Friday, October 28

Next week's construction-related closures

I-10 – East San Antonio
  • Monday, October 31-Friday, November 18. 7 p.m. until 7 a.m. nightly. Main lanes, both directions, between Foster Road and Martinez Creek. Alternating lanes will close while crews set barrier. 
I-10 – East San Antonio

  • Monday-Friday, October 31-November 4. 9 a.m. until 3 p.m. daily. Main lanes, both directions, between I-35 and I-410. The right lane will close while crews work on guardrail.

    I-35 – New Braunfels
    • Sunday-Monday, October 30-31. 10 p.m. until 6 a.m. Southbound main lanes between the Comal-Hays county line and FM 306. Alternating lanes will close while crews lay asphalt. 
    • Monday-Friday, October 31-November 4. 9 p.m. until 6 a.m. nightly. Southbound main lanes between the Comal-Hays county line and FM 306. Alternating lanes will close while crews lay asphalt. 
    • Friday, November 4. 10 a.m. until 3 p.m. Southbound main lanes at York Creek. The left lane will close while crews pour concrete. 
    I-35 – Northeast San Antonio
    • Sunday-Friday, October 30-November 4. 9 p.m. until 5 a.m. nightly. Northbound exit to westbound I-410. Alternating lanes will close while crews do overhead bridge work. Traffic will exit Walzem and continue along the frontage road to reach I-410. 
    • Sunday-Friday, October 30-November 4. 9 p.m. until 5 a.m. nightly. Main lanes, both directions, between Rittiman and Walzem roads. Alternating lanes will close while crews do road work. 
    • Sunday-Friday, October 30-November 4. 9 p.m. until 5 a.m. nightly. Frontage roads, both directions, between Rittiman and Walzem. Alternating lanes will close while crews do road work. 
    • Monday-Friday, October 31-November 4. 9 a.m. until 3:30 p.m. daily. Frontage roads, both directions, between Rittiman and Walzem roads. Alternating lanes will close while crews do road work. 
    I-410 – Northeast San Antonio
    • Sunday-Friday, October 30-November 4. 9 p.m. until 5 a.m. nightly. Eastbound exit ramp to Randolph Boulevard and the city of Windcrest. The ramp will close while crews do bridge work. Traffic will exit Thousand Oaks, turn around and return to Randolph Boulevard to reach its destination. 
    I-410 – East San Antonio
    • Current through Friday, December 2. Southbound main lanes over North WW White. The right lane will close while crews repair damaged bridge rail. 
    I-410 – Northwest San Antonio
    • Friday-Saturday, October 28-29. 9 p.m. until 11 a.m. Southbound main lanes between Military Drive and Hwy 151. The left two lanes will close while crews work on bridge support columns. 
    • Sunday-Monday, October 30-31. 9 p.m. until 2 a.m. Northbound main lanes between Hwy 151 and Military Drive. Alternating lanes will close while crews move equipment. 
    US Hwy 281 – Central San Antonio
    • Sunday-Friday, October 30-November 4. 11 a.m. until 3 p.m. daily. Main lanes, both directions, between I-35 and I-410. Alternating lanes will close while crews work on guardrail. This closure includes ramps as needed. Traffic will follow the posted detour route. 
    • Sunday-Friday, October 30-November 4. 9 p.m. until 6 a.m. nightly. Main lanes, both directions, between Airport and Josephine. Alternating lanes will close while crews do bridge work. This closure includes ramps as needed. Traffic will follow the posted detour route. 
    Loop 1604 – Northwest San Antonio
    • Friday-Saturday, October 28-30. 9 p.m. until 6 a.m. daily. Southbound frontage road at Alamo Ranch Parkway. All lanes will close while crews do overhead bridge work. Traffic will turn right onto Alamo Ranch Parkway, turn around and re-enter the frontage road to reach its destination. 
    • Friday-Monday, October 28-31. 9 p.m. until 5 a.m. nightly. Southbound frontage road at Alamo Ranch Parkway. All lanes will close while crews do overhead bridge work. Traffic will turn right onto Alamo Ranch Parkway, turn around and re-enter the frontage road to reach its destination. 
    • Saturday-Sunday, October 29-30. 11:55 p.m. until 5 a.m. nightly. Southbound frontage road between Culebra Road and Alamo Ranch Parkway. All lanes will close while crews do overhead bridge work at Alamo Ranch Parkway. Traffic will use Westwood Loop to reach its destination. This closure includes the southbound exit to Alamo Ranch Parkway. Exiting traffic will use the Culebra Road exit. 
    • Monday, October 31. 9 a.m. until 4 p.m. Southbound exit ramp to Alamo Ranch Parkway. The ramp will close while crews work on guardrail. Traffic will exit Culebra Road and pass through the intersection to reach its destination. 
    • Tuesday, November 1. 9 a.m. until 4 p.m. Southbound main lanes at Culebra Road. The right lane will close while crews work on guardrail. 
    Hwy 151 – Northwest San Antonio
    • Friday-Thursday, October 28-November 3. 9 p.m. until 5 a.m. nightly. Frontage road, both directions, between Wiseman Boulevard and Culebra Road. Alternating lanes will close while crews resurface the road. 
    • Monday-Thursday, October 31-November 3. 9 a.m. until 4 p.m. daily. Westbound frontage road between Wiseman Boulevard and Loop 1604. The frontage road/ramp will close while crews do road work. Traffic will go east on Hwy 151 to Westover Hills and turn around to reach Loop 1604 and Culebra Road. This closure includes one lane of the Hwy 151 lanes as they reach the Loop 1604 connector. 
    • Current until Sunday, October 30. 9 p.m. until 5 a.m. nightly. Westbound main lanes between I-410 and Westover Hills Boulevard. The right lane will close while crews do survey work. This closure will include ramps. Traffic will follow the posted detour route. 
    • Current until December 2016. Westbound exit ramp to Ingram and Potranco roads. The ramp will remain closed while crews install bridge support structures for the direct connector ramps being constructed. 
    Other roads – Seguin
    • Friday, October 28 at 8 p.m. until Sunday, October 30 at 6 p.m. Intersection of King and Cedar streets. The intersection will be closed to all through traffic while crews rebuild the intersection. Traffic will follow the posted detour route. 
    • Current until Saturday, December 31. 9 a.m. until 4 p.m. daily. King Street, both directions, between Cedar Street and US 90. All lanes will close while crews install storm drains and rebuild the road. Traffic will use Hwy 123 as a detour. 
    Other roads – Boerne
    • Sunday-Friday, October 30-November 4. 9 p.m. until 5 a.m. nightly. Scenic Loop Road, both directions, at I-10. Traffic will be reduced to one-way, controlled by off-duty officers while crews do roadwork. 
    Other roads – Southeast Bexar County
    • Sunday-Friday, October 30-November 4. 7 p.m. until 6 a.m. nightly. Northbound WW White between the intersection of WW White and SE Military and I-10. The right lane will close while crews resurface the road. 
    Other roads – Northwest San Antonio
    • Tuesday-Friday, November 1-4. 9 p.m. until 5 a.m. nightly. Military Drive, both directions, at I-410. All lanes will close while crews set bridge support beams overhead. Traffic will use the frontage roads and turnarounds to reach its destination. 
    All closures are pending weather.

