Friday, May 1

Next week's construction-related closures

I-10
  • Sunday-Friday, May 3-8. 8:30 p.m. until 5:30 a.m. nightly. Frontage road, both directions between Loop 1604 and Huebner Road (northwest San Antonio). Alternating lanes will close for road work.
  • Sunday-Friday, May 3-8. 8:30 p.m. until 5:30 a.m. nightly. Main lanes, both directions, between Huebner Road and Loop 1604 (northwest San Antonio). Alternating lanes will close while crews repave the roadway and work on overhead highway signs.
  • Monday-Friday, May 4-8. 9 a.m. until 4 p.m. daily. Frontage road, both directions, between Loop 1604 and Huebner Road (northwest San Antonio). Alternating lanes will close for road work.
  • Wednesday-Thursday, May 6-7. 9 p.m. until 5 a.m. Westbound frontage road at Boerne Stage Road (Leon Springs). The signals will be turned off and traffic will be controlled by officers while crews work on temporary traffic signals.
  • Wednesday-Thursday, May 6-7. 9 p.m. until 5 a.m. Westbound frontage road between Dominion Drive and the Boerne Stage Road exit ramp (Leon Springs). All lanes will close while crews do road work. Traffic will use the two-way frontage road on the eastbound side of I-10.
  • Friday-Monday, May 8-11. 8:30 p.m. until 5:30 a.m. continuous. Westbound exit ramp to DeZavala Road and Woodstone Drive (northwest San Antonio). The ramp will close for the weekend while crews do road work. Traffic will exit UTSA Boulevard and turn around to reach its destination.
  • Monday-Tuesday, May 11-12. 9 a.m. until 3 p.m. daily. Westbound exit ramp to Ralph Fair Road (Leon Springs). The ramp will close while crews resurface the road surface. Traffic will exit Fair Oaks Parkway and turn around.
I-35
  • Sunday-Friday, May 3-8. 8:30 p.m. until 5:30 a.m. nightly. Southbound main lanes between FM 3009 and Solms Road (Schertz-New Braunfels). Alternating lanes will close, including alternating closures of exit or entrance ramps, while crews repave the roadway.
  • Sunday-Friday, May 3-8. 8:30 p.m. until 5:30 a.m. nightly. Northbound main lanes between Schwab and Solms roads (New Braunfels). All lanes will close while crews repave the roadway. Traffic will exit Schwab Road and re-enter after Solms Road.
  • Friday, May 1-Saturday, May 9. 9 p.m. until 5:30 a.m. nightly. Southbound frontage road between Rittiman Road and George Beach. Alternating lanes will close while crews repair the road.
  • Sunday-Friday, May 3-8. 9 p.m. until 5 a.m. nightly. Northbound main lanes between George Beach and Eisenhauer Road (east San Antonio). Alternating lanes will close for concrete work.
  • Sunday-Friday, May 3-8. 9 p.m. until 5 a.m. nightly. Southbound main lanes between Walzem and George Beach (east San Antonio). Alternating lanes will close while crews move barrier.
  • Sunday-Friday, May 3-8. 9 p.m. until 5 a.m. nightly. Southbound frontage road between Walzem and George Beach (northeast San Antonio). Alternating lanes will close for road work.
  • Monday-Friday, May 4-8. 9 a.m. until 3:30 p.m. daily. Southbound frontage road between Walzem and George Beach (northeast San Antonio). Alternating lanes will close for road work.
  • Monday-Friday, May 4-8. 9 a.m. until 3:30 p.m. daily. Southbound frontage road at Fratt Road (northeast San Antonio). The left lane will close for concrete work.
  • Monday-Friday, May 4-8. 9 a.m. until 3:30 p.m. daily. Northbound connector to westbound I-410 (northeast San Antonio). The right lane will close while crews work on the guardrail.
  • Monday-Friday, May 4-8. 9 a.m. until 3:30 p.m. daily. Northbound frontage road between Greatfare and Rittiman Road (east San Antonio). The left lane will close for road work.
  • Monday-Friday, May 4-8. 9 a.m. until 4 p.m. daily. North-to-south turnaround at Salado Creek (east San Antonio). The turnaround will close while crews drill support shafts.
  • Monday-Friday, May 4-8. 9 a.m. until 4 p.m. daily. Northbound frontage road between Splashtown and Binz-Engleman (east San Antonio). The left lane will close while crews do bridge work.
  • Monday-Friday, May 4-8. 9 p.m. until 5 a.m. daily. Main lanes, both directions, between AT&T Parkway and Binz-Engleman (east San Antonio). Alternating lanes will close for pothole repairs.
I-410
  • Monday-Friday, May 4-8. 9 a.m. until 4 p.m. daily. Frontage road, both directions, between Marbach and Military Drive (northwest San Antonio). Alternating lanes will close for concrete work.
  • Monday-Friday, May 4-8. 9 a.m. until 4 p.m. daily. Southbound frontage road between Medina Base and Old Pearsall roads (west San Antonio). Alternating lanes will close for concrete work.
