Friday, August 30

UPCOMING SCHEDULED CLOSURES -- NONE OVER LABOR DAY WEEKEND

Loop 1604 – North Central San Antonio
  • Tuesday, September 3 until Friday, September 6. Nightly 9 p.m. until 5 a.m. Full eastbound mainlane closure of the US 281 north exit ramp to the Redland Road entrance ramp for bridge span work. DETOUR: Use the US 281 north exit ramp through the US 281 and Gold Canyon Road intersections and use the Gold Canyon Road entrance ramp.
  • Tuesday, September 3 until Friday, September 6. Nightly 9 p.m. until 5 a.m. Full westbound mainlane closure from the US 281 north exit ramp to the US 281 entrance ramp for bridge span work. DETOUR: Use the US 281 north exit ramp, continue through the US 281 intersection and use the US 281 Entrance Ramp.
  • Friday, September 6 until Monday, September 9. Full weekend closure 9 p.m. until 5 a.m. Full westbound frontage road closure from Gold Canyon Road to the US 281 northbound frontage road for utility work. DETOUR: Take a double left at Gold Canyon Road, take a double left at Redland Road, use the Redland Road entrance ramp, take the Stone Oak Parkway exit ramp, use the turnaround at Stone Oak Parkway.
  • Saturday, September 7 until Monday, September 9. Full weekend closure 2 a.m. until 5 a.m. Full eastbound mainlane closure of the US 281 north exit ramp to the Redland Road entrance ramp for direct connector work. DETOUR: Use the US 281 north exit ramp through the US 281 and Gold Canyon Road intersections and use the Gold Canyon Road entrance ramp.
  • Saturday, September 7 until Monday, September 9. Full weekend closure 2 a.m. until 5 a.m. Full westbound mainlane closure from the US 281 north exit ramp to the US 281 Entrance Ramp for direct connector work. DETOUR: Use the US 281 north exit ramp, continue through the US 281 intersection and use the US 281 entrance ramp.
Loop 1604 – Northeast San Antonio
  • Tuesday, September 3 until Saturday, September 14 (excluding Sundays). Daily 8 a.m. until 4 p.m. Westbound left frontage road lane between Redland Road and Bulverde Road for truck/material access.
Loop 1604 – Northwest San Antonio
  • Tuesday, September 3 until Friday, September 6. Nightly 9 p.m. until 5 a.m. Eastbound frontage road from SH 16 (Bandera Road) to Roger’s Ranch Road for pavement marking installation work.
  • Tuesday, September 3 until Friday, September 6. Daily 9 a.m. until 5 p.m. Eastbound frontage road from SH 16 (Bandera Road) to Roger’s Ranch Road for riprap and mow strip work.
Loop 1604 – West San Antonio
  • Tuesday, September 3 until Saturday, September 7. Daily 9 a.m. to 3 p.m. Alternating northbound frontage road between south of US 90 to just south of FM 1957 (Potranco Road) for closeout item work.
  • Tuesday, September 3 until Saturday, September 7. Daily 9 a.m. to 3 p.m. Alternating northbound mainlanes between south of US 90 to just south of FM 1957 (Potranco Road) for closeout item work.
  • Tuesday, September 3 until Saturday, September 7. Daily 9 a.m. to 3 p.m. Alternating southbound mainlanes between south of FM 1957 (Potranco Road) to just south of US 90 for closeout item, sidewalk, curb, mow strip and rip rap work.
  • Tuesday, September 3 until Saturday, September 7. Daily 9 a.m. to 5 p.m. The northbound Wiseman Boulevard exit ramp for beam curb work.
  • Tuesday, September 3 until Saturday, September 7. Daily 9 a.m. to 7 p.m. Alternating northbound frontage road lanes between south of FM 1957 (Potranco Road) to SH 151 for driveway and sign work.
  • Tuesday, September 3 until Saturday, September 7. Daily 9 a.m. to 7 p.m. Alternating southbound frontage road lanes between SH 151 to south of FM 1957 (Potranco Road) for driveway and sign work.