    Wednesday, October 26

    Public meeting upcoming: Bandera Rd at Lp 1604

    One of the trickier things we get to do is find a solution to intersections that are simply overloaded with traffic. One of those intersections is Bandera Road at Loop 1604.

    Well, we've got a plan for this intersection. Honestly, the plan is a bit tough to describe here on a blog (it's called a displaced left turn) so we hope you'll come out to see what we're hoping to do during an open house presentation Thursday night. Here are the details:

    • Thursday, Oct. 27, between 6 and 8 p.m. (come as you're able; we won't have a formal presentation but will have tables set up with engineers available for questions).
    • O'Connor High School cafeteria ... that's at 12221 Leslie Road in Helotes.
    • Discussion of proposed plans to address congestion issues on Bandera Road at Lp 1604; please let us know what you think. Your input can impact what will actually happen there.
    In the meantime, take a look at this video showing a similar intersection improvement on I-35 in San Marcos ... then come to the meeting ready to ask questions!

    Tuesday, October 25

    Mail Bag: A month-plus worth of questions

    Does TxDOT evaluate drainage conditions on major roads after a major rain?
    The left lane of the southbound 281 access road between Bitters and Wurzbach Parkway was under water Monday morning (9/26). The on-ramp to 281 was also under water with a stalled car on the ramp. Since there was not a flood gauge on the side of the road, it was hard to know how much water was on the on-ramp.
    - Tom

    We do take a look for problem areas and find ways to address these areas as needed after our major flood events. At your location we don't have a posted flood gauge because it's not the location of a creek bed. Per our Manual for Uniform Traffic Control Devices:
    "If used, the Depth Gauge sign shall be in addition to the ROAD MAY FLOOD, WATER CROSSING, or WHEN FLOODED TURN AROUND DON'T DROWN sign and shall indicate the depth of the water at the deepest point on the roadway." (Section 2C.35.03)
    That same section tells us not to post a "water crossing" sign where water only occasionally or temporarily crosses due to flash floods, like this instance. The "road may flood" sign is for areas with frequent flooding issues. This little section of the southbound frontage road of US 281 does not qualify for one of these signs.

    Do you know when will they begin to finish the clover on 1604 and 281? What is the projected duration of the project? Will they be expanding 281 from 1604 to Overlook Parkway and be adding bridges across the highway - for example, at Evans Road? Thanks.
    - Sal
    Are you talking about the other direct connectors at the intersection of Lp 1604 and US 281? Those are part of a project expanding US 281 to include overpasses and frontage roads through Stone Oak Parkway. That project is set to begin spring 2017 and will take more than three years to complete. Continuing the expressway from Stone Oak Parkway through the Comal County line is targeted for the winter of 2018-2019.

    Can VIA provide new or modified bus route(s) to relieve traffic congestion in the Alamo Ranch area (e.g, Wiseman west of 1604, Alamo Ranch Parkway, Culebra & FM 1560, etc.)?
    - Richard
    This would be a fantastic question to pose to VIA; we can't speak on their behalf.

    Regarding the "zipper merge", does the "merge at the last minute" rule apply to lanes which are used for entrance and exit ramps such as the ones on Loop 1604 between I-10 and Blanco Rd? Would it be possible to post "zipper merge" signs at several needed places in San Antonio?
    -Tom
    To be honest, we're still fleshing out the best places for us to use the late merge or "zipper" as well as signing policies. One place you should always use it is when you're approaching a construction zone or a crash scene that's got lanes closed off. Remember - this really only applies during heavy traffic. If traffic is free flowing and not all that congested, merge as soon as you feel comfortable.
    As for what to do at those ramp merge points, a good rule of thumb is to not cross a solid line. Wait for the broken line. That's supposed to show drivers where merging is to be done, but not everyone has gotten that memo.

    Hi, I think someone wrote up the construction notices incorrectly this week. Your notice said "Current through Wednesday, October 19. 9 p.m. until 5 a.m. nightly. Main lanes, both directions, at Hwy 151. Alternating lanes will close while crews do overhead bridge work. Traffic will use the frontage roads to reach its destination."
    1604 was closed off in the middle of the day all day Saturday, causing backups and gridlock. What happened here?
    - Rick
    Rick, you're absolutely correct. We completely missed the note regarding that closure and dropped the ball. We depend on contractors sending in closure alerts weekly by Thursday night in order to allow our communication staff time to get everything compiled into a weekly report. Sometimes a contractor misses this Thursday deadline, and we're working on getting accountability written into our contracts to prevent this. We're also working to ensure accountability exists when no notice is given.
    In this case, it was an oversight - one that won't soon be repeated.

    How far towards Canyon Lake is the FM 306 expansion project going to go?
    All the way thru to Hgy 281?
    - LD
    The current work we have going runs from about Hunter Road and ends at River Chase. We have another project at the intersection of Bravo, near Canyon Lake, but that's constructing a left-turn lane at that location and won't expand the road beyond that.

    What is the purpose of the new overpass at I-10 and Leon Spring Road?
    - Jim
    Jim, we're assuming you're talking about the work at Old Fredericksburg Road. If we're wrong, let us know.
    We do get asked about the purpose from time to time, and some folks assume it's a widening project that will add capacity to the I-10 main lanes. It's not. All we're doing is adding this new overpass at Old Fred and converting the frontage roads to one-way.
    The frontage road conversion is the key here; it's about safety, really. We're hoping to eliminate the excuse those on two-way frontage roads have when they end up driving the wrong way on an interstate. In order to do that, though, we need to shorten the distance for folks between their access point to I-10 and their feeder road. Old Fred cuts the distance between Ralph Fair and Fair Oaks roughly in half.
    It also provides an additional distribution route for traffic from the growing Leon Springs/Fair Oaks Ranch area to reach I-10. Right now all that traffic is squeezed into Ralph Fair and through Fair Oaks. With this overpass and its accompanying entrances and exits, we're effectively adding a third option for folks to use in order to reach I-10 and commute into town as they are.

