling repaired issues held over from the Ballenger work and addressed concerns with electrical work. Continued troubles with copper wire being stolen from the project site delayed completion by a few weeks. Still, project managers focused on doing whatever they could to get the road opened for use. Portions of Wurzbach Parkway have been opened as soon as they were available since late fall.
With everything opened next week, this will means drivers will be able to connect directly to Jones-Maltsberger on Wurzbach Parkway, traversing the northeast side of town with greater ease. Those using the Salado Creek Greenway will find the trail extended to Jones-Maltsberger as well, improving mobility for hikers and bikers as well as drivers.
The final remaining segment of the parkway to finish runs between Jones-Maltsberger and West Avenue, including an overpass at U.S. Highway 281. That work is on pace to wrap up this summer.
Related to the work on this final segment, Williams Brothers Construction will close the northbound frontage road between Nakoma Drive and Bitters Road Saturday between 3 a.m. and 5 p.m. to pour concrete that will form the new Bitters Road exit ramp. The work shouldn't take all of the time scheduled and could finish up by early afternoon. Traffic will use Nakoma Drive, Jones-Maltsberger and Bitters Road to reach its destination.
Over the next week Williams Brothers will be working to switch traffic on the southbound frontage road of U.S. Highway 281 to its final configuration. The exit ramp to Nakoma Drive is being eliminated in favor of a new exit ramp that will capture traffic headed to Wurzbach Parkway as well as Nakoma Drive. The entrance ramp from Bitters Road, which has been moved, is already it its permanent location.
When traffic on the southbound frontage road is shifted later this month, Williams Brothers will set up barrier near the center median of the Hwy 281 main lanes and begin some work in the median area. This shouldn't disrupt daily traffic too much, but those who drive the area may opt to slow down a few miles per hour as they pass through the work zone.
Here's what this means: Wurzbach Parkway will be completely open between Jones-Maltsberger and Wetmore by the middle of next week. Eastbound traffic is already active on this segment.
This marks an end to a tumultuous project that started back in 2010. In 2012 the original contractor, Ballenger Construction, defaulted on all their projects and filed for bankruptcy. By spring 2013 the bonding company, Liberty Mutual, had Texas Sterling Construction under contract to finish the project. Texas Sterling spent the first few months cleaning the project and assessing the needs of the job.
Over the last several months, Texas Sterling repaired issues held over from the Ballenger work and addressed concerns with electrical work. Continued troubles with copper wire being stolen from the project site delayed completion by a few weeks. Still, project managers focused on doing whatever they could to get the road opened for use. Portions of Wurzbach Parkway have been opened as soon as they were available since late fall.
With everything opened next week, this will means drivers will be able to connect directly to Jones-Maltsberger on Wurzbach Parkway, traversing the northeast side of town with greater ease. Those using the Salado Creek Greenway will find the trail extended to Jones-Maltsberger as well, improving mobility for hikers and bikers as well as drivers.
The final remaining segment of the parkway to finish runs between Jones-Maltsberger and West Avenue, including an overpass at U.S. Highway 281. That work is on pace to wrap up this summer.
![]() |
| The final segment of Wurzbach Parkway will bridge U.S. 281, running top to bottom in the picture, and connect Jones-Maltsberger to West Avenue. This segment is on pace to open this summer. |
Over the next week Williams Brothers will be working to switch traffic on the southbound frontage road of U.S. Highway 281 to its final configuration. The exit ramp to Nakoma Drive is being eliminated in favor of a new exit ramp that will capture traffic headed to Wurzbach Parkway as well as Nakoma Drive. The entrance ramp from Bitters Road, which has been moved, is already it its permanent location.
When traffic on the southbound frontage road is shifted later this month, Williams Brothers will set up barrier near the center median of the Hwy 281 main lanes and begin some work in the median area. This shouldn't disrupt daily traffic too much, but those who drive the area may opt to slow down a few miles per hour as they pass through the work zone.