  • Tuesday, September 3 until Saturday, September 7. Nightly 7 p.m. to 5 a.m. Alternating northbound frontage road lanes between SH 151 to south of FM 1957 (Potranco Road) for milling and paving work.
  • Tuesday, September 3 until Saturday, September 7. Nightly 7 p.m. to 5 a.m. Alternating lanes in both directions at FM 1957 (Potranco Road), Military Drive and Wiseman Boulevard for milling and final pavement work.
US 281 – North Central San Antonio
  • Tuesday, September 3 until Friday, September 6. Nightly 9 p.m. until 5 a.m. Full northbound mainlane closure from the Frontage Road exit ramp to the Sonterra Boulevard entrance ramp for direct connector work. DETOUR: Take the Frontage Road exit ramp, continue on the US 281 northbound frontage road through the Loop 1604 intersections and and use the Sonterra Boulevard entrance ramp.
  • Tuesday, September 3 until Friday, September 6. Nightly 9 p.m. until 5 a.m. Full southbound mainlane closure from the Sonterra Boulevard exit ramp to the Donella Drive entrance ramp for direct connector work. DETOUR: Take the Sonterra Boulevard exit ramp, continue on the Southbound Frontage Road through the Loop 1604 and Donella Drive intersections and use the Donella Drive entrance ramp.
  • Tuesday, September 3 until Friday, September 6. Nightly 9 p.m. until 5 a.m. Alternating northbound mainlane closure from Loop 1604 to Marshall Road for utility work and safety enhancements.
  • Tuesday, September 3 until Friday, September 6. Nightly 9 p.m. until 5 a.m. Alternating southbound mainlane closure from Marshall Road to Loop 1604 for bridge, PCP, retaining wall work and safety enhancements.
  • Tuesday, September 3 until Friday, September 6. Nightly 9 p.m. until 5 a.m. Alternating southbound mainlane closure of one of two left turn lanes at Evans Road for utility work.
  • Saturday, September 7 until Monday, September 9. Weekend continuous 2 a.m. until 5 a.m. Full northbound mainlane closure from the Frontage Road exit ramp to the Sonterra Boulevard entrance ramp for direct beam work. DETOUR: Take the Frontage Road exit ramp, if heading north on US 281, take a right on the Loop 1604 eastbound frontage road, use the turnaround at Gold Canyon Road and take a right at the Northbound Frontage Road. If heading west on the Eastbound Frontage Road, go through the Gold Canyon Road intersection, use the turnaround at Redland Road, take the Redland Road entrance ramp and use the Stone Oak Parkway exit ramp.
  • Saturday, September 7 until Monday, September 9. Weekend continuous 2 a.m. until 5 a.m. Full northbound mainlane closure from the Frontage Road exit ramp to the Sonterra Boulevard entrance ramp for direct beam work. DETOUR: Take the Frontage Road exit ramp, continue on the US 281 Northbound Frontage Road through the Loop 1604 intersections and use the Sonterra Boulevard entrance ramp.
  • Saturday, September 7 until Monday, September 9. Weekend continuous 2 a.m. until 5 a.m. Full northbound frontage road closure from the Loop 1604 westbound frontage road to Sonterra Boulevard for beam work. DETOUR: On the Loop 1604 westbound frontage road, turn left on the US 281 Southbound Frontage Road, take the turnaround at Donella Drive and use the US 281 Donella Drive entrance ramp.
I-10 – Northwest San Antonio/Bexar County/Kendall County/Kerr County
  • Tuesday, September 3 until Thursday, September 5. Nightly 9 p.m. until 6 a.m. One frontage road lane in both directions at Balcones Creek for barrier setting work.
  • Tuesday, September 3 until Friday, September 6. Nightly 9 p.m. until 5 a.m. Alternating mainlanes in both directions from SH 46 to Scenic Loop Road for barrier placement and pavement marking work in preparation for traffic switch.