    When will the construction of the north bound I-10 off ramp at Hwy 46 in Boerne be completed? This has been going on with little completion for over a year and there doesn't seem to be much current effort to complete it. This intersection is a daily mess. Thanks!
    - Mike
    We're still looking at spring 2017 for completion of this project. We don't have anything going on at the intersection, though, so we shouldn't really be impacting that much at all. None of the lane shifts we've had there actually impacts the operation of the intersection. What you're likely seeing in your daily commute is additional traffic from a rapidly growing section of Boerne.

    On Hwy 46 just East of Boerne the speed limits coming into town are way to fast. There has already been a fatality accident in that area. Traffic should slow down before the Esperonza sub division. Traffic from there to Charger Blvd should not be 50 mph, and from there to the bend at the Kendall County Fair Grounds should be lower than 45. Speed is a proven factor in all accidents. This area is becoming very populated. The limits really need to be lowered. Please!
    - Rodney
    Rodney, there's a specific process for setting our speed limits and our processes rarely yield a lowered speed limit. That said, we checked with our traffic engineer, who dug this information out for us about a rarely used provision in our policy allowing local governments to conduct their own speed studies on state highways, then make their own recommendation to us:

    ==================================================
    TxDOT’s Procedures for Establishing Speed Zones, Chapter 4, Section 2Speed Zones Unacceptable to a CityAlthough TxDOT has the authority to alter the speed limits on highways within the corporate limits of cities or override a speed limit set by city ordinance on such highways, it is intended that studies be made and recommendations be presented to the city for their acceptance and passage of a city ordinance to establish city speed zones. TxDOT should make every effort to have reasonable speed limits established.In the event that a city will not accept the zones within its corporate limits as submitted by the district, and it is not possible to reach an agreement with the city on reasonable and prudent speed limits, then the district should prepare one strip map showing the city’s preference and one strip map showing TxDOT’s  recommendation. Both strip maps should be submitted to TRF along with the district’s request for Transportation Commission action for making one of the zones effective.  When the commission minute order has been passed, the district should send a copy of the minute order, along with a copy of the strip map, to the city.The setting of speed limits within a city by commission minute order should only be used as a last resort; TxDOT should make every effort to secure the cooperation of the city so that the zones will be set by city ordinance.
    ==================================================

