I-10 – New Braunfels
  • Thursday-Friday, December 15-16. 8 p.m. until 5 a.m. Southbound main lanes at York Creek. The left lane will close while crews move barrier.
  • Wednesday-Thursday, December 14-15. 8 p.m. until 5 a.m. Northbound main lanes at York Creek. The right lane will close while crews move barrier.
I-10 – Boerne
  • Sunday-Friday, December 4-9. 9 p.m. until 5 a.m. nightly. Westbound main lanes at Scenic Loop Road. The left lane will close while crews repair the retaining wall.
I-10 – East San Antonio
  • Friday, December 9-Monday, December 12. 9 p.m. until 5 a.m. continuous. Eastbound main lanes between Foster Road and FM 1516. All lanes will close while crews install drain structures. Traffic will exit Foster Road and re-enter at the next available ramp. Officers will control traffic at the Foster Road and FM 1516 intersections. This closure is a rescheduled closure from Dec. 2-5, rescheduled due to weather.
I-35 – Northeast San Antonio
  • Sunday-Friday, December 4-9. 9 p.m. until 5 a.m. nightly. Northbound exit to westbound I-410. Alternating lanes will close while crews do overhead bridge work. Traffic will exit Walzem and continue along the frontage road to reach I-410.
  • Sunday-Friday, December 4-9. 9 p.m. until 5 a.m. nightly. Main lanes, both directions, between Rittiman and Walzem roads. Alternating lanes will close while crews do road work.
  • Sunday-Friday, December 4-9. 9 p.m. until 5 a.m. nightly. Frontage roads, both directions, between Rittiman and Walzem. Alternating lanes will close while crews do road work.
  • Monday-Thursday, December 5-8. 9 p.m. until 5 a.m. nightly. Southbound connector to southbound I-410. The connector will close while crews move barrier. Traffic will exit George Beach, turn around and reach southbound I-410 from the northbound frontage road of I-35.
  • Monday-Friday, December 5-9. 9 a.m. until 3:30 p.m. daily. Frontage roads, both directions, between Rittiman and Walzem roads. Alternating lanes will close while crews do road work.
I-35 – East San Antonio
  • Monday-Friday, December 5-9. 9 a.m. until 4 p.m. daily. Frontage road, both directions, between Binz-Engleman and AT&T Center Parkway. The left lane will close while crews do finish work.
I-410 – Northeast San Antonio
  • Monday-Thursday, December 5-8. 9 p.m. until 5 a.m. nightly. Eastbound exit ramp southbound I-35. The ramp will close while crews move barrier. Traffic will exit Thousand Oaks and turn around to reach southbound I-35.
I-410 – East San Antonio
  • Current through Friday, December 2. Southbound main lanes over North WW White. The right lane will close while crews repair damaged bridge rail.
I-410 – Northwest San Antonio
  • Current until April 2017. Northbound exit to Culebra Road. The exit will close while crews widen the main lanes and frontage road. Traffic will exit Ingram Road, turn around and get to Culebra on the southbound frontage road.
Hwy 151 – Northwest San Antonio
  • Current through Friday, December 16. Westbound exit ramp to Ingram and Potranco roads. The ramp will remain closed while crews install bridge support structures for the direct connector ramps being constructed.
Loop 1604 – Northwest San Antonio
  • Sunday-Tuesday, December 4-6. 9 p.m. until 5 a.m. nightly. Southbound direct connector to eastbound Hwy 151. The connector will close while crews painters paint the concrete.
Other roads – Seguin
  • Current until Saturday, December 31. 9 a.m. until 4 p.m. daily. King Street, both directions, between Cedar Street and US 90. All lanes will close while crews install storm drains and rebuild the road. Traffic will use Hwy 123 as a detour.
Other roads – Northeast San Antonio
  • Current until Tuesday, December 13. 8 p.m. until 6 a.m. nightly. Northbound FM 1103 between FM 78 and Brite Road. Alternating lanes will close as needed while crews repair the pavement.
Other roads – Northwest San Antonio
  • Current until Monday, December 5. 9 p.m. until 5 a.m. nightly. Military Drive, both directions, at I-410. All lanes will close while crews do overhead bridge work. Traffic will turn right onto the frontage roads and turn around at the next intersection to reach its destination.