I-10 – Far East San Antonio/Bexar County/Guadalupe County
  • Current until further notice. Eastbound entrance ramp from FM 1516. DETOUR: Take next entrance ramp east of Loop 1604.
  • Current until further notice. Eastbound Ackerman Road exit ramp will be closed through the summer. DETOUR: Eastbound I-10 and southbound I-410 traffic wishing to access Ackerman Road must take southbound I-410, exit at FM 1346/E. Houston St., turn around and take the northbound frontage road to Ackerman Road.
  • Tuesday, September 3 until Friday, September 6. Nightly 9 p.m. until 5 a.m. Left eastbound mainlane from Rosillo Creek bridge to Woodlake Parkway for concrete truck access and drainage work.
  • Wednesday, September 4 until Thursday, September 5. 7:30 a.m. until 7 p.m. Alternating eastbound mainlanes from SH 130 to US 183 for asphalt work.
  • Monday, September 9 until Wednesday, September 11. Nightly 7 p.m. until 5 a.m. Ackerman Road will be closed in both directions under I-10 for concrete beam placement. DETOUR: Northbound Ackerman Road traffic will take the I-10 eastbound frontage road to Foster Road, turn around, and take the I-10 westbound frontage road back to Ackerman Road. Southbound Ackerman Road traffic will take the I-10 westbound entrance ramp just west of Ackerman, stay in the right lane, take the I-410 South connecting ramp, travel southbound on I-410, exit to FM 1346/E. Houston St., turn around, and take the northbound frontage road back to Ackerman Road.
  • Monday, September 9 until Friday, September 27. Daily 7 a.m. until 5 p.m. Woodlake Parkway will be closed at the I-10 westbound frontage road. DETOUR: Traffic wishing to access the Horizon Pointe subdivision will continue traveling on the westbound frontage road, turn right on Foster Road, and take another right on Sierra Sunset to return to Woodlake Parkway.
I-10 – Central San Antonio
  • Tuesday, September 3 until Friday, September 6. Nightly 8:30 p.m. until 5 a.m. Westbound left mainlane at I-37 (including I-37 southbound ramp) for guard fence installation work.
I-35 – Northeast San Antonio & Comal County
  • Tuesday, September 3 until Saturday, September 7. Daily 9 a.m. until 3 p.m. Right frontage road lane in both directions between Austin Street and New Braunfels Avenue for sidewalk and driveway work.
  • Tuesday, September 3 until Wednesday, September 4. Nightly 9 p.m. until 5 a.m. Alternating southbound mainlanes between Schwab Road and FM 1103 for barrier installation work.
  • Wednesday, September 4 until Friday, September 6. Nightly 9 p.m. until 5 a.m. Alternating northbound frontage road lanes between FM 1103 and Schwab Road for barrier installation work.
  • Friday, September 6 until Saturday, September 7. 9 p.m. until 5 a.m. Alternating southbound frontage road lanes between Schwab Road and FM 1103 for barrier installation work.
I-410 – West San Antonio
  • Tuesday, September 3 until Thursday, September 5. Daily 9 a.m. to 3 p.m. The left eastbound frontage road between Ray Ellison Drive to I-410 to set equipment for work under the connector.
  • Tuesday, September 3 until Saturday, September 7. Daily 8 a.m. to 7 p.m. The left westbound mainlane between just east of Loop 1604 to just west of US 90 for mowstrip work.
  • Tuesday, September 3 until Saturday, September 7. Daily 9 a.m. to 3 p.m. Alternating eastbound frontage road between west of Loop 1604 to east of Loop 1604 island ramp work.
  • Tuesday, September 3 until Friday, September 6. Nightly 8 p.m. to 5 a.m. All westbound mainlanes between I-410 to Hunt Lane for rail and single slope concrete barrier work. DETOUR: Traffic will continue on the frontage road to access the next entrance ramp.