    Friday, October 21

    Next week's construction-related closures

    I-10 – Seguin
    • Tuesday, October 25. 9 a.m. until 5 p.m. Westbound main lanes at FM 78. The right lane will close while crews place bridge support beams. This closure includes exit 607. Traffic will follow the posted detour route.
    • Tuesday, October 25 at 9 a.m. until Wednesday, October 26. at 5 a.m. Westbound frontage road between Hwy 123 and Business 123. The left lane will close to stage materials for bridge work.
    I-10 – Fair Oaks Parkway
    • Monday-Wednesday, October 24-26. 9 p.m. until 5 a.m. nightly. Main lanes, both directions, at Fair Oaks Parkway. The right lane will close while crews set barrier.
    I-10 – Northwest San Antonio
    • Monday-Friday, October 24-28. 9 a.m. until 3 p.m. daily. Main lanes, both directions, between I-410 and I-35. The right lane will close while crews pour concrete.
    I-35 – New Braunfels
    • Sunday-Monday, October 23-24. 8 p.m. until 5 a.m. nightly. Southbound main lanes between the Comal-Hays county line and FM 306. Alternating lanes will close while crews lay asphalt.
    I-35 – Northeast San Antonio
    • Sunday-Friday, October 23-28. 9 p.m. until 5 a.m. nightly. Northbound exit to westbound I-410. Alternating lanes will close while crews do overhead bridge work. Traffic will exit Walzem and continue along the frontage road to reach I-410.
    • Sunday-Friday, October 23-28. 9 p.m. until 5 a.m. nightly. Main lanes, both directions, between Rittiman and Walzem roads. Alternating lanes will close while crews do road work.
    • Sunday-Friday, October 23-28. 9 p.m. until 5 a.m. nightly. Frontage roads, both directions, between Rittiman and Walzem. Alternating lanes will close while crews do road work.
    • Monday-Friday, October 24-28. 9 a.m. until 3:30 p.m. daily. Frontage roads, both directions, between Rittiman and Walzem roads. Alternating lanes will close while crews do road work.
    I-35 – East San Antonio
    • Sunday-Friday, October 23-28. 9 p.m. until 5 a.m. nightly. Main lanes, both directions, between I-410 and Broadway. Alternating lanes will close while crews lay asphalt.
    I-410 – Northeast San Antonio
    • Sunday-Friday, October 23-28. 9 p.m. until 5 a.m. nightly. Eastbound exit ramp to Randolph Boulevard and the city of Windcrest. The ramp will close while crews do bridge work. Traffic will exit Thousand Oaks, turn around and return to Randolph Boulevard to reach its destination.
    I-410 – East San Antonio
    • Current through Friday, December 2. Southbound main lanes over North WW White. The right lane will close while crews repair damaged bridge rail.
    I-410 – Northwest San Antonio
    • Friday-Saturday, October 21-22. 11 p.m. until 3 p.m. Southbound main lanes between Military Drive and Hwy 151. The left two lanes will close while crews pour concrete.
    US Hwy 281 – Central San Antonio
    • Sunday-Friday, October 23-28. 9 p.m. until 6 a.m. nightly. Northbound main lanes between West Basse and I-410. Alternating lanes will close while crews resurface the road.
    • Sunday-Friday, October 23-28. 11 a.m. until 3 p.m. daily. Main lanes, both directions, between I-35 and I-410. Alternating lanes will close while crews work on guardrail. This closure includes ramps as needed. Traffic will follow the posted detour route.
    • Sunday-Friday, October 23-28. 9 p.m. until 6 a.m. nightly. Main lanes, both directions, between Airport and Josephine. Alternating lanes will close while crews do bridge work. This closure includes ramps as needed. Traffic will follow the posted detour route.
    Loop 1604 – North San Antonio
    • Monday, October 24. 9 a.m. until 3 p.m. Eastbound main lanes between Huebner Road and Stone Oak Parkway. The right lane and shoulder will close while crews repair signs.
    Loop 1604 – Northwest San Antonio