  • Sunday-Friday, May 3-8. 9 p.m. until 5 a.m. nightly. Northbound connector to northbound I-35 (east San Antonio). The connector will close while crews place barrier. Traffic will exit Space Center Drive and proceed through the Rittiman Road intersection before entering the northbound main lanes of I-35.
  • Sunday-Friday, May 3-8. 9 p.m. until 5 a.m. nightly. Eastbound connector to northbound I-35 (northeast San Antonio). The right lane will close while crews repair crash cushions.
U.S. Hwy 281
  • Saturday, May 2. 7 a.m. until 5 p.m. Northbound main lanes at Nakoma Drive (north-central San Antonio). The left lane will close while crews pour concrete.
  • Monday-Saturday, May 4-9. 9 p.m. until 5 a.m. nightly. Northbound main lanes between Nakoma Drive and Bitters Road (north-central San Antonio). The two left lanes will close while crews do bridge work.
  • Monday-Friday, May 4-8. 9 a.m. until 3 p.m. daily. Main lanes, both directions, between the Guadalupe River and the Bexar/Comal county line (Comal County). The left lane will close while crews work on the cable median barrier.
  • Saturday, May 9. 7 a.m. until 7 p.m. Southbound main lanes at Nakoma Drive (north-central San Antonio). All lanes will close while crews hang bridge support beams. Traffic will exit Nakoma Drive, pass through the intersection and re-enter the highway.
  • Sunday, May 10. 7 a.m. until 7 p.m. Northbound main lanes at Nakoma Drive (north-central San Antonio). All lanes will close while crews hang bridge support beams. Traffic will exit Nakoma Drive, pass through the intersection and re-enter the highway.
Loop 1604
  • Monday, March 30-Saturday, May 9. 9 a.m. until 5 p.m. continuous. Turnarounds, both directions, at Braun Road (northwest San Antonio). The turnarounds will close for a month while crews build bridge support columns. Traffic will move through the intersection to turn around.
Other roads
  • Monday, March 30-Friday, May 15. 9 a.m. until 5 p.m. continuous. Walnut Avenue, both directions, between Floral and Wood avenues (New Braunfels). All lanes will close for a month while crews build a drain structure. Local traffic will have access to businesses on this block via Lockner and Howard roads.
  • Friday-Monday, May 1-4. 9 p.m. until 5 a.m. continuous. Eastbound Eisenhauer Road at I-35 (northeast San Antonio). All lanes will close for roadwork. Traffic will turn right onto the southbound I-35 frontage road and turn around at George Beach.
  • Friday-Monday, May 1-4. 9 p.m. until 5 a.m. continuous. Eastbound Rittiman Road at I-35 (northeast San Antonio). All lanes will close for roadwork. Traffic will turn right onto the southbound I-35 frontage road and turn around at George Beach.
  • Friday-Monday, May 1-4. 9 p.m. until 5 a.m. continuous. Westbound Eisenhauer Road at I-35 (northeast San Antonio). The left lane will close while crews do roadwork.
  • Friday-Monday, May 1-4. 9 p.m. until 5 a.m. continuous. Westbound Rittiman Road at I-35 (northeast San Antonio). The left lane will close while crews do roadwork.
  • Monday-Friday, May 4-8. 9 p.m. until 5 a.m. nightly. Eastbound Eisenhauer Road at I-35 (northeast San Antonio). All lanes will close for roadwork. Traffic will turn right onto the southbound I-35 frontage road and turn around at George Beach.
  • Monday-Friday, May 4-8. 9 p.m. until 5 a.m. nightly. Eastbound Rittiman Road at I-35 (northeast San Antonio). All lanes will close for roadwork. Traffic will turn right onto the southbound I-35 frontage road and turn around at George Beach.
  • Monday-Friday, May 4-8. 9 p.m. until 5 a.m. nightly. Westbound Eisenhauer Road at I-35 (northeast San Antonio). The left lane will close while crews do roadwork.
  • Monday-Friday, May 4-8. 9 p.m. until 5 a.m. nightly. Westbound Rittiman Road at I-35 (northeast San Antonio). The left lane will close while crews do roadwork.
  • Sunday-Saturday, May 3-9. 7 p.m. until 5 a.m. nightly. Medical Drive, both directions, between Ewing Halsell and Fairhaven Street (Medical Center). Alternating lanes will close while crews do road work.
  • Sunday-Saturday, May 3-9. 7 p.m. until 5 a.m. nightly. Fredericksburg Road, both directions, between Louis Pasteur and Data Point (Medical Center). Alternating lanes will close while crews do roadwork.
  • Wednesday-Saturday, May 6-9. 7 p.m. until 5 a.m. nightly. Medical Drive, both directions, Between Ewing Halsell and Fairhaven Street (Medical Center). Alternating lanes will close while crews work on street lights.
  • Friday-Monday, May 8-11. 7 p.m. until 5 a.m. continuous. Fredericksburg Road, both directions, between Louis Pasteur and Data Point (Medical Center). All lanes will close while crews reconstruct the road. Traffic will use Wurzbach Road, Ewing Hallsell and Louis Pasteur to reach its destination. Traffic on Medical Drive will use the new through lanes.
All closures are pending weather.