US 90 – West San Antonio
  • Tuesday, September 3 until Thursday, September 5. Daily 9 a.m. to 3 p.m. The left eastbound frontage road between Ray Ellison Drive to I-410 to set equipment for work under the connector.
  • Tuesday, September 3 until Saturday, September 7. Daily 8 a.m. to 7 p.m. The left westbound mainlane between just east of Loop 1604 to just west of US 90 for mowstrip work.
  • Tuesday, September 3 until Saturday, September 7. Daily 9 a.m. to 3 p.m. Alternating eastbound frontage road between west of Loop 1604 to east of Loop 1604 island ramp work.
  • Tuesday, September 3 until Friday, September 6. Nightly 8 p.m. to 5 a.m. All westbound mainlanes between I-410 to Hunt Lane for rail and single slope concrete barrier work. DETOUR: Traffic will continue on the frontage road to access the next entrance ramp.
  • Tuesday, September 3 until Saturday, September 7. Daily 9 a.m. until 3 p.m. Eastbound right frontage road lane from Springvale Drive to West Military Road for sidewalk and driveway work.
PA 1502 – Wurzbach Parkway
  • City of San Antonio closure for Hardberger Park Landbridge project. Monday, September 2 until Friday, September 6. Daily 9 a.m. until 4 p.m. Right lane in both directions from FM 1535 (NW Military Hwy.) to FM 2696 (Blanco Road) for construction truck and equipment access.
  • City of San Antonio closure for Hardberger Park Landbridge project. Saturday, September 7. 7 a.m. until 5 p.m. Right lane in both directions from FM 1535 (NW Military Hwy.) to FM 2696 (Blanco Road) for construction truck and equipment access.
FM 1560 – Hausman Road
  • Tuesday, September 3 until Friday, September 6. Nightly 9 p.m. until 5 a.m. Eastbound left lane from SH 16 to Loop 1604 for utility work.
Spur 371 – General Hudnell Drive
  • Tuesday, September 3 until Friday, September 6. Daily 7 a.m. to 3 p.m. The northbound left lane between Billy Mitchell Boulevard and Cupples Road for removing existing guardrail and installing concrete barrier.
  • Tuesday, September 3 until Friday, September 6. Daily 9 a.m. to 5 p.m. The southbound left lane between Billy Mitchell Boulevard and Cupples Road for removing existing guardrail and installing concrete barrier.
Loop 13 – WW White Road
  • Tuesday, September 3 until Saturday, September 7. Daily 9 a.m. until 4 p.m. Northbound right lane from Emil Road to Springfield Road for sidewalk and driveway work.
FM 1976 – Walzem Road
  • Current until further notice. Daily 7 a.m. until 7 p.m. Alternating southbound lanes from Woodlake Parkway until Gibbs Sprawl Road for barrier work (existing seven total lanes narrowed to three, with one in each direction and a two-way turn lane in the middle).
SH 46 – Boerne/Kendall County
  • Current until further notice. 9 p.m. until 5 a.m. Eastbound left lane from East Sharon Drive to Charger Boulevard for traffic switch (drivers diverted to the right side for construction access on the right side; left turn lane remains open).
I-37 – Atascosa County
  • Current until 10 p.m. Saturday, August 31. Alternating northbound mainlanes from Mile Marker 108 to Mile Marker 117 for paving work.
Other Roads – Bexar County
  • Wednesday, September 4 until Friday, September 6. Nightly 9 p.m. until 5 a.m. All lanes in both directions of Wilderness Parkway at US 281 for restriping work.
  • Tuesday, September 3 until Friday, September 6. Nightly 9 p.m. until 5 a.m. Alternating eastbound crossing closure East of US 281 for traffic phasing.
  • Tuesday, September 3 until Friday, September 6. Nightly 9 p.m. until 5 a.m. Alternating westbound crossing closure East of US 281 for traffic phasing.