    • Friday-Saturday, October 21-22. 9 p.m. until 6 a.m. Southbound frontage road at Alamo Ranch Parkway. All lanes will close while crews do overhead bridge work. Traffic will turn right onto Alamo Ranch Parkway, turn around and re-enter the frontage road to reach its destination.
    • Monday-Tuesday, October 24-25. 9 a.m. until 1 p.m. daily. Southbound frontage road at Alamo Ranch Parkway. All lanes will close while crews do overhead bridge work. Traffic will turn right onto Alamo Ranch Parkway, turn around and re-enter the frontage road to reach its destination.
    • Friday-Saturday, October 28-30. 9 p.m. until 6 a.m. daily. Southbound frontage road at Alamo Ranch Parkway. All lanes will close while crews do overhead bridge work. Traffic will turn right onto Alamo Ranch Parkway, turn around and re-enter the frontage road to reach its destination.
    Hwy 151 – Northwest San Antonio
    • Sunday, October 23 until Sunday, October 30. 9 p.m. until 5 a.m. nightly. Westbound main lanes between I-410 and Westover Hills Boulevard. The right lane will close while crews do survey work. This closure will include ramps. Traffic will follow the posted detour route.
    • Sunday-Friday, October 23-28. 9 p.m. until 5 a.m. nightly. Frontage road, both directions, between I-410 and Hunt Lane. Alternating lanes will close while crews repair the road.
    • Tuesday-Wednesday, October 25-26. 9 p.m. until 6 a.m. Westbound main lanes between Wiseman Boulevard and Loop 1604. The right lane will close while crews do electrical work.
    • Wednesday-Thursday, October 26-27. 9 p.m. until 6 a.m. Eastbound main lanes between Loop 1604 and Wiseman Boulevard. The right lane will close while crews do electrical work.
    • Current until December 2016. Westbound exit ramp to Ingram and Potranco roads. The ramp will remain closed while crews install bridge support structures for the direct connector ramps being constructed.
    Other roads – New Braunfels
    • Monday-Friday, October 24-28. 8 a.m. until 4 p.m. daily. FM 306, both directions, between River Chase Drive and Western Oaks Drive. One-way traffic will be controlled by flaggers while crews install underground drain structures across the road.
    • Tuesday-Wednesday, October 25-26. 8 p.m. until 6 a.m. FM 306, both directions, at the intersection of Hoffman Lane. One-way traffic will be controlled by flaggers while crews rebuild the intersection.
    Other roads – Seguin
    • Tuesday, October 25. 9 a.m. until 5 p.m. FM 78, both directions, at I-10. All lanes will close while crews place bridge support beams overhead. Traffic will follow the posted detour.
    • Current until Saturday, December 31. 9 a.m. until 4 p.m. daily. King Street, both directions, between Cedar Street and US 90. All lanes will close while crews install storm drains and rebuild the road. Traffic will use Hwy 123 as a detour.
    Other roads – Boerne
    • Tuesday-Friday, October 25-28. 9 p.m. until 5 a.m. nightly. Scenic Loop Road, both directions, at I-10. Traffic will be reduced to one-way, controlled by off-duty officers while crews do roadwork.
    • Monday-Friday, October 31-November 4. 9 p.m. until 5 a.m. nightly. Scenic Loop Road, both directions, at I-10. Traffic will be reduced to one-way, controlled by off-duty officers while crews do roadwork.
    Other roads – Northeast San Antonio
    • Sunday-Friday, October 23-28, 9 p.m. until 5 a.m. nightly. Randolph Boulevard, both directions, between Crestway and I-35. Traffic will be reduced to a single lane, controlled by off-duty police, while crews do overhead bridge deck work.
    Other roads – South San Antonio
    • Current until Friday, October 28. 9 a.m. until 5 p.m. daily. Northbound Palo Alto Road (state Highway 16) between South Zarzamora and I-410. The right lane will close while crews resurface the road.
    Other roads – Southeast Bexar County
    • Sunday-Friday, October 23-28. 7 p.m. until 6 a.m. nightly. Northbound WW White between the intersection of WW White and SE Military and I-10. The right lane will close while crews resurface the road.
    All closures are pending weather.