Friday, August 23

UPCOMING SCHEDULED CONSTRUCTION CLOSURES

Loop 1604 – North Central San Antonio
  • Monday, August 26 until Friday, August 30. Nightly 9 p.m. until 5 a.m. Full eastbound mainlane closure of the US 281 northbound exit ramp to the Redland Road entrance ramp for bridge span work. DETOUR: Use the US 281 northbound exit ramp through the US 281 and Gold Canyon Road intersections and use the Gold Canyon Road entrance ramp.
  • Monday, August 26 until Friday, August 30. Nightly 9 p.m. until 5 a.m. Full westbound mainlane closure from the US 281 northbound exit ramp to the US 281 Entrance Ramp for bridge span work. DETOUR: Use the US 281 northbound exit ramp, continue through the US 281 intersection and use the US 281 Entrance Ramp.
Loop 1604 – Northeast San Antonio
  • Monday, August 26 until Thursday, August 29. Daily 8 a.m. until 4 p.m. Westbound frontage road left lane between Redland Road and Bulverde Road for truck/material access.
  • Current until 9 a.m. Saturday, Full eastbound mainlane closure at FM 2252 (Nacagdoches Road) for barrier removal work and guard fence and rail installation work.
  • Sunday, August 25 until Friday, August 30. Nightly 9 p.m. to 5 a.m. The right mainlane in both directions between Lakeview Parkway to FM 2252 (Nacogdoches Road) for pavement bore work.
  • Sunday, August 25 until Friday, August 30. Nightly 9 p.m. to 5 a.m. Alternating mainlanes in both directions between I-35 to FM 2252 (Nacogdoches Road) for pavement bore work.
  • Monday, August 26 until Wednesday, August 28. Nightly 9 p.m. until 5 a.m. Left mainlane in both directions from Kitty Hawk to Palisades for barrier resetting work.
Loop 1604 – West San Antonio
  • Sunday, August 25 until Thursday, August 29. Nightly 7 p.m. to 5 a.m. Alternating northbound frontage road lanes between SH 151 to south of FM 1957 (Potranco Road) for milling and paving work.
  • Sunday, August 25 until Thursday, August 29. Nightly 7 p.m. to 5 a.m. Alternating lanes in both directions at FM 1957 (Potranco Road), Military Drive, and Wiseman Boulevard for milling and final pavement work.
  • Monday, August 26 until Friday, August 30. Daily 9 a.m. to 5 p.m. Alternating lanes in both directions at FM 1957 (Potranco Road), Military Drive, and Wiseman Boulevard for sign and curb/directional island work.
  • Monday, August 26 until Thursday, August 30. Daily 9 a.m. to 5 p.m. The northbound Wiseman Boulevard exit ramp for beam curb work.
  • Monday, August 26 until Friday, August 30. Daily 9 a.m. to 5 p.m. Alternating northbound frontage road lanes between south of FM 1957 (Potranco Road) to SH 151 for driveway and curb work.
  • Monday, August 26 until Friday, August 30. Daily 9 a.m. to 5 p.m. Alternating southbound frontage road lanes between SH 151 to south of FM 1957 (Potranco Road) for final paving and rip rap work.
US 281 – North Central San Antonio
  • Friday, August 23 until Sunday, August 25. Full weekend closure 9 p.m. until 5 a.m. Full northbound frontage road closure from the Loop 1604 westbound frontage road to Sonterra Boulevard for bridge cap work. DETOUR: On the Loop 1604 westbound frontage road, turn left on the US 281 Southbound Frontage Road, take the turnaround at Donella Drive and use the US 281 Donella Drive entrance ramp.
  • Friday, August 23 until Monday, August 26. Full weekend closure 9 p.m. until 5 a.m. Alternating northbound mainlane closure of one of two left turn lanes at Evans Road for phasing work.
  • Friday, August 23 until Monday, August 26. Full weekend closure 9 p.m. until 5 a.m. Alternating southbound mainlane closure at Evans Road for phasing work.
  • Monday, August 26 until Friday, August 30. Nightly 9 p.m. until 5 a.m. Full northbound mainlane closure from the Frontage Road exit ramp to the Sonterra Boulevard entrance ramp for direct connector work. DETOUR: Take the Frontage Road exit ramp, if heading north on US 281, take a right on the Loop 1604 Eastbound Frontage Road, use the turnaround at Gold Canyon Road and take a right at the Northbound Frontage Road. If heading west on the Eastbound Frontage Road, go through the Gold Canyon Road intersection, use the turnaround at Redland Road, take the Redland Road entrance ramp and use the Stone Oak Parkway exit ramp.
  • Monday, August 26 until Friday, August 30. Nightly 9 p.m. until 5 a.m. Full southbound mainlane closure from the Sonterra Boulevard exit ramp to the Donella Drive entrance ramp for direct connector work. DETOUR: Take the Sonterra Boulevard exit ramp, continue on the southbound frontage road through the Loop 1604 and Donella Drive intersections and use the Donella Drive entrance ramp.
  • Monday, August 26 until Friday, August 30. Nightly 9 p.m. until 5 a.m. Full northbound frontage road closure from the Loop 1604 westbound frontage road to Sonterra Boulevard for bridge cap work. DETOUR: On the Loop 1604 westbound frontage road, turn left on the US 281 southbound frontage road, take the turnaround at Donella Drive and use the US 281 Donella Drive entrance ramp.
  • Monday, August 26 until Friday, August 30. Nightly 9 p.m. until 5 a.m. Alternating northbound mainlane closure from Loop 1604 to Marshall Road for utility work and safety enhancements.
  • Monday, August 26 until Friday, August 30. Nightly 9 p.m. until 5 a.m. Alternating southbound mainlane closure from Marshall Road to Loop 1604 for bridge, PCP, retaining wall work and safety enhancements.
US 281 – Southern Region
  • Sunday, August 25 until Thursday, August 29. Nightly 8 p.m. to 5 a.m. Alternating northbound lanes 0.25 miles south and 0.25 north of Mission Del Lago for concrete barrier work
I-10 – Northwest San Antonio/Bexar County/Kendall County/Kerr County
  • Sunday, August 25 until Friday, August 30. Nightly 9 p.m. until 5 a.m. Alternating mainlanes in both directions between Scenic Loop and SH 46 for barrier resetting and pavement marking work.
  • Sunday, August 25 until Friday, August 30. Nightly 9 p.m. until 5 a.m. Full mainlane closure in both directions between Fair Oaks Parkway and Old Fredericksburg Road (exits 546-548, including entrance/exit ramps) for milling and paving work.
  • Sunday, August 25 until Friday, August 30. Nightly 9 p.m. until 6 a.m. Eastbound right mainlane from Scenic Loop to Balcones Creek Road (including Boerne Stage entrance ramp) for milling and paving work.
I-10 – Far East San Antonio/Bexar County/Guadalupe County
  • Current until further notice. Eastbound entrance ramp from FM 1516. DETOUR: Take next entrance ramp east of Loop 1604.
  • Current until further notice. Eastbound Ackerman Road exit ramp will be closed through the summer. DETOUR: Eastbound I-10 and southbound I-410 traffic wishing to access Ackerman Road must take southbound I-410, exit at FM 1346/E. Houston St., turn around, and take the northbound frontage road to Ackerman Road.
  • Monday, August 26 until Friday, August 30. Nightly/daily 9 p.m. to 5 a.m. Left eastbound frontage road lane from Rosillo Creek to Foster Road for traffic barrier placement.
I-10 – Central San Antonio
  • Sunday, August 25 until Wednesday, August 28. Nightly 8:30 p.m. until 5 a.m. Westbound left mainlane at I-37 (including I-37 southbound ramp) for guard fence installation work.
I-35 – Northeast San Antonio & Comal County
  • Current until Friday, August 30. Nightly 9 p.m. to 5 a.m. Left mainlane in both directions between Walters Street just north of FM 1103 for pavement bore work.
  • Monday, August 26 until Friday, August 30. Daily 9 a.m. until 3 p.m. Right frontage road lane in both directions between Austin Street and New Braunfels Avenue for sidewalk and driveway work.
  • Sunday, August 25 until Monday, August 26. 9 p.m. until 5 a.m. Right mainlane in both directions between Walters Street and I-410 for pavement bore work.
  • Sunday, August 25 until Thursday, August 29. Nightly 9 p.m. until 5 a.m. Alternating southbound mainlanes between Schwab Road and FM 1103 for barrier installation work.
  • Sunday, August 25 until Friday, August 30. Nightly 9 p.m. to 5 a.m. Left mainlane shoulder and alternating frontage road lanes in both directions between Walters Street to just north of FM 1103 for pavement bore work.
  • Wednesday, August 28 until Friday, August 30. Nightly 8:30 p.m. until 5 a.m. Northbound left mainlane at I-10 (including US 90 westbound exit ramp) for guard fence installation work.
I-410 – West San Antonio
  • Friday, August 23 until Saturday, August 24. Nightly 8 p.m. to 5 a.m. All northbound mainlanes between US 90 exit ramp to SH 151 restriping the mainlanes, open the new Marbach Road ramp, and ramp reversal on the SH 151 on and off ramp. DETOUR: All traffic will be detoured the northbound frontage road to access the next on-ramp.
  • Saturday, August 24 until Monday, August 26. Nightly 8 p.m. to 5 a.m. All southbound mainlanes between Lakeside exit ramp to US 90 bridge for traffic switch. The Marbach Road, US 90 exit ramp and south/westbound connector ramp will also be closed. DETOUR: All traffic will be detoured to continue on the southbound frontage road to Valley Hi Drive.