    Thursday, October 20

    Mail Bag: I-10 from Leon Springs to Boerne

    Over the last 4-6 weeks we've had a few questions about the various I-10 projects now active between Leon Springs and Boerne. For those not familiar, here's a brief list of what we've got going:
    We've also got an expansion project coming to I-10 in 2017, where we'll be adding two lanes in each direction between La Cantera Parkway and Ralph Fair Road ... but we've not started that yet, so we won't say much about it here for now.
    Anyway, without further ado, here are the questions:

    First, love your blog!
    What are the current projected timelines for the remaining work from Ralph Fair to Fair Oaks on I-10, namely: 
    • New Bridge at Old Fredericksburg Rd 
    • Bridge at Fair Oaks Rd 
    • Conversion of frontage roads to one-way 
    Also, is the westbound exit to Fair Oaks Rd scheduled to be moved farther east before the frontage roads are converted to one-way. 
    I remember reading that all this work would take at least three more years, but can't find that blog post.
    Thanks for keeping us updated!
    - AJ
    Can you provide an update on when the sections between dominion, Boerne stage road, and Ralph Fair will be complete? What is delaying the opening of the lanes on the frontage roads?
    - Christina
    Project update on the I-10 Old Fredericksburg Road overpass? Still on schedule? Whats with the uneven bumpy widening of the east bound frontage road south of Fair Oaks Parkway overpass?
    - Peter
    The completion date for the overpass at Old Fred is still targeted for mid-2018. Sundt is staying on pace with work on this job and trying to speed up where possible. Don't tell too many folks, but they gained nine days on their schedule last month!
    Conversion of the frontage roads to one-way between RFR and FOP will happen when we finish the overpass at Old Fred. Again, that's mid-2018.
    Sundt is working hard on the outside of the frontage roads right now, as well as building up the approaches to the new overpass bridge. If all goes well the bridge supporting drill shafts will be finished this month, allowing concrete crews to start making the support columns through the month of November. On the frontage roads, Sundt wants to be all done with driveway construction before Thanksgiving (sidewalks will be under construction through the rest of the year).
    By the way, Sundt is getting their subcontractor (Austin Materials) to address the bumpy ride on the frontage roads, as well as repairing a couple of potholes that are forming on the main lanes.
    The bridge at Fair Oaks just started this month (Oct. 3) and should wrap up mid-2018. We'll be monitoring this one close to keep it on track. 