  • Sunday, August 25 until Tuesday, August 27. Nightly 8 p.m. to 5 a.m. The left northbound mainlane between US 90 exit ramp to SH 151 entrance ramp for staging equipment and mill asphalt.
  • Sunday, August 25 until Tuesday, August 27. Nightly 8 p.m. to 5 a.m. The left southbound mainlane between Lakeside exit ramp to US 90 bridge at I-410 for staging equipment and mill asphalt work.
  • Monday, August 26 until Thursday, August 29. Daily 9 a.m. to 3 p.m. The right northbound frontage road lane between Meadow Leaf to Meadow Glade Drive for staging equipment and sidewalk work.
  • Monday, August 26 until Thursday, August 29. Daily 9 a.m. to 3 p.m. The left southbound frontage road lane between Waters Edge to Marbach Road for staging equipment and ditch work.
I-410 – Northeast San Antonio
  • Sunday, August 25 until Friday, August 30. Nightly 9 p.m. to 5 a.m. The left frontage road lane in both directions between Wehman Drive to Nacogdoches Road for pavement bore work.
  • Sunday, August 25 until Friday, August 30. Nightly 9 p.m. to 5 a.m. The right mainlane in both directions between Wehman Drive to Nacogdoches Road for pavement bore work.
PA 1502 – Wurzbach Parkway
  • City of San Antonio closure for Hardberger Park Landbridge project. Monday, August 26 until Friday, August 30. Daily 9 a.m. until 4 p.m. Right lane in both directions from FM 1535 (NW Military Hwy.) to FM 2696 (Blanco Road) for construction truck and equipment access.
  • City of San Antonio closure for Hardberger Park Landbridge project. Saturday, August 31. 7 a.m. until 5 p.m. Right lane in both directions from FM 1535 (NW Military Hwy.) to FM 2696 (Blanco Road) for construction truck and equipment access.
SH 218 – Pat Booker Road
  • Wednesday, August 28 until Friday, August 30. Nightly 9 p.m. until 5 a.m. Full westbound closure at Loop 1604 for bridge work.
Spur 371 – General Hudnell Drive
  • Monday, August 26 until Thursday, August 29. Daily 7 a.m. to 3 p.m. The northbound left lane between Billy Mitchell Boulevard and Cupples Road for removing existing guardrail and installing concrete barrier.
  • Monday, August 26 until Thursday, August 29. Daily 9 a.m. to 5 p.m. The southbound left lane between Billy Mitchell Boulevard and Cupples Road for removing existing guardrail and installing concrete barrier.
Loop 13 – WW White Road
  • Current until 5 a.m. Saturday, August 24. Southbound left lane at Martin Luther King Boulevard for sidewalk and driveway work.
FM 1976 – Walzem Road
  • Current until further notice. Daily 7 a.m. until 7 p.m. Alternating southbound lanes from Woodlake Parkway until Gibbs Sprawl Road for barrier work (existing seven total lanes narrowed to three, with one in each direction and a two-way turn lane in the middle).
SH 46 – Boerne/Kendall County
  • Current until further notice. 9 p.m. until 5 a.m. Eastbound left lane from East Sharon Drive to Charger Boulevard for traffic switch (drivers diverted to the right side for construction access on the right side; left turn lane remains open).
  • Monday, August 26 until Friday, August 30. Daily 7 a.m. until 7 p.m. Intersections with Copper Creek, Herff Ranch and Charger for reconstruction and paving. Work will be performed on the side roads so traffic on SH 46 should not be impacted.
I-37 – Atascosa County
  • Current until Saturday, August 31. Daily 6 a.m. until 10 p.m. Alternating northbound mainlanes from Mile Marker 108 to Mile Marker 117 for paving work.
SH 16 – Atascosa/McMullen County
  • Current until Friday, August 30. Daily 5:30 a.m. until 7 p.m. Alternating lanes in both directions from FM 1332 to the Atascosa/McMullen County line for milling and inlay, bridge rail and guard fence work.
  • Monday, August 26 until Friday, August 30. Daily 8 a.m. until 5 p.m. Alternating southbound lanes from Tilden to FM 624 (Mile Markers 686-696) for excavation work.
Other Roads – Bexar County
  • City of San Antonio project. Current until Friday, August 30. Daily 9 a.m. until 4 p.m. Southbound left lane of North Pecos Street at Buena Vista for sidewalk and curb work.
  • Current until Monday, August 26. Full weekend closure 9 p.m. until 5 a.m. Alternating eastbound crossing closure of Evans Road west of US 281 for intersection work.
  • Friday, August 23 until Monday, August 26. Full weekend closure 9 p.m. until 5 a.m. Alternating westbound crossing closure of Evans Road west of US 281 for intersection work.
  • Wednesday, August 28 until Friday, August 30. Nightly 9 p.m. until 5 a.m. All lanes in both directions of Wilderness Parkway at US 281 for restriping work.

I-410/US 90 Interchange Project: Traffic Switch & Ramp Work

New exit for SH 151 on I-410 northbound
For our peeps on San Antonio's West Side, listen up, this one's for you!

There will be quite a bit of construction activity taking place this weekend on the I-410/US 90 interchange project.

Friday night
Starting tonight (Friday 8/23) at 8 p.m., all northbound mainlanes between the US 90 exit ramp to SH 151 will be closed to restripe the northbound mainlanes and open up the new exit ramps for Marbach Road and SH 151.

A third frontage road lane will also open up for the exit and entrance ramps. Traffic will be detoured to the frontage road. The new configuration will be open to traffic tomorrow (Saturday 8/24) at 5 a.m.

Saturday night
Later that same day (Saturday) starting at 8 p.m. and running through Monday (8/26) morning at 5 a.m. all southbound mainlanes between the Lakeside exit ramp to the US 90 bridge will be closed to prepare for a traffic switch and to open up the new Marbach Road entrance ramp.
Crews working on the new southbound entrance ramp near Marbach Road


A look ahead
We are gradually approaching the last phase of this project (yay!) that is expected to be completed in 2020. We know, we know, that should prompt a round of applause for everyone!

But we're not quite there yet. We still have work at Marbach Road that includes demolishing the middle section of the current bridge.

Weather permitting, we are planning for the bridge to be demolished the weekend after Labor Day. Stay tuned here and on our social media channel for further updates on this project!

Wednesday, August 21

US 281 Phase I Expansion Project: Evans Road Traffic Switch Scheduled This Weekend


Important step taking place this weekend on the US 281 Phase I Expansion project!

We've been working on the reconstruction of Evans Road a bit a time. This weekend, our contractor (Webber) will be putting in place  traffic switch on the westbound side of the Evans & 281 intersection (see adjacent illustration).

As a result, both westbound and eastbound will be reduced to one lane in both directions at the 281 intersection. 

This is so crews can finish the intersection reconstruction process on the west side of the intersection.

The switch will start this Friday, August 23, at 9 p.m. and will be in place for the weekend, until  5 a.m. Monday, August 26. The goal is to have Evans fully reopened with two lanes in each direction by the Monday morning commute.

Intersection reconstruction can require multiple changes in traffic flow/configuration to ensure construction can be completed smoothly and -- most importantly -- safely for drivers and crews. We appreciate your patience during this switch.

As always, we remind you that any scheduled work is subject to change due to weather and other factors that could prompt a delay.

Tuesday, August 20

I-10 & SH 46 in Boerne: Retaining Wall Work Requires Turn Lane Change

Lots and lots of work going on in Boerne, we know!

As part of our project on I-10 improvements between Scenic Loop Road and SH 46, our contractor has begun working on the retaining wall at the I-10 & SH 46 intersection.

You may have noticed this has had an impact on the existing SH 46 bridge/overpass over I-10.
 itself. In order to safely conduct this retaining wall work, the contractor was required to remove the northbound SH 46 right lane, which in turn forced to take away the dedicated left-turn lane to get on the I-10 westbound frontage road (see map above). 

So the one open lane is being used both for left turns as well as for through-traffic continuing on SH 46 past I-10. The traffic light has been adjusted to reflect this traffic flow change. As you may expect, this necessary move will cause delays, as drivers waiting to go straight through will have to wait until those making the left turn clear out (these in turn have to yield to southbound SH 46 traffic coming the other way).