    Why do your personnel only work one, and at the most, two days a week on a project and then there is no further work until the next week when they may or may not work one or two days again. Why can't you finish a project in a timely fashion rather than taking up to 2 years to finish and then blaming the weather when the project goes beyond it's estimated completion date. 
    To me, it's not the weather, it's the inefficient method of construction. 
    I live in the I-10W corridor and now have found out it will take 18 months to put in a new bridge at the FOR exit!
    - Gayle
    Why does it appear that there is no work occurring in the construction zones on both the west and east bound frontage roads on I-10 between Boerne Stage Rd and Ralph Fair Rd. The area in front of LaQuinta that appeared is be mostly complete is closed adds to the congestion in that area. I never see anyone working there. The same is true with the Frontage Rd eastbound in front on the new WalMart. Opening this section would relieve congestion at Boerne Stage Rd. What's the delay?
    - Robert
    Why is it your contractors cannot finish just one project? The construction you are doing between the Dominion and Ralph Fair is absolutely terrible. There are literally thousands of residents terribly inconvenienced because of a lack of proper project planning. Your inability to even finish the Ralph Fair area is forcing so many people to be late for work and school. And now you want to start the Fair Oaks project, which is going to be even more of a nightmare without a proper turn around lane, that so many of us will be forced to use.
    - Dave

    First of all, we feel pretty similar about the pace of production and are trying to spur along the work wherever we can. Texas Sterling is keeping with their current baseline schedule, which reflects delays from utilities and from weather - the utility delays were particularly hampering for this project. Those delays have now pushed work well beyond our initial project completion date and Texas Sterling no longer has the available resources to knock the job out (those resources were committed elsewhere some time ago). With a full compliment we might have the job finished by Thanksgiving. Unfortunately that's not the hand we are dealt on this job and we're pushing the best we can to finish by the end of the year. 
    With that in mind, TSC is dividing their forces between work items on the eastbound frontage road near Wal-Mart (need to have the full section finished before reopening this) and east of Boerne Stage (still a lot to do to build the new on-ramp, which will allow them to build the new exit; the remaining work on the frontage road itself will then follow).
    On the westbound side TSC still has curb and sidewalk between Dominion and Fralo's. that bridge at Boerne Stage which has gummed up the elementary school commute lacks bridge rails and approaches, and is currently set to open by Thanksgiving. The last bit, approaching Ralph Fair, has been opened up a bit recently but TSC still has the new RFR exit to finish tying in - that will happen when the bridge by Rudy's is open. 
    Bottom line - TSC is devoting all their available resources to the project and they're keeping pace with the schedule they've submitted to us. We're trying to find areas to improve the pace, but this is the deal we've got for right now.
    As for the relationship of this project to others, folks should note each project out there has a different contractor. RELMCo Incorporated has the Fair Oaks Parkway bridge, and that work shouldn't impact at all the project schedule on the project at Boerne Stage Road.

    It appears that construction has stopped on the I-10 and Scenic Loop project in Boerne. What's the story?
    - Pamela
    The simple answer is we've got a quality control issue the contractor is looking for a fix on. When Austin Bridge and Road put in a temporary wire wall - that wire-mesh wall acting as a temporary retaining wall to allow crews to build the bridge approach and the permanent retaining wall simultaneously - our inspectors noticed some problems. We've been working the last week or two to find a fix, and the folks at Austin Bridge have submitted some paperwork to our bridge division to show what they have will indeed work.
    Until it's all ironed out, they really can't do much. Since this is an issue caused by the contractor, we are still charging time against the contract, so this could cost Austin Bridge a bit if it's left untended too long.
    We're hoping to see progress on that bridge resume next week. If our engineers disagree with the Austin Bridge position on the current wire wall, we will require them to tear down everything and start over - at their cost. Right now, though progress is minimal (or, as you've pointed out, non-existent), everyone on the project is actually trying to save a little time (and, yes, money).
    In the meantime, and to Austin Bridge's credit, they are doing work down on the intersection area as they are able during this down time.